LaValle v. Aqualand Pool Co., Inc.

257 N.W.2d 324, 1977 Minn. LEXIS 1418
CourtSupreme Court of Minnesota
DecidedJuly 29, 1977
Docket46982
StatusPublished
Cited by46 cases

This text of 257 N.W.2d 324 (LaValle v. Aqualand Pool Co., Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
LaValle v. Aqualand Pool Co., Inc., 257 N.W.2d 324, 1977 Minn. LEXIS 1418 (Mich. 1977).

Opinion

MacLAUGHLIN, Justice.

Lloyd and Margaret LaValle brought an action for breach of contract against Aqua-land Pool Co., Inc., alleging negligent installation and defective construction of a swimming pool on the LaValles’ residential property. Aqualand crosselaimed for contribution or indemnification against William Reitherman, a codefendant, who had* been hired by Aqualand to construct the pool, alleging that any defects in the construction resulted from Reitherman’s negligence. The case was tried to a jury which found damages of $4,650 of which $1,150 was attributed to Reitherman. Aqualand appeals from the judgment. We affirm.

On August 2, 1973, the LaValles entered into a contract with Aqualand for the construction of a 20- by 40-foot in-ground, steel-walled, vinyl-lined swimming pool for a price of $6,900. Aqualand hired Reither-man, an independent contractor, to excavate and construct the pool at the LaValles’ residence in Waconia, Minnesota, for a flat fee of $1,000. By a separate agreement the LaValles employed Reitherman, for an agreed price of $2,700, to perform additional work in connection with the pool, including construction of a pool deck, installation of a slide, diving board, ladder, and handrails purchased from Aqualand, and landscaping of the surrounding area. This separate contract between the LaValles and Reitherman was not at issue in the instant lawsuit.

In September 1973, after the construction of the pool was largely completed but before the concrete had been laid for the deck, the LaValles found that the northwest corner of the pool was lower than other parts of the pool and that the vinyl liner would not fit properly. LaValle stopped payment on his final check to Aqualand, and subsequently Reitherman returned and raised the sagging corner to bring it into line with the rest of the structure. LaValle then paid the remaining balance owed for the pool.

After completion of the pool and deck in October 1973, the LaValles used it for a short time, but in the spring of 1974 they noticed several additional problems of which they gave notice to Aqualand’s vice-president, Harvey Blumenberg. Blumen-berg inspected the work and, after draining the pool to replace an ill-fitting liner, discovered that the pool had not been constructed to the specified length of 40 feet but was actually 41½ feet long. Since the standard vinyl liner was made for a 20- by 40-foot pool, the one installed in plaintiffs’ pool would not fit properly and a new one was available only by special order from a manufacturer in New Jersey. The pool was left unfilled during the 3 weeks required to obtain the extra-long liner.

When the new liner arrived, it was installed by Aqualand’s workmen since Reith-erman had refused to perform the necessary repairs. After the liner was in place the LaValles noticed new defects in the pool. The northwest corner which had been raised the previous fall was again lower than the rest of the pool; the steps protruded inward into the pool; and the northwest sidewall bowed inward.

When Aqualand refused to make further repairs, the LaValles began this action. At trial, the existence of the alleged defects was not disputed by Aqualand or Reither-man, and the sole question for decision by the jury was the amount of the LaValles’ damages.

*327 The evidence established that the assembly of the pool was made by Reitherman with pool panels of the wrong size, causing the pool to be 41½ feet in length rather than 40 feet as specified. Reitherman admitted that his men had procured the wrong panels from Aqualand and that he had not noticed the deviation upon installation. Reitherman also testified that bowing had probably occurred during the 3-week period when Aqualand’s workmen had drained the pool and failed to brace the walls while waiting for the custom-made liner since without proper bracing of the sides such bowing is likely to occur.

Aqualand and Reitherman offered testimony of what they claimed it would cost to repair all the defects in the LaValies’ pool. Blumenberg stated that the cost of repairs would be approximately $500 although he admitted that repair of the pool would necessitate tearing up part of the surrounding concrete deck and patching it after the repairs were completed. Blumenberg acknowledged that even after repairs the extra IV2 feet in length could not be altered and gave no guarantee that tearing up and replacing the deck would not be noticeable nor that the section replaced would not be weakened by being constructed separately and not attached to the unitary steel mesh which underlay the entire deck.

Reitherman gave testimony that the repairs could be made for $550 to $650. Aqualand’s witness, Virgil Mulvaney, owner of a competing swimming pool company, testified that the cost of repairs would be approximately $600.

Plaintiffs’ only witness was Lloyd La-Valle who testified that the pool and its surrounding area would have been worth approximately $10,000 if properly installed, based on the contract price of $6,900 paid to Aqualand and the $2,700 separately paid to Reitherman for the deck work and landscaping. La Valle further testified that in July 1974 the reasonable value of the entire improvement was $5,000.

After the case had been submitted to the jury by special verdict and plaintiffs’ damages were assessed at $4,650, Aqualand moved the trial court for judgment notwithstanding the verdict or, in the alternative, for a new trial. This appeal followed denial of the motion and entry of judgment.

1. Aqualand asserts that the trial court incorrectly charged the jury as to the measure of damages. The jury was instructed to apply the following rule:

“ * * * In the absence of special circumstances showing approximate damages of a greater amount the loss or damage is the difference between the value of the property as delivered and installed and the value of the property delivered and installed if it had been delivered and installed as agreed upon. * * # tf

The record discloses the following declaration by Aqualand’s counsel just after the final arguments:

“Your Honor, I wish to state for the record that I have discussed this matter with the other counsel and in light of the fact that we have thoroughly discussed the instructions that the court proposed to give in this matter and we have all agreed to those instructions, and also in light of the fact that each one of us has various things after the noon recess, it’s my understanding that each and every counsel would waive presence during the time that the jury is instructed, and we will also waive appearance at the time that the verdict is returned * * *

The waiver of presence of counsel during the jury instructions was concurred in by counsel for plaintiffs and for Reitherman, and agreed to by the trial court. Aqualand now claims that the jury should have been instructed that the cost of repairs would be the proper measure of damages under the facts and circumstances of this case. However, it is clear that the instructions were generally discussed and approved by all counsel prior to the charge to the jury, that counsel waived the right to be present during the charge, and that the trial court gave the instructions as previously discussed and approved without any objection by counsel. Under all these circumstances, we will not *328

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Galaxy Wireless, LLC v. Western National Mutual Insurance Company
8 N.W.3d 698 (Court of Appeals of Minnesota, 2024)
Schedin v. Ortho-McNeil-Janssen Pharmaceuticals, Inc.
700 F.3d 1161 (Eighth Circuit, 2012)
West St. Paul Federation of Teachers v. Independent School District No. 197
713 N.W.2d 366 (Court of Appeals of Minnesota, 2006)
Clifford v. Geritom Med, Inc.
681 N.W.2d 680 (Supreme Court of Minnesota, 2004)
Nuessmeier Electric, Inc. v. Weiss Manufacturing Co.
632 N.W.2d 248 (Court of Appeals of Minnesota, 2001)
Sentinel Management Co. v. Aetna Casualty & Surety Co.
615 N.W.2d 819 (Supreme Court of Minnesota, 2000)
LeDoux v. Northwest Publishing, Inc.
521 N.W.2d 59 (Court of Appeals of Minnesota, 1994)
Mertes v. Estate of King
501 N.W.2d 660 (Court of Appeals of Minnesota, 1993)
Green v. City of Coon Rapids
485 N.W.2d 712 (Court of Appeals of Minnesota, 1992)
Reider v. City of Spring Lake Park
480 N.W.2d 662 (Court of Appeals of Minnesota, 1992)
Peters v. Independent School District Number 657
477 N.W.2d 757 (Court of Appeals of Minnesota, 1991)
Gorecki v. County of Hennepin, Dept. of Public Works
443 N.W.2d 236 (Court of Appeals of Minnesota, 1989)
Gilmore v. Control Data Corp.
442 N.W.2d 835 (Court of Appeals of Minnesota, 1989)
Hydra-Mac, Inc. v. Onan Corp.
430 N.W.2d 846 (Court of Appeals of Minnesota, 1989)
Robinson v. MacK Trucks, Inc.
426 N.W.2d 220 (Court of Appeals of Minnesota, 1988)
Leach v. Estate of Dahl
419 N.W.2d 93 (Court of Appeals of Minnesota, 1988)
Gale v. Howard
413 N.W.2d 234 (Court of Appeals of Minnesota, 1987)
Gertken v. Farmers Elevator of Kensington, Minnesota, Inc.
411 N.W.2d 550 (Court of Appeals of Minnesota, 1987)
Shipka v. Helvig
405 N.W.2d 248 (Court of Appeals of Minnesota, 1987)
Betzold v. Sherwin
404 N.W.2d 286 (Court of Appeals of Minnesota, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
257 N.W.2d 324, 1977 Minn. LEXIS 1418, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lavalle-v-aqualand-pool-co-inc-minn-1977.