Leavel v. Porter

52 Mo. App. 632, 1893 Mo. App. LEXIS 429
CourtMissouri Court of Appeals
DecidedJanuary 30, 1893
StatusPublished
Cited by7 cases

This text of 52 Mo. App. 632 (Leavel v. Porter) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Leavel v. Porter, 52 Mo. App. 632, 1893 Mo. App. LEXIS 429 (Mo. Ct. App. 1893).

Opinion

G-ill, J.

This case was tried before Ben. T. Hardin, Esq., as referee, and I know of no better statement of the controversy than to give the substance of his findings, of both law and fact, as reported by him to the circuit court.

“On the fifteenth day of June, 1889, plaintiff and Alonzo P. Johnson entered into a written contract, by the terms and conditions of which Johnson was to well and sufficiently, in a careful, skilful and workmanlike manner, build and complete one two-story and attic frame building, according to the plans and specifications made and furnished by W. W. Polk, architect, and under his supervision, on the southeast corner of Thirteenth street and Bales avenue, Kansas City, Missouri, to furnish, all materials and labor therefor, and to finish the same on or before the fifteenth day of September, 1889, to the satisfaction and under the direction of said W. "W. Polk, to be testified by a writing or certificate under his hand, etc.

“In consideration thereof, plaintiff Leavel was to pay $2,158, payable in the 'following manner: ‘Seventy-five per cent, of the value of the labor, work and materials actually put into the building, to be paid to the party of the first part [Johnson] by the party of [634]*634the second part [Leavel] on Saturday of each week, as the work progresses, to be paid only on the certificate of Mr. Polk, architect, certifying to the value of the work and materials so put into said building.

“ ‘Provided, however, that the remaining twenty-five per cent, of the contract price be reserved by the party of the second part until the building is completed and accepted by the owner.

“ ‘Provided, further, that there shall be satisfactory evidence that there shall then be no claims then existing against said building for labor or materials done on* or used in, the construction of the same.

“ ‘Provided that in all cases the said party of the first part [Johnson] before he shall be entitled to demand or receive payment for the work, or any part, thereof done under this contract, shall produce unto the said party of the second part [Leavel] a writing or certificate under the hand of said W. W. Polk, the architect above named, to the purport and effect that the materials furnished, and the work done by the said party of the first part, are in accordance with the plans, drawings and specifications above referred to,, and of the respective provisions hereof.

“ ‘Provided, further, before final acceptance of the building when completed, a certificate shall be obtained by the contractor, from the clerk of the office where liens are secured, etc., that no liens are recorded against said building; neither shall there be any legal or lawful claims against the contractor, in any manner, from any source whatever, for work or materials furnished on said works.’

“The contract also contains the following: ‘And it is hereby further agreed that the plans, specifications and drawings above referred to are hereby made and shall be considered and construed to be a part of this contract.

[635]*635“By the terms of the contract, the architect may, at his discretion, reject any work or materials and has power to have any work altered at the expense of the contractor.’

“The plaintiff Leavel had power to make all alterations by adding to, or omitting, or deviating from the plans, drawings and specifications which he shall deem proper, and the architect shall advise, ‘without in any manner impairing the validity and virtue hereof.’ In such case the architect should appraise such alteration, and add to or deduct from the contract price, as the case might be.

“If Johnson should, during the progress of the work, become bankrupt, refuse or neglect to supply a deficiency of materials or workmen, Leavel • should have power to supply the same after one day’s notice in writing should be given to Johnson; and in such case the costs of such work and materials should be retained by Leavel as liquidated damages, and Leavel should not be accountable to Johnson in any way ‘for the manner in which he may have had the work completed.’

“On the reverse side of said contract, and on the same date thereof, is a bond entered into by A. P. Johnson, as principal, and John Porter and D. E. Sullivan as sureties, conditioned that if the said Alonzo P. Johnson ‘shall duly perform said contract’ the bond to be void, etc. The contract proper simply calls for the building of a two-story and attic frame building according to the plans and specifications.- But the plans, drawings and specifications, which are expressly made a part of the contract, call for privy, walk and cistern.

“It is also provided in the contract that, ‘for each day the building remained unfinished after the time [636]*636that it was agreed that it should be completed, the liquidated damages shall be $10 per day.’

“The plans, drawings and specifications were to be construed and interpreted by Polk, the architect, and he was to have absolute control, and the iron-clad contract makes his will the law throughout. If any differences should arise between the parties to the contract, the decision of the architect above named shall be final and binding on all the parties hereto.

“Polk prepared the plans, specifications and drawings; the contract and bond were executed and accepted. There were some changes made during the progress of the work, in the wainscoting in the bath room, moving closet, changing a partition, one door, and some other minor changes, no notice of which was given to Sullivan and Porter. But no changes were ordered by Leavel. They were made by Polk and Johnson. No change was ever made in the contract, bond, plans, drawings or specifications. Leavel never consented to any delay in the completion of the building. A closet was moved by a foreman of Johnson on his own responsibility, Leavel acquiescing in the move.

“I also find that during the progress of the work Polk, in accordance with the terms of the contract, made written certificates of the value of the work and materials, upon which, on the following dates, were paid to Johnson by Leavel the following amounts * * * in the aggregate the total of $1,499.50, paid on the contract price, as called for by Johnson, as shown by the certificates issued by Polk. The amount of each payment was estimated by taking total estimate of work, deducting twenty-five per cent., and then deduct the total sum of all prior payments. This was done in accordance with the terms of the contract, and I find from the evidence that, at the time these payments were made, no claims were existing against [637]*637Johnson on account of material furnished for said work. Polk looked after the construction of the work and ascertained that the labor and material had entered into the building before issuing the certificates above mentioned.

“I further find from the evidence that Johnson never completed the building, but abandoned the same a short time before finishing it, and the three defendants were notified by Polk, in writing, that it was not finished according to the contract, and that Polk, the architect for Leavel, after more than one day’s notice in writing to defendants, employed men and purchased materials to complete the work, on account of which Leavel was compelled to pay out the following sums, as shown by items mentioned in plaintiff’s petition: * * * making a total of $1,106.66 which, added to the $1,499.50, paid out to Johnson on Polk’s certificates, makes $2,606.16.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Massachusetts Bonding & Insurance v. Realty Trust Co.
73 S.E. 1053 (Supreme Court of Georgia, 1912)
Nowell v. Mode
111 S.W. 641 (Missouri Court of Appeals, 1908)
Reissaus v. Whites
106 S.W. 603 (Missouri Court of Appeals, 1907)
John A. Tolman Co. v. Hunter
88 S.W. 636 (Missouri Court of Appeals, 1905)
Fullerton Lumber Co. v. Gates
89 Mo. App. 201 (Missouri Court of Appeals, 1901)
Fullerton Lumber Co. v. Calhoun
89 Mo. App. 209 (Missouri Court of Appeals, 1901)
United States v. Freel
92 F. 299 (U.S. Circuit Court for the District of Eastern New York, 1899)

Cite This Page — Counsel Stack

Bluebook (online)
52 Mo. App. 632, 1893 Mo. App. LEXIS 429, Counsel Stack Legal Research, https://law.counselstack.com/opinion/leavel-v-porter-moctapp-1893.