Legoland Discovery Centre (Dallas), LLC v. Superior Builders, LLC

531 S.W.3d 218
Court of Appeals of Texas·Decided April 27, 2017·No. NO. 02-16-00425-CV·Published·Cited by 6 cases

Opinion

OPINION

LEE GABRIEL, JUSTICE

Appellant Legoland Discovery Centre (Dallas), LLC appeals from the trial court’s interlocutory order denying its motion to compel arbitration. Because appel-lee Superior Builders, LLC did riot meet its heavy burden to show that Legoland waived its right to arbitrate by substantially invoking the judicial process as to Superior’s claims raised against Legoland, we reverse the trial court’s order and remand for entry of an order compelling arbitration.

I. BACKGROUND

. A.. Factual

Legoland hired Superior to be the geri-eral contractor for a water-feature addition to Legoland’s entertainment center in Grapevine, Texas. The contract, drafted by Superior, included the following arbitration clause:

Any controversy or claim arising out of or relating to this contract, or' 'the breach thereof, shall be settled by arbitration administered by the Américan Arbitration Association' under its Construction Industry Arbitration Rules, and judgment on the award rendered by the arbitrator(s) may be entered in any court having jurisdiction thereof.

The contract also contained a- choice-of-law clause providing that Texas law would govern the contract and a venue clause setting venue regarding “any action other than a lien foreclosure may at [Superior’s] option lie in .,. Tarrant County.”.

Legoland believed that Superior did not complete the work contracted for and damaged adjacent property, Legoland also began to. receive nonpayment notices, from several of Superior’s • subcontractors and suppliers: Sunbelt Rentals; Roofing & Siding Specialists, Inc.; National Wholesale Supply, Iñc.; Love Service .Company; H & H Pool Decks, Inc.; Chas." F. Williams Co.; and Aeroflow. See Tex. *220 Prop. Code Ann. §§ 53.056-.057 (West 2014). Several of these subcontractors filed lien affidavits, seeking payment. See id. § 53.103 (West 2014). Legoland stopped paying Superior, leaving an alleged balance due to Superior of $89,642.10. See id. § 53.102 (West 2014).

Legoland notified Superior that it would terminate the contract under its terms unless Superior cured the defaults. Superior failed to cure; therefore, Legoland notified Superior that Legoland had terminated the contract and notified the affected subcontractors of the termination. See id. § 53.107 (West 2014).

B. Procedural

Superior filed suit against Legoland on December 11, 2014, raising claims for breach of contract, violation of the Prompt Payment Act, quantum meruit, and promissory estoppel. Superior also requested a declaration that it was entitled to a lien against Legoland’s entertainment center and for a judgment “foreclosing on [its] Lien ... together with an order of sale.” Legoland answered and filed counterclaims for breach of contract, negligence, and breach of express warranty based on Superior’s alleged faulty work and failure to pay its subcontractors. See Tex. R. Civ. P. 97(a). Legoland included in its counterclaims a request for disclosure. See Tex. R. Civ. P. 194.1,194.2.

Superior amended its petition on April 1, 2015, adding as defendants most of the subcontractors identified in Legoland’s counterclaims but raising the same claims against Legoland that it raised in its original petition. Superior also included a request for disclosure in its amended petition, which Legoland responded to. On May 13, 2015, Legoland and Superior both signed a letter agreement, reflecting that Superior’s deadline to respond to Lego-land’s requests for disclosure would be extended to May 20, 2015. See Tex. R. Civ. P. 11,194.3.

Two of the defendant subcontractors— Sunbelt and Roofing & Siding Specialists—filed counterclaims against Superior and cross-claims against Legoland; one subcontractor, which was not named in Superior’s suit or in Legoland’s counterclaims, intervened in Superior’s suit. See Tex. R. Civ. P. 60, 97(e). On January 29, 2016, Superior filed an agreed motion for entry of a scheduling order. 1 See Tex. R. Civ. P. 166, 190.4, 192. On March 3, 2016, the trial court entered the requested scheduling order, setting the trial for the week of November 14, 2016. On April 15, 2016, Superior again amended its petition to add Legoland’s surety to its claim seeking a lien declaration. See Tex. Prop. Code Ann. § 53.171 (West 2014).

Legoland conducted discovery with several of the defendant subcontractors. By October 2016, Legoland had resolved the subcontractors’ claims. 2 On October 6, 2016, Legoland filed a motion to compel Superior’s claims against it to arbitration based on the terms of their contract. Superior responded that Legoland had waived its right to arbitrate by substantially invoking the judicial process to Superior’s detriment. The trial court held a hearing on October 28, 2016, and concluded that Legoland had affirmatively waived its right to compel arbitration by agreeing to the trial court’s scheduling order. On November 3, 2016, the trial court entered an *221 order denying Legoland’s motion to compel, specifically stating that Legoland “has waived its right to arbitration by substantially invoking the judicial process to [Superior’s] detriment.”

Legoland filed a request for findings of fact and conclusions of law 3 and a notice of appeal from the denial of its motion to compel arbitration. Legoland argues that the trial court erred because it had not substantially invoked the judicial process and because Superior failed to carry its burden to show that it was prejudiced by Legoland’s actions. See 9 U.S.C.A. § 16(a)(1)(C) (West 2009) (allowing interlocutory appeal from order denying arbitration where matter is subject to the Federal Arbitration Act); Tex. Civ. Prac. & Rem. Code Ann. § 51.016 (West 2015), § 171.098(a)(1) (West 2011) (allowing immediate appeal from interlocutory denial order under the Texas General Arbitration Act). 4

II. WAIVER OF ARBITRATION

A. Standard of Review

In general, we review the denial of a motion to compel arbitration for an abuse of discretion. See Brand FX, LLC v. Rhine, 458 S.W.3d 195, 203 (Tex. App.Fort Worth 2015, no pet.). In this appeal, however, no party disputes that the parties entered into a binding arbitration agreement or that Superior’s claims against Le-goland fell within the scope of that agreement. The sole point of contention is whether the trial court correctly concluded that Legoland had waived its right to enforce the valid and applicable arbitration agreement by availing itself of the judicial process to Superior’s detriment.

Free access — add to your briefcase to read the full text and ask questions with AI

Legoland Discovery Centre (Dallas), LLC v. Superior Builders, LLC, 531 S.W.3d 218 (Tex. Ct. App. 2017).

531 S.W.3d 218 (Legoland Discovery Centre (Dallas), LLC v. Superior Builders, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related