Nowell v. Mode

111 S.W. 641, 132 Mo. App. 232, 1908 Mo. App. LEXIS 527
CourtMissouri Court of Appeals
DecidedMay 25, 1908
StatusPublished
Cited by13 cases

This text of 111 S.W. 641 (Nowell v. Mode) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nowell v. Mode, 111 S.W. 641, 132 Mo. App. 232, 1908 Mo. App. LEXIS 527 (Mo. Ct. App. 1908).

Opinion

JOHNSON, J.

Defendant Mode contracted to erect a building on premises owned by plaintiff in. the city of Columbia for the price of $12,850, and executed and delivered to plaintiff a bond in the penal sum of $5,000 for the performauce of the contract. This action was brought on the bond by the obligee against Mode, the principal obligor, and the Title Guaranty and Trust Company of Scranton, Pennsylvania, surety, to recover damages alleged to have been sustained by plaintiff in consequence of certain breaches of the obligation. Verdict and judgment were for plaintiff in the sum of $1,000, and defendants appealed.

First, defendants insist that the petition fails to state a cause of action for the reason that a breach of the bond is not alleged. They argue that the undertaking was one of indemnity and that to constitute a cause of action thereon, it was incumbent on plaintiff to plead and prove that Mode (the contractor) “broke the building contract in some one or more particulars; that Nowell (the owner) suffered pecuniary loss therefrom and that Mode failed to indemnify him for such loss.” This objection was not made the subject of a demurrer to the petition but defendants answered to the merits and first raised the point during the progress of the trial. In such situation, the question for us to decide is whether the petition omits to state one or more of the essential elements of the cause of action intended to be asserted. However loose or defective the statement of some of the elemental facts may be, objection to such defects must be raised by demurrer to the petition [237]*237and if not thus raised, should he held to be cured by verdict. The rule is well expressed by the St: Louis Court of Appeals in Thomason v. Insurance Co., 114 Mo. App. 109, where it is said: “There is a marked distinction in our practice between a petition which defectively states a cause of action and one which states no cause of action at all. A defective cause of action is one thing and a defectively stated cause of action is another. A petition stating a cause of action defectively is good after judgment.” [Citing Malone v. Insurance Co., 71 Mo. App. 1; Edmondson v. Phillips, 78 Mo. 59; State ex rel. v. Rush, 77 Mo. 586; Bank v. Leyser, 116 Mo. 51.]

After referring to the contract between Nowell and Mode for the construction of the building, the bond thus states the obligation assumed by the obligors: “Now, therefore, the condition of the foregoing obligation is such that if the said principal shall well and truly indemnify and save harmless the said obligee from any pecuniary loss resulting from the breach of any of the terms, covenants and conditions of the said contract on the part of the said principal to be performed, then this obligation shall be void; otherwise to remain in full force and effect.” The building contract required defendant Mode to construct the building in accordance with plans and specifications prepared, by the superintending architect and to complete the work on or before October 1,1904. It provided “that the said party of the second part (the contractor) shall forfeit the sum of $20 liquidated damages for every day expiring after that day before the completion and delivery of said building as aforesaid to the said party of the first part, and this condition not to be made or rendered void by any alteration or additional work being performed, but in such case the time shall be extended as shall be deemed proper by the architect and agreed to by the •said party of the second part, at the time of such exten[238]*238sion.” • Terms of payment of the contract price then were stated, followed by this stipulation: “Provided that the wages of the artisans and laborers, and all those employed by, or furnishing materials to the said party of the second part, shall have been paid and satisfied, so that they shall have no lien upon the building or works, and in case the said party of the second part shall fail to pay and satisfy all and every claim against said building as aforesaid, the said party of the first part may, if he deems proper so to do, retain from the moneys due and coming to the said party of the second part, enough to pay and satisfy such claims and demands, it being, however, understood that nothing herein contained shall in any way be construed as impairing the right of the said party of the first part to hold the said party of the second part, or securities, liable on his bond for any breach of the conditions of the same.”

It is alleged in the petition that the contractor did not complete the building by October 1, 1904, or at any time thereafter, but left it unfinished and that on December 18, 1904, plaintiff took possession of the premises and was compelled to finish the building at his own expense. Then follows a detailed statement of various mechanics’ liens filed against the property for labor and materials furnished for the building under contracts with defendant, and the allegations that plaintiff was compelled to pay these judgments, together with court costs amounting in all to $3,069.04, and “that under the provisions of said builders’ coiitract he retained the final payment of $2,350, which was payable to the said defendant, Benjamin F. Mode; and applied said amount on the payment of the above-mentioned judgments; . . . that none of the breaches of said contract by the defendant above mentioned were occasioned by an act of God, or public enemies or mobs, or riots, or civil commotion or by employees leaving the work being done on said contract on account of socalled [239]*239strikes or labor difficulties. . . . that by reason of the delay in completing said building by the first day of October, 1904, as required by the provisions of the said contract, he is entitled to the sum of $1,560, as liquidated damages, and that by reason of the fact that the defendant, Benjamin F. Mode, failed to construct and finish said building in the manner and according to the plans and specifications provided therefor, the plaintiff is damaged in the sum of $500; that by reason of the pecuniary losses resulting to the plaintiff from his being compelled' to pay the aforesaid judgments and other claims against said building and premises, court costs and attorney’s fees incurred in connection therewith, and interest on sums expended, the plaintiff is damaged in the sum of $1,000.”

The answer of the defendant Mode contained-a series of denials, a plea that the delay was caused by alterations and changes and by delay on the plaintiff’s part in removing old buildings from the lot and a counterclaim for extra work. The answer of the surety company was a general denial, a plea that the delay was caused by plaintiff’s improper conduct and a further plea that the liquidated damages sought to be recovered were unreasonable and excessive and amounted to a penalty.

Though we find no specific allegation that defendant Mode failed to reimburse plaintiff for his damages and outlay on account of mechanics’ liens, we think that fact fairly is inferable from those pleaded. The obligation of defendants was more than a mere contract of indemnity. They undertook affirmatively to deliver to plaintiff a completed building by the time specified and to hold him harmless from pecuniary loss on account of unpaid demands for labor and materials for which, liens might be enforced against the property. The allegation of facts which show a breach of these covenants in effect, we think, was the allegation of a [240]*240breach of the bond under the. rules of construction applicable to a petition, the sufficiency of which is not attacked by demurrer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Commercial Nat. Bank of Kansas City, Kan. v. White
254 S.W.2d 605 (Supreme Court of Missouri, 1953)
Hann v. Venetian Blind Corporation
15 F. Supp. 372 (S.D. California, 1936)
National Cash Register Co. v. Kay
93 S.W.2d 260 (Missouri Court of Appeals, 1936)
United Iron Works v. Twin City Ice & Creamery Co.
296 S.W. 109 (Supreme Court of Missouri, 1927)
Callahan v. Simons
228 P. 892 (Utah Supreme Court, 1924)
Bray v. Culp
219 S.W. 129 (Missouri Court of Appeals, 1920)
French Republic v. Inland Nav. Co.
263 F. 410 (E.D. Missouri, 1920)
Cosgrove v. Stange
183 S.W. 691 (Missouri Court of Appeals, 1916)
Loewenthal v. McElroy
168 S.W. 813 (Missouri Court of Appeals, 1914)
Hinton v. Stanton
165 S.W. 299 (Supreme Court of Arkansas, 1914)
Lindsey v. Nagel
137 S.W. 912 (Missouri Court of Appeals, 1911)
Wright v. Sebastian
130 S.W. 1125 (Missouri Court of Appeals, 1910)
Norman v. Sheip
125 S.W. 527 (Missouri Court of Appeals, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
111 S.W. 641, 132 Mo. App. 232, 1908 Mo. App. LEXIS 527, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nowell-v-mode-moctapp-1908.