Legacy Crossing, L.L.C. v. Travis Wolff & Co.

229 F. App'x 672
CourtCourt of Appeals for the Tenth Circuit
DecidedApril 9, 2007
Docket06-6210
StatusUnpublished
Cited by5 cases

This text of 229 F. App'x 672 (Legacy Crossing, L.L.C. v. Travis Wolff & Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Legacy Crossing, L.L.C. v. Travis Wolff & Co., 229 F. App'x 672 (10th Cir. 2007).

Opinion

*674 ORDER AND JUDGMENT **

PAUL KELLY, JR., Circuit Judge.

In this diversity action, Plaintiff-Appellant Legacy Crossing, LLC (“Legacy Crossing”) appeals from the district court’s grant of summary judgment in favor of Defendant-Appellee Travis Wolff & Company, LLP (“TWC”). The district court held that Legacy Crossing’s state law claims against TWC for fraud, negligence/professional malpractice, and violation of the Oklahoma Consumer Protection Act were barred as untimely under the applicable Oklahoma statute of limitations. The district court also declined Legacy Crossing’s invitation to toll the statute of limitations. Our jurisdiction arises under 28 U.S.C. § 1291, and we affirm.

Background

Legacy Crossing is the owner and operator of an apartment complex in Oklahoma City. As an LLC, it is organized under the laws of Oklahoma with its principal place of business in Oklahoma. TWC is an accounting and financial advisory firm organized under the laws of Texas with a principal place of business in Dallas, Texas.

Construction of Legacy Crossing’s apartment complex began in February 2000, and was completed in August 2001. Legacy Crossing employed Barry, Bette & Led Duke, Inc. (“BB & L”) as the contractor on the project. In conjunction with construction, Legacy Crossing obtained a commitment from the United States Department of Housing and Urban Development (“HUD”) to guarantee a construction loan for the project. One requirement of that commitment was that Legacy Crossing and BB & L enter into a form contract that required BB & L to furnish a “Contractor’s Certificate of Actual Cost” before BB & L could receive final payment. BB & L was further required to furnish a report from an independent public accountant that BB & L’s certification of the actual costs was true and accurate. On February 9, 2000, Legacy Crossing and BB & L entered into a construction contract.

BB & L thereafter hired TWC to conduct an independent audit, and on February 18, 2002, TWC submitted a final revised report to HUD certifying that the Contractor’s Actual Cost of Construction submitted by BB & L was correct. Legacy Crossing also received a copy of the report at that time. Legacy Crossing was nonetheless unhappy with, and questioned, the amount charged for “General Requirements” 1 expenses. At $1.952 million, the amount charged for general requirements was nearly $900,000 above prior estimates. Consequently, Legacy Crossing disputed the general requirement charges and requested supporting documentation from BB & L regarding the amount of overhead.

On March 6, 2002, BB & L attempted to respond to Legacy Crossing’s concerns by sending it a letter enclosing a copy of an auditor’s worksheet showing items of expense by trade, a letter to TWC explaining BB & L’s reasons for several variances from the original HUD budget, and a copy of a detailed computer report showing expenses by line item. Legacy Crossing deemed BB & L’s letter unresponsive. Legacy Crossing expressed its displeasure *675 with the amount of the general requirements expenses to HUD representatives, who found nothing improper about TWC’s report. Despite Legacy Crossing’s dissatisfaction, on March 14, 2002, it went forward with the HUD closing because it believed that further delays would harm the construction project.

Instead of holding up the construction project, Legacy Crossing refused to pay an identity of interest fee 2 to BB & L. In response, BB & L filed suit against Legacy Crossing in federal court alleging that Legacy Crossing had breached several agreements it had entered into with BB & L. Legacy Crossing then cross-claimed for breach of contract and “[accounting, [restitution, and [djamages.” In its cross-complaint, filed May 16, 2002, Legacy Crossing alleged:

34. Legacy Crossing believes that some portion of the “General Requirement” charges that were paid to Plaintiff included charges for general overhead expenses that were not directly connected to the construction of the project. Legacy Crossing previously requested that Plaintiff provide supporting documentation for such charges to resolve the issue, but Plaintiff refused the request.
35. Legacy Crossing is entitled to an equitable accounting to determine whether such costs were proper and/or directly connected to Plaintiffs construction of the apartment complex.

Aplt. App. at 183. In apprising the owners of Legacy Crossing about the litigation, Mike Henderson, Managing Partner of Legacy Crossing, wrote in May 2002:

[BB & L] ha[s] been paid approximately one-half of their profit as called for in the Identity of Interest Agreement. We are now in litigation over the balance of this profit. We have refused to pay this additional profit as called for in the Identity of Interest Agreement until we get a proper accounting of why the general conditions cost ended up being so high. It is my suspicion that their cost certifier [ (TWC) ] included the general overhead, as allowed by HUD regulations, in the general conditions. Then when the report was initially sent to HUD and HUD noted that there was no general overhead requested in the cost certification BB & L then redid the cost certification adding general overhead back in and redoing the cost certification which HUD allowed. When I questioned HUD on this re-certification they said they did not want to make waves because the contractor had done a good job of construction. While I agree that they did a good job of construction they should not ask us to pay costs twice. As part of our defense on [sic] this litigation we are counter claiming that some of the buildings were completed late and that we can invoke a penalty clause in the Identity of Interest Agreement. We had not intended to invoke this clause until these double-charging suspicions arose.

Id. at 146.

On November 27, 2002, Legacy Crossing responded to interrogatories from BB & L. In response to BB & L’s request for the identities of all persons having discov *676 erable information, Legacy Crossing provided the name of Ed Wolff, of TWC, as someone who would have information about “[fjacts relating to certified costs.” Id. at 221-22. Moreover, interrogatory 13 was asked and answered, in relevant part, as follows:

INTERROGATORY NO. 13: Describe in detail why the audit relating to the Construction Project performed by [TWC] is not a sufficient accounting so that you are demanding in your counterclaim an equitable accounting from [BB & L].
ANSWER: ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
229 F. App'x 672, Counsel Stack Legal Research, https://law.counselstack.com/opinion/legacy-crossing-llc-v-travis-wolff-co-ca10-2007.