Leasecomm Corp. v. Hollyleaf Group, Inc.

16 Mass. L. Rptr. 678
CourtMassachusetts Superior Court
DecidedAugust 13, 2003
DocketNo. 020856H
StatusPublished

This text of 16 Mass. L. Rptr. 678 (Leasecomm Corp. v. Hollyleaf Group, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Leasecomm Corp. v. Hollyleaf Group, Inc., 16 Mass. L. Rptr. 678 (Mass. Ct. App. 2003).

Opinion

Fishman, J.

The plaintiff, Leasecomm Corporation (“Leasecomm”), through its motion for summary judgment, requests that this Court enter a declaratory judgment that the defendant, Hollyleaf Group, Inc. (“Hollyleaf’), failed to comply with the terms of the alternative dispute provision (“ADR provision”) of their contract, arid that because of this failure, Hollyleaf has waived any rights to pursue its claims against Leasecomm. In its cross motion, Hollyleaf asserts that both parties waived the time requirement of the ADR provision, and, therefore, when it submitted the dispute to mediation, it was not untimely. For the following reasons, Leasecomm’s motion for summary judgment is DENIED, and Hollyleaf s cross motion for summary judgment is ALLOWED.

BACKGROUND

The undisputed facts are as follows. The dispute between the parties arises from a Purchase Agreement (“Agreement”) entered into on January 3, 2001. Pursuant to the terms of the Agreement, Leasecomm was entitled to hold back one million dollars of the purchase price (“Hold Back amount”) due Hollyleaf until a software program, named AMI 2000, was completed. The Agreement also contained an ADR provision which provided that:

If any dispute arises under this Agreement between the Seller and the Buyer, such dispute shall be resolved as follows:
(a) The Seller and the Buyer shall promptly meet; and each agrees to use its best efforts to reasonably resolve the dispute without resort to Mediation or Arbitration;
(b) In the event the Seller and the Buyer cannot reasonably resolve any such dispute between them pursuant to Section 12.14(a), then the dispute shall be submitted by either the Seller or the Buyer for informal mediation (“Mediation”) within ten (10) days of the date the dispute shall first arise . . . Mediation shall be concluded within ninety (90) days of its commencement. Mediation shall be a condition precedent to either the Seller’s or the Buyer’s right to pursue any other remedy available under this Agreement or otherwise available under law.
(c) In the event the Seller and the Buyer cannot resolve the dispute by Mediation, then such dispute shall be submitted to binding arbitration (“Arbitration”) . . . Any and all disputes shall be submitted to Arbitration within one (1) year from the date the dispute first arose or shall be forever barred. The Seller and the Buyer agree that Arbitration hereunder shall be in lieu of all other remedies and procedures, and shall be the exclusive method for resolving any disputes arising out of this Agreement.

Section 12.14 (emphasis added).

In April and May of 2001, Henry “Chip” Nichols, (“Nichols”), the president of Hollyleaf, notified Richard Latour (“Latour”), the executive vice president, chief financial officer and chief operating officer of [679]*679Leasecomm that all of the conditions for the release of the Hold Back amount had been met, and requested that Leasecomm relinquish the money. On July 24, 2001, Latour responded to Nichols stating that there were at least five areas where the software was deficient, and that Leasecomm would not release the Hold Back amount.1 The parties agreed that, pursuant to the ADR procedure provided for in the Agreement, they should schedule a time to discuss the deficient areas. The meeting was scheduled for August 29, 2001, the earliest and most convenient time for both parties. At this meeting, Leasecomm agreed that all, but two, of the criteria for the AIM 2000 completion had been met. At the conclusion of the meeting, Nichols indicated that he would review the materials Leasecomm provided, and that he would respond soon thereafter. On September 4, 2001, Nichols sent an e-mail to Leasecomm reflecting on the August 29, 2001 meeting, and indicating that Hollyleaf understood that the parties were going to continue negotiating the remaining issues. On October 9, 2001, Hollyleaf provided Leasecomm with a letter reiterating its position on why the Hold Back amount should be released, and made a settlement offer for a reduced amount. On December 4, 2001, Leasecomm had not responded to the letter. At that time, Nichols deemed the negotiations to be unsuccessful, and on December 7, 2001, pursuant to the Agreement, he initiated mediation proceedings.

On December 10, 2001, Leasecomm wrote to Hollyleaf saying that it intended to continue negotiations. On February 18, 2002, approximately eighty days into the ninety-day period allowed for mediation, Leasecomm raised the issue of timeliness of the mediation proceeding. On February 28, 2002, Leasecomm filed its Complaint with this Court seeking a declaratory judgment on the issue of whether Leasecomm is obligated to mediate the dispute. On March 13, 2002, after the ninety-day period for mediation expired, Hollyleaf, pursuant to the American Arbitration Association (“AAA”) Mediation Rules, informed the AAA that it was terminating the mediation as unsuccessful. Pursuant to Section 12.14(c) of the Agreement, the termination of mediation required that the dispute be submitted for binding arbitration. On March 21, 2002, Hollyleaf filed a Demand for Arbitration with the AAA. At this time, the arbitration is pending.

DISCUSSION

Summary judgment will be granted when there are no genuine issues as to any material facts and where the moving party is entitled to judgment as a matter of law. Mass.R.Civ.P. 56(c); Cassesso v. Commissioner of Corr., 390 Mass. 419, 422 (1983); Community Nat’l Bank v. Dawes, 369 Mass. 550, 553 (1976). The moving party bears the burden of affirmatively demonstrating the absence of a triable issue, and that the summary judgment record entitles it to judgment in its favor as a matter of law. Pederson v. Time, Inc., 404 Mass. 14, 16-17 (1989). The moving party may satisfy this burden either by submitting affirmative evidence that negates an essential element of the opposing party’s case or by demonstrating that the opposing party has no reasonable expectation of proving an essential element of his case at trial. Flesner v. Technical Communications Corp., 410 Mass. 805, 809 (1991); Kourouvacilis v. General Motor Corp., 410 Mass. 706, 716 (1991).

The issue before this Court is whether Hollyleaf waived its right to arbitration by failing to timely file for mediation within ten days of the date that the dispute first arose. This Court will address the matter both in its procedural context and by an analysis of the contractual provisions at issue.

The question of whether a party has waived its right to arbitration is generally a question for the court to determine. See Martin v. Norwood, 395 Mass. 159, 162 (1985). As with any contractual right, the right to arbitration may be lost if it is not asserted in a timely manner. See Home Gas Corp. of Massachusetts, Inc. v. Walter’s of Hadley, Inc., 403 Mass. 772, 775 (1989). However,

where the contract contains an arbitration clause, there is a presumption of arbitrability in the sense that [a]n order to arbitrate the particular grievance should not be denied unless it may be said with positive assurance that the arbitration clause is not susceptible of an interpretation that covers the asserted dispute. Doubts should be resolved in favor of coverage .. . Such a presumption is particularly applicable where the clause is broad.2

Local Union No. 1710, Int’l Ass’n of Fire Fighters v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

At&T Technologies, Inc. v. Communications Workers
475 U.S. 643 (Supreme Court, 1986)
Home Gas Corp. of Massachusetts, Inc. v. Walter's of Hadley, Inc.
532 N.E.2d 681 (Massachusetts Supreme Judicial Court, 1989)
Pederson v. Time, Inc.
532 N.E.2d 1211 (Massachusetts Supreme Judicial Court, 1989)
Merrimack Mutual Fire Insurance v. Nonaka
606 N.E.2d 904 (Massachusetts Supreme Judicial Court, 1993)
Church of God in Christ, Inc. v. Congregation Kehillath Jacob
353 N.E.2d 669 (Massachusetts Supreme Judicial Court, 1976)
Community National Bank v. Dawes
340 N.E.2d 877 (Massachusetts Supreme Judicial Court, 1976)
Kourouvacilis v. General Motors Corp.
575 N.E.2d 734 (Massachusetts Supreme Judicial Court, 1991)
Flesner v. Technical Communications Corp.
575 N.E.2d 1107 (Massachusetts Supreme Judicial Court, 1991)
Cassesso v. Commissioner of Correction
456 N.E.2d 1123 (Massachusetts Supreme Judicial Court, 1983)
USM Corp. v. Arthur D. Little Systems, Inc.
546 N.E.2d 888 (Massachusetts Appeals Court, 1989)
Carpenter v. Pomerantz
634 N.E.2d 587 (Massachusetts Appeals Court, 1994)
Martin v. Norwood
478 N.E.2d 955 (Massachusetts Supreme Judicial Court, 1985)
Ober v. National Casualty Co.
60 N.E.2d 90 (Massachusetts Supreme Judicial Court, 1945)
McCarthy v. Tobin
706 N.E.2d 629 (Massachusetts Supreme Judicial Court, 1999)
Local No. 1710, International Ass'n of Fire Fighters, AFL-CIO v. City of Chicopee
721 N.E.2d 378 (Massachusetts Supreme Judicial Court, 1999)
Joseph Francese, Inc. v. Dos Concrete Services, Inc.
47 Mass. App. Ct. 367 (Massachusetts Appeals Court, 1999)
Cady v. Marcella
729 N.E.2d 1125 (Massachusetts Appeals Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
16 Mass. L. Rptr. 678, Counsel Stack Legal Research, https://law.counselstack.com/opinion/leasecomm-corp-v-hollyleaf-group-inc-masssuperct-2003.