Leonard Partnership v. Town of Chenango

779 F. Supp. 223, 1991 U.S. Dist. LEXIS 17505, 1991 WL 256366
CourtDistrict Court, N.D. New York
DecidedDecember 3, 1991
Docket88-CV-0065
StatusPublished
Cited by8 cases

This text of 779 F. Supp. 223 (Leonard Partnership v. Town of Chenango) is published on Counsel Stack Legal Research, covering District Court, N.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Leonard Partnership v. Town of Chenango, 779 F. Supp. 223, 1991 U.S. Dist. LEXIS 17505, 1991 WL 256366 (N.D.N.Y. 1991).

Opinion

MEMORANDUM-DECISION AND ORDER

McCURN, Chief Judge.

INTRODUCTION

In September, 1990, the court heard oral argument on defendant’s motion for summary judgment and for Rule 11 sanctions. Following oral argument, the court reserved decision and requested that the parties provide additional briefing on the due process claim. Thereafter, the parties engaged in extensive settlement negotiations. At the parties’ request, the court agreed to hold this motion in abeyance pending the outcome of the settlement negotiations. Despite serious efforts, the case could not be settled. The court was so advised in March, 1991, when the parties asked the court to finally decide this outstanding motion. Following constitutes the court’s decision in this regard.

BACKGROUND

This is a somewhat factually complicated case in that it involves a subdivision application to a town planning board, and a subsequent application for a building permit. Therefore, in an effort to place the legal issues raised by defendant’s motion into the proper factual context, the court will first provide a general discussion of *226 the relevant facts. Then, facts specific to a given cause of action will be discussed in greater detail in the section pertaining to that cause of action.

In July, 1986, plaintiff The Leonard Partnership (“the partnership”), 1 a family partnership, submitted a subdivision application to the Planning Board (“the Board”) for defendant and third-party plaintiff, the Town of Chenango (“the Town”). 2 According to the Town, certain questions arose during the application review process pertaining to the nature of the water and sewer services to be provided to the proposed subdivision. Those questions had to be answered by the partnership prior to the final stages of the subdivision application procedure.

In October, 1986, the Town Engineer recommended that public water be required. 3 One month later the Broome County Department of Planning and Economic Development recommended that the Town withhold its approval of the subdivision application until questions regarding water and sewer services were resolved. 4 Apparently in an attempt to answer some of those concerns, Dobbs Engineering Firm, P.C. (“Dobbs”), the engineering firm retained by the partnership in connection with this project, informed the Board that the partnership planned to use septic sewer systems in the proposed subdivision. 5 Dobbs further advised the Board that its original plan to use individual wells had been rejected by the Broome County Department of Health (“DOH”). 6 In addition, Dobbs reported to the Board that “[w]e will have public water,_” 7 Evidently that response did not satisfy either the Town Planning Board or the Broome County Planning Board; nor did it satisfy the DOH. Thus, primarily out of a concern over the water and sewer systems, the Town Planning Board did not take any further action regarding the subdivision application. The Town Planning Board was awaiting additional submissions from the partnership, as well as for comments from other government agencies. 8

In February, 1987, the DOH notified the Town Engineer that “[installation of public water will be a requirement of this Department” because of the proximity of the subdivision property to the Town landfill. 9 One of the reasons given for the public water requirement was DOH’s belief that a water septic system based upon 45 individual wells adjacent to the landfill might result in the migration of contaminants from the landfill to the subdivision property and into the groundwater thereunder. 10 The DOH believed that public water was “readily accessible” and could be easily extended to the partnership’s property because of the Town’s plan to extend public water to serve another development near the partnership’s property. 11 In addition to the public water requirement, a Senior Public Health Engineer for DOH also informed the Town Engineer of the necessity of developing a “comprehensive *227 sewage plan for the entire area including existing houses....” 12 In March, 1987, David Leonard, one of the partners in the partnership, applied for and was issued individual sewage specifications with a private well for the construction of a single family dwelling on the subject property. 13 The DOH engineer, claims, however, that the issuance of those individual sewage specifications by the DOH was erroneous because when David Leonard applied for those specifications, he failed to inform DOH that the lot was part of the subdivision property near the landfill. 14 As a result, the DOH engineer wrote the Town’s Ordinance Officer recommending that the building permit for this property be withheld. 15 He also indicated that DOH would not issue any further individual sewage specifications. 16 In DOH’s view, the application for the single family residence was simply a means to circumvent DOH’s public water requirement.

On April 27, 1987, David Leonard then applied for a building permit to construct a single family house with attached garage on the subject property. 17 On May 11, 1987, the Town’s Ordinance Officer denied that application stating that the application was “incomplete” in that it was not accompanied by a site plan; nor had Mr. Leonard obtained the DOH’s approval for water supply and septic systems. 18

Plaintiffs then commenced this lawsuit in January, 1988, alleging six causes of action. The first cause of action is brought pursuant to the Comprehensive Environmental Response, Compensation and Liability Act (“CERCLA”), 42 U.S.C. §§ 9601 et seq. The second, third and fourth causes of action are based upon the New York State law of public nuisance. The fifth cause of action seeks restitution under New York State law on a theory of unjust enrichment. Finally, in the sixth cause of action plaintiffs allege that the Town has taken their property without just compensation and violated their due process rights.

The Town advances a number of reasons as to why each of those causes of action must fail as a matter of law. The court will first consider the federal claims because if the Town is entitled to summary judgment dismissing those claims, the court will in all likelihood not be inclined to entertain the remaining pendent state claims.

DISCUSSION

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tomlins v. Village of Wappinger Falls Zoning Board of Appeals
812 F. Supp. 2d 357 (S.D. New York, 2011)
Frooks v. Town of Cortlandt
997 F. Supp. 438 (S.D. New York, 1998)
Pierzynowski v. Police Dept. City of Detroit
941 F. Supp. 633 (E.D. Michigan, 1996)
City of New York v. Chemical Waste Disposal Corp.
836 F. Supp. 968 (E.D. New York, 1993)
Allied Princess Bay Co. 2 v. Atochem North America, Inc.
855 F. Supp. 595 (E.D. New York, 1993)
McDonald's Corp. v. Wilson
814 F. Supp. 935 (D. Oregon, 1993)
Alloy Briquetting Corp. v. Niagara Vest, Inc.
802 F. Supp. 943 (W.D. New York, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
779 F. Supp. 223, 1991 U.S. Dist. LEXIS 17505, 1991 WL 256366, Counsel Stack Legal Research, https://law.counselstack.com/opinion/leonard-partnership-v-town-of-chenango-nynd-1991.