League to Save Lake Tahoe v. Crystal Enterprises

490 F. Supp. 995, 1980 U.S. Dist. LEXIS 11748
CourtDistrict Court, D. Nevada
DecidedJune 6, 1980
DocketCiv. R-75-87 BRT
StatusPublished
Cited by3 cases

This text of 490 F. Supp. 995 (League to Save Lake Tahoe v. Crystal Enterprises) is published on Counsel Stack Legal Research, covering District Court, D. Nevada primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
League to Save Lake Tahoe v. Crystal Enterprises, 490 F. Supp. 995, 1980 U.S. Dist. LEXIS 11748 (D. Nev. 1980).

Opinion

OPINION

BRUCE R. THOMPSON, District Judge.

This lawsuit involves the construction of a parking garage/hotel tower at the Crystal Bay Club at Lake Tahoe. The plaintiffs contend that construction ceased on this project for periods of time which would require the defendants to: (1) become subject to the requirements of the Tahoe Regional Planning Agency’s Land Use Ordinance, and (2) acquire a new building permit and administrative permit for Washoe County, Nevada which would, in turn, also subject the project to the requirements of the Land Use Ordinance.

*997 A. FACTUAL AND PROCEDURAL BACKGROUND

In 1970, the predecessors in interest of defendant Crystal Enterprises began the process of adding a parking garage and 15-story hotel tower to the existing facilities of the Crystal Bay Club on Nevada’s side of the north shore of Lake Tahoe. The Washoe County, Nevada Building Department granted a building permit for this construction on August 20, 1970. Shortly thereafter construction commenced and by the end of June, 1971, the parking garage and the structural portion of three floors of the hotel tower were completed. After the end of June, 1971, construction activity virtually ceased.

On June 5, 1972, the Building Department renewed the original building permit upon the payment of one-half the original fee. On July 5, 1972, separate and original permits were issued for some remodeling and fence construction. No renewal for the main permit was sought in 1973. On January 4, 1974, a renewal permit was issued and renewal permits have issued yearly thereafter.

In April of 1975, construction was restarted on the project. On May 28, 1975, this lawsuit was filed and in early June construction again ceased. After the lawsuit was begun, the Washoe County Building Department inspected the project each year to determine if sufficient work had been done before granting renewal of the original permit.

The Tahoe Regional Planning Agency’s Land Use Ordinance became effective on April 11, 1972. Under this ordinance, the project at Crystal Bay Club is a nonconforming use. See § 7.12(15). However, the ordinance also contained a grandfather clause, § 9.11, which exempted from the requirements of the ordinance existing uses and projects “upon which construction has commenced as allowed by . permit prior to February 10, 1972. . . . ” The exemption does not apply if “any such use ceases for a period of one (1) year.” Id.

The plaintiffs alleged violations of both the TRPA Land Use Ordinance (hereafter LUO) and, as a pendent claim, violations of Section 302(d) of the Washoe County Uniform Building Code. 1 This court originally dismissed the suit for lack of subject matter jurisdiction under 28 U.S.C. § 1331(a). In League to Save Lake Tahoe v. B.J.K. Corp., 547 F.2d 1072 (1976), the Ninth Circuit Court of Appeals reversed, finding that a suit involving interpretation of § 9.11 of the LUO raises a federal question sufficient to maintain jurisdiction under 28 U.S.C. § 1331(a) because the effective implementation of the regional plan requires uniform interstate interpretation of the TRPA ordinances.

B. VIOLATIONS OF THE TAHOE REGIONAL PLANNING AGENCY LAND USE ORDINANCE

The question of whether the cessation of construction activity forfeited the grandfather clause exception can be separated into two sections: (1) whether or not construction is part of a use “to be created” under § 9.11, and (2) if so, whether or not construction actually ceased for one year or more on this project.

I. Construction and Use Under § 9.11.

The defendants maintain that the unfinished structure is a nonconforming use not subject to review by the bi-state agency by *998 reason of the grandfather clause, § 9.11. Section 9.11, in its full and correct form, 2 states:

“9.11 Existing Uses and Structures
Uses of land and structures that do not conform to the regulations established by this Ordinance and which lawfully existed on February 10, 1972, or which are to be created in connection with structures for which a valid permit was issued on or before February 10,1972 and upon which construction has commenced as allowed by such permit prior to February 10, 1972, may be continued, transferred or sold, provided, however, in the case of a use to be created it shall occupy no greater area than planned at the time such permit was issued. If any such use ceases for a period of one (1) year, subsequent use of such land shall be in conformity with the regulations contained in this Ordinance.”

(emphasis in original.) Both sides agree that if use of a completed structure ceases for a period of one year or more, then the grandfather clause protection of the nonconforming use will be lost. The entire argument revolves around the cessation of construction work on a use “to be created.” The plaintiffs maintain that the words “such use” in the last sentence include the course of construction required to create the future use. Under this interpretation, the cessation of construction for a period of one year or more would forfeit the exemption from TRPA review allowed by § 9.11. The defendants maintain that the course of construction is not included within the words “such use” and that it is irrelevant what happens during construction. The defendants’ position is that the nonconforming use classification can only be lost once the structure is completed, used for its purpose and then that use abandoned for more than a year.

This issue presents a very difficult point of statutory construction. Nowhere in the LUO is “use” or “nonconforming use” defined. Both plaintiffs and defendants have asserted plausible arguments for their respective interpretations. The court finds the plaintiffs’ arguments more convincing when looking at the ordinance as a whole and § 9.11 in particular. This interpretation is supported by C.F. Lytle Co. v. Clark, 491 F.2d 834 (10th Cir. 1974). Pitkin County, Colorado had a zoning ordinance which provided that

“[wjhenever a non-conforming use has been discontinued for a period of one year, such use shall not thereafter be re-established, and any further use shall be in conformance with the provisions of this resolution or any amendment thereof.”

Id. at 837. The trial court found that the nonconforming use had been discontinued because construction had ceased and the developer had stopped communicating with the county building department for 5 years. The Court of Appeals upheld the trial court and added that intent to abandon the project is not required where the ordinance states a specific time limit. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The Reserve, Ltd. v. Town of Longboat Key
17 F.3d 1374 (Eleventh Circuit, 1994)
League to Save Lake Tahoe v. Crystal Enterprises
685 F.2d 1142 (Ninth Circuit, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
490 F. Supp. 995, 1980 U.S. Dist. LEXIS 11748, Counsel Stack Legal Research, https://law.counselstack.com/opinion/league-to-save-lake-tahoe-v-crystal-enterprises-nvd-1980.