Lesny Development Co. v. Kendall

164 Cal. App. 3d 1010, 210 Cal. Rptr. 890, 1985 Cal. App. LEXIS 1668
CourtCalifornia Court of Appeal
DecidedFebruary 21, 1985
DocketCiv. 33110
StatusPublished
Cited by8 cases

This text of 164 Cal. App. 3d 1010 (Lesny Development Co. v. Kendall) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lesny Development Co. v. Kendall, 164 Cal. App. 3d 1010, 210 Cal. Rptr. 890, 1985 Cal. App. LEXIS 1668 (Cal. Ct. App. 1985).

Opinion

Opinion

KAUFMAN, J.

This is the second time this case has been before us. On the first appeal (4 Civ. 23262) in an unpublished opinion filed April 20, 1982, we reversed with directions a judgment of specific performance of a contract for the purchase and sale of real property, returning the matter to the trial court for a determination of the amount of compensation, if any, the defaulting contract purchasers might be entitled to on account of unjust enrichment of the contract sellers resulting from expenditures and efforts by the contract purchasers that enhanced the value of the property or otherwise benefited the contract sellers.

When jurisdiction was restored to the trial court the matter was submitted on the basis of the evidence already adduced and briefs from the parties. Thereafter the trial court rendered a statement of decision and, ultimately, a judgment awarding the contract purchasers (plaintiff) $78,750, $18,750 compensation at the rate of $75 per hour for 250 hours of effort the court found plaintiff expended in obtaining approval of the tentative tract map and $60,000 on account of plaintiff’s efforts, apparently part of the same 250 hours, resulting in the authorization of 8 additional subdivision lots over and above the number of lots originally anticipated. The $60,000 was arrived at on the basis of a figure of $7,500 per lot. Originally it was indicated plaintiff should recover costs of trial, but ultimately the parties were ordered to bear their own respective costs.

The contract sellers (defendants) again appeal, contending: the award is not supported by substantial evidence; no part of any compensation to plain *1015 tiff should have been based upon the increased value of the property but rather solely on the reasonable value to plaintiff of the services rendered; and defendants were the prevailing parties in the lawsuit and should have been awarded their trial costs.

Facts

Defendants were the owners of unimproved acreage in San Bernardino County. Although they had already engaged engineers and started on a program to subdivide the property, they were interested in selling some of the acreage for subdivision but had grown suspicious of real estate developers because of past experiences and did not want to tie their property up for any substantial time only to have the sale fall through.

After proposals back and forth, on January 16, 1976, plaintiff and defendants signed escrow instructions for the sale of approximately 18¿67 acres for $210,000. The escrow was made contingent inter alia upon “Buyer obtaining approval of its tentative tract map.”

No immediate cash deposit into escrow was required, but it was provided: “Within five days following San Bernardino County’s approval of the buyer’s tentative tract map, buyer will deposit the sum of $25,000.00 into escrow, which deposit is to be immediately released to seller without recourse. Said release is to be made regardless of the condition of title, regardless of the ultimate completion of this escrow, and without any liability whatsoever on Title Insurance & Trust Co. In the event buyer does not deposit the $25,000.00 within said five day period, seller reserves the right to cancel this escrow unilaterally. ”

The escrow instructions also provided that both buyer and seller should have the right to “examine engineering progress and question engineers and engineering data at reasonable intervals during escrow period to satisfy themselves that work is proceeding as fast as possible.” It was further provided: “If for any reason other than seller’s inability to convey title in conformance with preliminary title report as approved by buyer, this escrow does not close, Buyer agrees to reimburse seller for all costs of engineering incurred from December 1, 1975 to date of buyer’s default.”

The tentative tract map application was filed January 2, 1976, two weeks before the escrow instructions were actually signed, and plaintiff paid the application fee of $940. The map had been drawn up in December 1975 by the engineers defendants had engaged but it incorporated plaintiff’s design criteria. The tentative tract map was approved by the San Bernardino County Planning Commission on March 18, 1976.

*1016 On March 23, plaintiff delivered a check for $25,000 to a branch office of the escrow holder other than the branch in which the escrow was pending. However, the check was accompanied by a letter stating that the funds could be released to defendants only after the escrow holder had received a grant deed from defendants and defendants had signed corrected instructions resolving a discrepancy in the closing date. The escrow instructions did not require defendants to deposit a deed until June 1. Plaintiff also requested that defendants deposit in the escrow a recordable memorandum of sale. When defendant Thomas Kendall arrived at the escrow office to pick up the $25,000 on the morning of March 24, he was told the funds could not be released because of the conditions on release imposed by plaintiff. He immediately wrote out a cancellation notice and thereafter a written notice of cancellation of the escrow pursuant to its terms was delivered to the escrow holder.

Plaintiff thereupon filed this suit for specific performance. The trial court granted specific performance as to 46 of the 69 lots in the tract 1 apparently in the belief that it would be inequitable not to do so. The court made findings that between December 1, 1975, and March 24, 1976, plaintiff through its officers and agents expended a substantial amount of time and money and incurred engineering costs in obtaining conditional approval of the tentative tract map and that the value of the property had increased because of the time and effort expended by plaintiff. The court concluded that plaintiff had thereby acquired “a valuable equitable interest in the subject real property” and that “the failure to grant specific performance to Plaintiffs would constitute a forfeiture of Plaintiffs’ equitable interest in the subject property. ’ ’

The court also found, however, that during the pendency of the action, defendants, at their sole expense, completed the installation of all subdivision offsite improvements including streets, curbs, sewers, underground utilities, flood control measures and walls required by the County of San Bernardino and prepared and recorded the final subdivision map, all of which the court found reasonably necessary to protect the value of all the lots in the tract. Defendants expended $412,619.16 in so doing and the court conditioned its judgment of specific performance upon plaintiff’s paying to defendants two-thirds of that amount.

In reversing the judgment of specific performance this court rejected the trial court’s conclusion that a denial of specific performance would work a *1017 forfeiture or otherwise be inequitable. We stated in pertinent part: “Although there is a body of California law under which a court of equity is authorized to grant specific performance to prevent imposition of forfeiture on a party who has wilfully breached a contract, not every litigant is entitled to the relief.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Justin S.
59 Cal. Rptr. 3d 376 (California Court of Appeal, 2007)
Santa Clara County Department of Family & Children's Services v. Sheika L.
150 Cal. App. 4th 1426 (California Court of Appeal, 2007)
Carlino v. Kaplan
139 F. Supp. 2d 563 (S.D. New York, 2001)
Amelco Electric v. City of Thousand Oaks
98 Cal. Rptr. 2d 159 (California Court of Appeal, 2000)
Repeki v. Mac Homes (Saipan) Co.
2 N. Mar. I. 33 (Sup. Ct. of the Comm. of the N. Mariana Islands, 1991)
George Arakelian Farms, Inc. v. Agricultural Labor Relations Board
783 P.2d 749 (California Supreme Court, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
164 Cal. App. 3d 1010, 210 Cal. Rptr. 890, 1985 Cal. App. LEXIS 1668, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lesny-development-co-v-kendall-calctapp-1985.