Ldg Timber Enterprises, Inc. v. Dan Glickman, Secretary of Agriculture

114 F.3d 1140, 41 Cont. Cas. Fed. 77,109, 1997 U.S. App. LEXIS 13108, 1997 WL 292787
CourtCourt of Appeals for the Federal Circuit
DecidedJune 4, 1997
Docket96-1139
StatusPublished
Cited by10 cases

This text of 114 F.3d 1140 (Ldg Timber Enterprises, Inc. v. Dan Glickman, Secretary of Agriculture) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ldg Timber Enterprises, Inc. v. Dan Glickman, Secretary of Agriculture, 114 F.3d 1140, 41 Cont. Cas. Fed. 77,109, 1997 U.S. App. LEXIS 13108, 1997 WL 292787 (Fed. Cir. 1997).

Opinion

PAULINE NEWMAN, Circuit Judge.

LDG Timber Enterprises, Inc. (LDG) appeals the decision of the United States Department of Agriculture Board of Contract Appeals, AGRBCA Nos. 91-213-1 and 95-228-R, 1 denying LDG’s claim for damages based on certain timber contracts in national forests. We affirm the Board’s judgment.

*1141 BACKGROUND

This case concerns the relationship between two timber contracts: the Blacksmith Timber Sale in the Sierra National Forest and the Boundary Timber Sale in the Sequoia National Forest. LDG’s performance of the Blacksmith contract was required to be completed by June 25, 1988, and the Boundary contract by March 31, 1992. During the summer of 1987, while LDG was logging the Blacksmith area, a fire occurred at the Boundary area. The Forest Service estimated that 40% of the remaining Boundary timber would die because of insect infestation and other events that follow a forest fire. LDG, with the agreement of the Forest Service, transferred its operations in the fall of 1987 to the Boundary sale area in order to harvest and salvage the remaining timber. In view of this transfer of operations, various time extensions to the Blacksmith contract ensued. The Forest Service refused to extend the Blacksmith contract beyond October 15,1989, leading to this dispute.

The extensions to the Blacksmith contract were documented as follows: By letter of March 10, 1988 the Forest Service, through Contracting Officer Moyle, wrote that the twenty-five days lost between June 1, 1988 (the start of the Normal Operating Season 2 for Blacksmith) and June 25, 1988 (the original Blacksmith completion date) would commence seven days after the work at Boundary was completed, subject to certain contingencies not here relevant. By contract modification with letter of June 17, 1988 the contracting officer extended the termination date of the Blacksmith contract to August 12, 1988. By contract modification with letter of August 11, 1988 the contracting officer extended the termination date of the Blacksmith contract to August 11, 1989. The contracting officer wrote:

If additional adjustments in termination date is requested after operations on fire damaged timber is completed, operating days available to you on the Blacksmith Timber Sale that may occur outside the normal operating period will be included in determining a new contract termination date.

LDG points to this letter as confirming the Forest Service’s promise of “day for day” credit for the days not worked at Blacksmith because of the Boundary operations, subject only to weather or road conditions (ie., available operating days) at Blacksmith.

LDG resumed operations at Blacksmith in June 1989, and on July 5,1989 LDG requested further extension of the Blacksmith contract in accordance with these arrangements. On July 26, 1989 the contracting officer sent a contract modification to extend the Blacksmith termination date to November 30, 1989, but added the condition that the Blacksmith Normal Operating Season would be redefined as extended to November 30,1989. Contracting Officer Moyle’s letter of July 26 stated:

The contract term is being extended to November 30,1989 pursuant to B8.21 Contract Term Adjustment (CTA). The CTA is being offered to compensate for time you have spent logging fire damaged timber on the Sequoia National Forest Boundary Timber Sale through November 30, 1988. Boundary Timber Sale operations after that date are not being included in the CTA because Blacksmith Timber Sale was not operable during that period of time.

Section B8.21 Contract Term Adjustment provided:

[In applicable circumstances] the contract term shall be adjusted in writing to include additional calendar days in one or more Normal Operating Seasons equal to the actual time lost----

The Blacksmith contract set the Normal Operating Season for that area as from June 1 to October 15 of each calendar year. With specified exceptions, LDG was permitted by the Blacksmith contract to conduct timber operations outside the Normal Operating Season, if weather and ground conditions permitted.

*1142 LDG promptly objected to the part of the July 26, 1989 letter that proposed enlargement of the Blacksmith Normal Operating Season to November 30, 1989, stating that such enlargement was not in LDG’s interest since it foreclosed LDG from obtaining additional working days without consuming contract extension days; LDG requested extension of the contract to September 5, 1990, that is, into the ensuing Normal Operating Season. Contracting Officer Moyle then withdrew the proffered extension, and on August 1, 1989 presented a formal contract modification finally terminating the Blacksmith contract on October 15, 1989, with a letter wherein the contracting officer stated that he was “incorrect” when he wrote LDG a year earlier (on August 11, 1988) with the contract extension then provided, that additional days of extension would be available at Blacksmith based on Boundary activities outside of the Blacksmith Normal Operating Season. The contracting officer also advised LDG that LDG could “qualify for a contract term extension by cutting and removing at least 75% of the advertised sale volume” by October 15,1989. LDG executed, under protest, the contract modification accompanying this letter.

LDG had cut 60-65% of the Blacksmith timber by October 15,1989. The contracting officer refused further extension, and LDG appealed to the Department of Agriculture Board of Contract Appeals, seeking extension of the Blacksmith contract. The Board dismissed that appeal without prejudice, holding that it had no authority to grant the requested form of relief. LDG then filed a claim for damages, in the amount of the contract price of the uncut timber. The contracting officer denied the claim, and LDG appealed to the Board.

In the Board proceedings LDG’s position was that it was wrongly denied extension as was needed to complete logging of the Blacksmith sale. LDG stated it had relied on the Forest Service’s representations that it would extend the term of the Blacksmith sale, day for day, for the time spent on the Boundary sale both within and outside the Blacksmith Normal Operating Season. LDG also stated that the offer to extend the term to November 30, 1989 was wrongfully withdrawn, referring to Contracting Officer Moyle’s sudden action on August 1, 1989 wherein he set the final deadline of October 15,1989, leaving insufficient time for LDG to log the remaining 5,245,000 board feet of the Blacksmith sale. LDG stated that the Forest Service was required to extend the contract in accordance with its representations, and that LDG was entitled to an extension into the following year’s Normal Operating Season and commensurate damages.

In an initial ruling the Board held that the Forest Service was not bound by the representations accompanying the various contract modifications, holding that “[t]he CO’s actions do not rise to the level of a formal contract modification.” The Board held that the issue was controlled by the theory of equitable estoppel.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
114 F.3d 1140, 41 Cont. Cas. Fed. 77,109, 1997 U.S. App. LEXIS 13108, 1997 WL 292787, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ldg-timber-enterprises-inc-v-dan-glickman-secretary-of-agriculture-cafc-1997.