LeBlanc v. State ex rel. Department of Transportation & Development

615 So. 2d 365, 1993 La. App. LEXIS 940, 1993 WL 57832
CourtLouisiana Court of Appeal
DecidedFebruary 25, 1993
DocketNo. 92-CA-699
StatusPublished
Cited by3 cases

This text of 615 So. 2d 365 (LeBlanc v. State ex rel. Department of Transportation & Development) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
LeBlanc v. State ex rel. Department of Transportation & Development, 615 So. 2d 365, 1993 La. App. LEXIS 940, 1993 WL 57832 (La. Ct. App. 1993).

Opinion

BOWES, Judge.

The State of Louisiana, through the Department of Transportation and Development (hereinafter “DOTD”), appeals a judgment of the district court in favor of plaintiffs, Carroll LeBlanc Constance, wife of/and Gerald Constance, and Cleary Bicycle, Moped and Go-Cart Center, Inc. (hereinafter called “Cleary”) in the amount of $108,153.00, plus $20,000.00 in attorney fees, plus expert witness fees. We affirm the judgment (in toto) as explained in a particularly well written and soundly reasoned opinion of the district court, as follows.

PROCEDURAL FACTS

Mr. and Mrs. Constance and Cleary filed suit in the Twenty-Fourth Judicial District Court for damages and losses sustained due to the redesign and construction of the exit ramp at Clearview northbound. Made defendants were DOTD, Pepper & Associates (engineers who designed construction signing) and contractors T.L. James and Louisiana Paving, Inc. All claims except those against DOTD were dismissed or settled prior to trial. In the suit, plaintiffs claimed that they lost business income and that their building was devalued because of a construction project and redesigning of the traffic routes at the Clearview Parkway North and Interstate 10 Interchange. Following trial against DOTD, the trial judge determined that plaintiffs proved by a preponderance of the evidence that they suffered both a devaluation of property and a loss of sales. The court determined that the loss of profits due to construction and redesign was $53,153.00, using a “reasonable time period of loss” of two years. It was further determined that the property had a loss of $55,000.00 in value, for a total of $108,153.00. The Court awarded these amounts as damages to plaintiffs, as well as attorney fees of $20,000.00 based on the amount of legal work involved, the expertise of plaintiffs’ attorney, his success, and “other criteria set forth by law.” Expert witness fees in the amount of $1,400.00 were also assessed against defendants.

DOTD appeals, assigning as error the following:

(1) The trial court committed error when it failed to apply the principle of law that the plaintiff owner is obligated to tolerate certain inconveniences resulting from the lawful use of another neighbor’s property.

(2) The trial court was manifestly erroneous in awarding $53,153.00 for loss of profits based on uncorroborated self-serving evidence.

(3) The trial court erred in awarding $55,000.00 for devaluation of property when, by plaintiff’s own testimony, the property continued to be equally productive.

(4) The trial court erred in granting attorneys fees not provided by statute or contract.

[368]*368Appellee answered the appeal averring that the court erred in limiting his recovery to the period of time from August, 1981 through July, 1983.

EVIDENCE AND TESTIMONY

Mr. and Mrs. Constance purchased the property at 3001 Clearview Parkway, Me-tairie, Louisiana in 1978 and constructed a commercial building thereon for a total of $150,000.00. Cleary began operations in that location later that same year. In August of 1981, the State, through DOTD, was issued a work order to realign the westbound exit ramp of Interstate 10 to Clearview Parkway northbound, including a direct connection from the ramp to Frontage Road. “Cleary” is located on the I — 10 Service Road at its intersection with Sanford Street “tucked” immediately behind Clearview Shopping Center. The property and business are completely surrounded by a fence from the shopping center.

DOTD, in requesting permits from the Federal Highway Administration, classified the project in a letter dated March 19, 1979 as a “non major” action which would not substantially alter social, economic, or environmental conditions or essentially change traffic patterns in the area. “The project should have no impact on land use in the area either.” Therefore, the DOTD concluded that an opportunity for public hearing would not be afforded. There would not, the State averred, be displacements of residences or businesses. At that point, DOTD concluded that “only a narrow strip of additional right-of-way will be required adjacent to the northbound roadway of Clearview Parkway, between Veterans Boulevard and the Clearview interchange.”

By the time the project actually began in 1981, Cleary had been in operation for several years. There is apparently also a radio broadcasting station and a medical testing laboratory in the area, but no other retail businesses dependent upon customer access like the plaintiffs are. Constance testified that he knew nothing of the project until he noticed the surveyors in front of his store and upon questioning them, learned of the situation. Construction actually began on September 1, 1981.

Prior to construction, there were four principal methods of access to “Cleary”:

(1) From I — 10 from the East (Metairie and New Orleans) traffic could exit at Clearview north and turn right onto Frontage Road, then directly into the “Cleary” parking lot;

(2) From the South, traffic going north on Clearview would turn right onto Frontage Road;

(3) Westerly traffic from Kenner was able to exit northbound on the Clearview exit and turn right onto Frontage; and

(4) Traffic from the North from Pontchartrain Lake was able to proceed southbound on Clearview and turn left across Clearview just south of Veterans Boulevard onto Frontage Road.

Two other, but more circuitous, routes through the Clearview Shopping Center to an exit on Woodland, then on to Sanford; and Frontage Road from Causeway were also available.

There was testimony from Russell Doyle, formerly a project engineer of DOTD, that at the beginning of construction, Frontage Road was originally changed to one-way traffic going in an easterly direction, but that motorists ignored the one-way signs and therefore, the road was finally blocked on Sanford at some distance beyond the bicycle shop. He further testified that according to his log books, “local traffic” was permitted to go through the “detours.” However, Mr. Doyle agreed that his log books had no specific entries regarding the actual placing of signs by DOTD on the project in question.1 Aswah Lam, a traffic engineer at DOTD, testified that he reviewed the sign plan prepared by a consultant hired by DOTD (Pepper and Associates) for approval. According to his testimony, economic impact is considered in such traffic engineering and local traffic is [369]*369to be allowed during such projects. However, Mr. Lam had nothing to do with the actual placing of the signs either and did not testify regarding the sign plan actually employed at these intersections.

Lloyd Gautreaux was the district traffic operations engineer for DOTD in 1981 and 1982. He testified, as did Mr. Russell, that motorists ignored the one-way signs on Frontage Road, and as a result, a barricade was placed in the roadway just beyond Kingman Street (westbound); barricades were also placed in the southbound roadway off Woodlawn and in the westbound lane of Sanford. This was supposed to redirect traffic into a one-way system which would eliminate the possibility of head-on collisions on Frontage Road. While the barricades were supposed to have been placed in one lane only, the department deleted any “Local Traffic Only” signs. Referring to Clearview Shopping Center motorists, Gautreaux stated:

...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

STATE, DOTD v. Morein
628 So. 2d 1191 (Louisiana Court of Appeal, 1993)
Constance v. State, Through DOTD
626 So. 2d 1151 (Supreme Court of Louisiana, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
615 So. 2d 365, 1993 La. App. LEXIS 940, 1993 WL 57832, Counsel Stack Legal Research, https://law.counselstack.com/opinion/leblanc-v-state-ex-rel-department-of-transportation-development-lactapp-1993.