LDS Development, LLC v. City of Eugene

382 P.3d 576, 280 Or. App. 611
CourtCourt of Appeals of Oregon
DecidedAugust 16, 2016
Docket161211098; A158294
StatusPublished
Cited by9 cases

This text of 382 P.3d 576 (LDS Development, LLC v. City of Eugene) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
LDS Development, LLC v. City of Eugene, 382 P.3d 576, 280 Or. App. 611 (Or. Ct. App. 2016).

Opinion

SHORR, J.

This action arises from a to-date failed housing development in Eugene. Although it involves multiple parties, it primarily relates to the question of whether two of the parties have an obligation to construct certain public infrastructure improvements outlined in the agreement authorizing the subdivision and development of the property. Under that agreement, which we refer to throughout this opinion as the development agreement, the original developer agreed to install water supply infrastructure and a sewer system, and posted a bond securing that obligation. Years after the original developer withdrew from the project without completing those improvements, plaintiff LDS Development, LLC (LDS) purchased the property. LDS then joined this action as a substituted plaintiff,1 alleging that the City of Eugene was obligated to complete the improvements or enforce the bond securing the original developer’s obligation. The city brought two counterclaims, one for declaratory relief and the other for breach of contract, asserting in each that LDS was obligated under the agreement to complete the improvements as successor to the original developer. The trial court granted summary judgment in favor of the city on all of the claims and counterclaims.

LDS now appeals the trial court’s judgment granting summary judgment in favor of defendant City of Eugene against LDS’s claims and granting summary judgment to the city on its counterclaims against LDS. In the first and second assignments of error, LDS argues that the trial court erred in granting the city’s motion for summary judgment, which dismissed LDS’s first and second claims against the city. Those claims both allege that the city was required either to complete the improvements or call in the bond. LDS’s third assignment of error pertains to the grant [614]*614of summary judgment in favor of the city’s two counterclaims against LDS. LDS argues that the trial court erred in concluding that it was successor to the original developer’s responsibilities and obligations under the development agreement.2

We conclude, as to the first and second assignments of error, that the trial court did not err in granting summary judgment against LDS’s first and second claims. The city does not have any contractual or statutory obligation to construct the infrastructure improvements at issue in these circumstances.3 We further conclude, with respect to the third assignment of error, that the trial court erred in granting summary judgment in favor of the city’s counterclaims. As explained below, those rulings were based on the erroneous premise that LDS is contractually bound under the development agreement. Because LDS is neither a party nor an assignee to the development agreement, LDS has no contractual obligation under it. And, because the city’s counterclaims do not allege that the obligation to construct the improvements is a covenant running with the land or an equitable servitude (as opposed to a personal contractual obligation), we do not address or decide those issues. Accordingly, we reverse and remand as to the grant of summary judgment on the city’s first and second counterclaims.4

[615]*615We review a trial court’s grant of summary judgment to determine whether there are any genuine issues of material fact and whether the moving party is entitled to judgment as a matter of law, and, in so doing, we view the facts in the light most favorable to the nonmoving party. ORCP 47 C; Jones v. General Motors Corp., 325 Or 404, 420, 939 P2d 608 (1997). We state the underlying facts, which are undisputed, in accordance with that standard.

This is one of four appeals arising from litigation over the unfinished Moon Mountain subdivision development in Eugene. We relate only the historical and procedural facts that are relevant to this particular appeal. The Real Estate Development Group, LLC (REDG) was the original Moon Mountain developer. REDG entered into a development agreement with the city that authorized the subdivision of the original large parcel into 102 smaller residential lots, with spaces dedicated for roads and other public improvements.

Several aspects of the development agreement are significant. The only parties to the agreement were the city and REDG. The agreement required REDG to complete certain infrastructure improvements in two phases, with phase 1 pertaining to one area of the development and phase 2 pertaining to another, with phase 2 to be developed after the completion of phase 1. Relatedly, the agreement required REDG to post a bond in an amount equal to the estimated cost of completing the phase 2 water and sewer improvements as a condition to final approval of the project. The agreement did not, however, expressly impose any affirmative obligation on the city to complete the improvements. In addition, the agreement provided that “[t]here is no intent on the City’s part to bestow a benefit on individual third parties,” and that the city has “sole and unfettered discretion” to seek damages or specific performance in the event of a breach by REDG. It included a provision stating that the prevailing party in any suit or action brought under it was entitled to attorney fees. Finally, a “successor interest” clause provided that the agreement was “binding upon heirs, executors, administrators, and assigns of both parties and is a condition and covenant running with the land.”

[616]*616As required under the development agreement, REDG obtained a bond for over a million dollars securing its obligation to complete the phase 2 improvements. Developers Surety and Indemnity Company (DSIC) issued the bond. Under its terms, the bond would become void once REDG constructed the improvements free of defects. Otherwise, the bond would “remain in full force and effect” and DSIC would be “held and firmly bound unto the City of Eugene as [o]bligee.”

REDG completed work on phase 1 of the development, but, due to financial difficulties, abandoned the project shortly after starting work on phase 2. In lieu of foreclosure, REDG transferred its interest in the development to Umpqua Bank.

Stonecrest Properties, LLC, later acquired the subdivision from the bank. Stonecrest filed this action, which LDS later joined, alleging various claims against multiple defendants, including the city and DSIC.5 Among other things, the operative complaint alleged that, under various statutes and regulations and the development agreement, the city was required to enforce DSIC’s bond or to complete the phase 2 infrastructure improvements itself.6 Based on those allegations, LDS sought a declaration to that effect in its first claim for relief and sought specific performance of the obligation to construct the improvements in its second claim for relief.

The city’s answer denied that it had any legal or contractual obligation to complete the improvements. In addition, the city asserted two counterclaims, the content of which is particularly important to our analysis of the third assignment of error.

The city’s first counterclaim sought a declaration that, “to the extent the Improvements are required to be [617]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dept. of Human Services v. M. B.
347 Or. App. 890 (Court of Appeals of Oregon, 2026)
Adelsperger v. Elkside Development LLC
373 Or. 621 (Oregon Supreme Court, 2025)
Doss v. Farmers Ins. Co. of Oregon
334 Or. App. 826 (Court of Appeals of Oregon, 2024)
Adelsperger v. Elkside Development LLC
523 P.3d 142 (Court of Appeals of Oregon, 2022)
Sander v. Nicholson
473 P.3d 1113 (Court of Appeals of Oregon, 2020)
Vukanovich v. Kine
461 P.3d 223 (Court of Appeals of Oregon, 2020)
Brookline Residential, LLC v. City of Charlotte
796 S.E.2d 369 (Court of Appeals of North Carolina, 2017)
LDS Development, LLC v. City of Eugene
383 P.3d 976 (Court of Appeals of Oregon, 2016)
Stonecrest Properties, LLC v. City of Eugene
382 P.3d 539 (Court of Appeals of Oregon, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
382 P.3d 576, 280 Or. App. 611, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lds-development-llc-v-city-of-eugene-orctapp-2016.