Lawrence D. Baker v. Defense Logistics Agency

782 F.2d 1579, 1986 U.S. App. LEXIS 19987
CourtCourt of Appeals for the Federal Circuit
DecidedFebruary 5, 1986
DocketAppeal 85-2040
StatusPublished
Cited by4 cases

This text of 782 F.2d 1579 (Lawrence D. Baker v. Defense Logistics Agency) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lawrence D. Baker v. Defense Logistics Agency, 782 F.2d 1579, 1986 U.S. App. LEXIS 19987 (Fed. Cir. 1986).

Opinion

JACK R. MILLER, Senior Circuit Judge.

Petitioner timely appealed to the Chicago Regional Office of the Merit Systems Protection Board (“MSPB”) from the action taken by the Defense Logistics Agency, Defense Construction Supply Center, Columbus, Ohio, demoting him, effective February 12, 1984, from the position of Equipment Mechanic Foreman of the Operations Production Control/Maintenance Division of the agency’s Directorate of Maintenance to the position of Electrical Equipment Repairer Foreman in the Industrial Equipment Maintenance Branch of the Equipment and Maintenance Division of the agency’s Directorate of Installation Services. Petitioner was demoted for his alleged failure to perform two of the five critical elements 1 of his position at an acceptable level of competence under the agency’s employee performance appraisal system. 2

The Presiding Official (“PO”) reversed the agency action, finding that it failed to prove by substantial evidence that petition *1580 er did not meet the performance standards for the minimally acceptable level of performance of the two critical elements, and ordered the agency to cancel its action demoting petitioner. The MSPB reversed the initial decision of the PO and sustained the agency action, finding that the agency did prove by substantial evidence that petitioner failed to acceptably perform the critical elements. 25 M.S.P.R. 614 (1985). We affirm. 3

Presiding Official’s Opinion

With respect to the first critical element, the PO stated that the agency had alleged that petitioner’s performance was unacceptable because (1) petitioner was not familiar with his unit’s program and the required results; (2) nearly 18% of his completed machine repair projects exceeded 10% of the actual manhours/materials estimates required for completion of repairs; (3) only 80% of his repair estimates were submitted within the established time frames; and (4) most of those estimates resulted in excessive expenditures by petitioner’s unit. The PO further stated that the agency had alleged that petitioner’s immediate supervisor (Chief of the Operations Production Control/Maintenance Division) met with petitioner and the other branch foreman and outlined specific actions he required of them as branch foremen, namely: (1) maintain full knowledge of their shop work load, including completion dates; (2) assure that all of their employees were productive and that they were aware of work requirements and completion dates; (3) take immediate steps to avoid work delays; and (4) plan and organize their shop work to enhance continuous and even workflow. 4

The PO found that to achieve the minimally acceptable level of performance for the first critical element, petitioner had to meet, inter alia, the ■ following performance standards:

b. (He is) normally familiar with most of the ongoing work of the organization;
c. (His) competent technical advice normally can be provided to subordinates as necessary to achieve an effective work product; and, d. (He) in most cases assures that work is completed on time, according to the work plan of the unit.

With respect to familiarity with most of the ongoing work of the organization, the PO related that petitioner’s supervisor testified that on several occasions he asked petitioner for status reports and that petitioner told him he was unable to provide an on-the-spot status report for some of the work in his unit; however, petitioner established that he was familiar with most of the ongoing work of his unit. The PO found that, because, the performance standard was phrased in terms of “normally familiar” with “most” of the ongoing work, the agency did not establish by substantial evidence that petitioner failed to meet this standard. Regarding the standard that his competent technical advice normally can be provided to subordinates, the PO found this standard conclusory in nature and factually unsupported. As to the standard that in *1581 most cases assures that work is completed on time, the PO observed that the record discloses that petitioner’s unit completed repairs on or rebuilt 97 machines from August 1,1982, through July 31,1983; that of these 97 machines, 51 were completed on time and 46 were late; that of the 46, six were late for reasons beyond petitioner’s control; that, even assuming that 40 of the 97 machines were late for reasons within petitioner’s control, the standard is stated in terms of “most cases”; and that the common meaning of the word “most” (citing American Heritage Dictionary) is “the greatest number” or “the majority.”

As to the second critical element, the PO stated that the agency alleged that petitioner failed to meet the minimally acceptable standard because (1) petitioner’s unit completed work on 97 machines during the period August 1, 1982, through July 31, 1983; (2) of that total, work on 46 machines exceeded the required completion dates— an on-time effectiveness of 53%; and (3) petitioner failed to meet his own work load projections by more than 50% for the month of July, 1983. The PO related that the agency relied on the statement of petitioner’s supervisor that he had emphasized to petitioner the importance of completing two of the late machines in time to contact the customers to witness the final test and inspection; that these two machines were not completed on schedule and one of them was reassigned to another repair unit because of unsatisfactory progress in petitioner’s unit; and that during the August 1, 1982 — July 31, 1983 period, 17% of the completed machines were rejected during final tests due to petitioner’s failure to assure that the work met the required quality.

The PO found that to achieve the minimally acceptable level of performance for the second critical element, the standard states that “the work unit usually meets deadlines, and quality of work is usually acceptable”; that the word “usual,” from which “usually” is derived, means (citing Random House College Dictionary) occurs more often than not; and.that petitioner met his deadlines “more often than not” (51 times out of 97) and that the quality of the work he produced was acceptable “more often than not” (83% of the time).

MSPB Opinion

Quoting 5 U.S.C. § 4302(b)(1), 5 the board stated that Congress recognized that the statute would benefit employees by protecting them from arbitrary labeling of their work as “unacceptable” and would ensure that employees were made aware in advance of what was expected of their performance; further, that Congress intended the agency to have considerable flexibility in devising methods for evaluating performance and, therefore, limited the board’s scope of review to determining whether the agency abused its discretion in promulgating performance standards. The board found that the agency had not abused its discretion in establishing petitioner’s performance standards.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kristen Westling v. Department of Defense
Merit Systems Protection Board, 2023
Angelina Feesago v. Department of Defense
Merit Systems Protection Board, 2022

Cite This Page — Counsel Stack

Bluebook (online)
782 F.2d 1579, 1986 U.S. App. LEXIS 19987, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lawrence-d-baker-v-defense-logistics-agency-cafc-1986.