Laswell v. National Handle Co.

126 S.W. 969, 147 Mo. App. 497, 1910 Mo. App. LEXIS 572
CourtMissouri Court of Appeals
DecidedMarch 22, 1910
StatusPublished
Cited by9 cases

This text of 126 S.W. 969 (Laswell v. National Handle Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Laswell v. National Handle Co., 126 S.W. 969, 147 Mo. App. 497, 1910 Mo. App. LEXIS 572 (Mo. Ct. App. 1910).

Opinion

GOODE, J.

Petition in two counts for damages for refusal to perform a contract. Defendant is a corporation now known as the National Handle Company, hut formerly as the American Handle Company, under which title,» on April 20,1904, it entered into the following contract with plaintiffs,- who were partners:

“Articles of Agreement, made and entered into this 20th day of April, 1904, by and between J. P. Las-well & Co., of Manila, Ark., of the first part, and the American Handle Company, of Cleveland, Ohio, of the second part, represented by-.
“Witnesseth: That the party of the first part agrees to sell their entire output of handles made at their mill from date until July 1, 1905.
“Handles to be as near as possible to the requirements of the second party, and such as are named in their schedule, which is hereby attached and forms a part of this agreement.
“The second party agrees to buy said first party’s handles for the time as stated above and will pay:
“15 per cent ádvance for XX; 10 per cent advance for X and No. l’s, f. o. b. cars at Manila, 15c per 100 pounds freight allowed. Inspection to be made at first party’s mill. Terms cash.
“J. P. Laswell & Co.,
“By J. P. Laswell.
“American Handle Co.,
“G. B. Durell, Treas.”

[505]*505Said contract had attached as part of it a schedule of the "varieties and sizes of handles to he taken by the American Handle Company under it. The contract ' was executed in duplicate and the schedule attached to the copy retained by defendant showed at the trial the species of handles known as “D-stem” had been entirely erased, whereas the schedule attached to the copy retained by plaintiffs showed defendant was to accept from plaintiffs D-stem handles of certain kinds, but the printed provision for D-stem handles of other kinds had been struck out. Plaintiffs, who lived at Campbell, Missouri, moved to and established a mill at Manila, Arkansas, at a cost of five thousand dollars, to manufacture handles and supply them to defendant pursuant to said contract, entered into an agreement with the owners of eight sections of land covered with ash timber suitable for handles, to buy the timber, and in other ways prepared to perform their contract. The arrangement between the parties required the handles manufactured by plaintiffs to be inspected by an in-' spector furnished by defendant, before defendant was bound to accept the output'of plaintiffs’ factory, and the course of action followed in performing the contract was for defendant to inform plaintiffs where to ship the handles after they had been manufactured; whereupon it became plaintiffs’ duty to get suitable cars from the railway company, load the handles at their expense and forward them according to defendant’s directions. Defendant knew plaintiffs could not procure ears until they were able to notify the railway company what destination they were desired for, and this they could not tell until defendant advised them. Defendant company dealt in handles, its main place of business being at Fort Wayne, Indiana, though its correspondence was written from Cleveland, Ohio. From August to October, 1904, plaintiffs manufactured, sold and delivered to defendant seven carloads of handles of varieties mentioned in the schedule, but another car[506]*506load, which was composed of 37,000 handles, of which 22,000 were D-stems, was not taken by defendant. These D-stem handles are a kind nsed for spades, shovels and garden forks, and are so called because the part of the handle grasped by the hand of the person who is using an implement to which such handle is attached, is in the shape of a “D,” the straight part being held in the hand, while a stem of varying length, twenty-four to thirty-two inches, extends from the rounded part of the D to the iron socket in which the handle is fastened. Plaintiffs manufactured only the straight part or .stem of the handle, the D part being attached by defendant. As these handles were short, they were made of pieces of timber left after longer varieties had been made. This carload of 37,000 handles seems to have been ready for delivery as early as August, 1904, but though defendant was notified of the fact and had the handles inspected, it did not notify plaintiffs where they were to be shipped, and instead a correspondence ensued which shows procrastination and evasion by defendant, and the handles have not yet- been accepted or paid for. It will be observed defendant’s letters said nothing of these handles being different from the varieties called for in the contract, as it claimed later by way of excuse for not taking them. The correspondence, which is important, as it shows the spirit of the parties about carrying out the contract and also that defendant knew plaintiffs needed prompt payment for'their output in order to run their plant, will be abridged. The first letter relevant to any point involved in the appeal was written by plaintiffs June 14, 1904-, and asked defendant to send an inspector at once to take up two carloads of handles and for advice where to ship. The letter said:

“If you will let us know what kind of cars you will want to ship in, we will order them in so as not to delay the shipment; our reason for wanting to get these two [507]*507carloads out soon is, that we have been much longer getting them made than we expected, and our plant cost us more than we figured, and we are short of money to pay for timber.”

On June 17, 1904, defendant, by its manager, George B. Durell, answered saying an inspector would be sent as soon as possible; that the only man available for the purpose was at South Campbell, Missouri, and he would he written to go to Manila as soon as possible. On June 20th plaintiffs wrote defendant of information they had received which looked like the arrival of the inspector would he delayed and saying: “If we would have to wait for the inspector until he finishes at Campbell, we will he compelled to shut down for the want of room and funds. If you could, have the inspector leave the Campbell handles and take up our two loads, or make us an advancement of about fifty per cent, say eight hundred dollars, on the two cars, this will enable us to build more room and go ahead with the work. ... Do the best for us you can; we do not want to shut down if possible to prevent it. We are getting some fine timber now. We note what you say in regard to getting all the 6-ft. hay fork handles we can, and will be governed accordingly.” On July 2, 1904, plaintiffs again wrote defendant saying no answer had been received to plaintiffs’ letter of June 20th; that they had ready for shipment three carloads of handles and defendant would greatly oblige by sending a check for $500 as an advance on these cars, as nothing had been heard from the inspector. Durell answered on July 11, 1904, saying defendant’s inspector at Campbell had been ordered to stop' work there and go to Manila, Arkansas, to take up what handles plaintiffs had on hand; that defendant could not allow plaintiffs to draw in advance of handles being-taken up. On August 5,1904, plaintiffs wrote they had 15,600 hay fork handles loaded in a car and ready to ship; also 20,000 handles of different lengths which [508]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ritchie v. Metropolitan Life Insurance
66 P.2d 622 (Supreme Court of Kansas, 1937)
Metcalf v. R. D. Keene & Co.
164 So. 704 (Supreme Court of Florida, 1935)
Reed v. Cooke
55 S.W.2d 275 (Supreme Court of Missouri, 1932)
Bacon Piano Co. v. Medcalf Jewelry & Music Co.
40 S.W.2d 762 (Missouri Court of Appeals, 1931)
Hiatt Investment Co. v. Buehler
16 S.W.2d 219 (Missouri Court of Appeals, 1929)
Edwards v. School District No. 73
297 S.W. 1001 (Missouri Court of Appeals, 1927)
Big Muddy Coal & Iron Co. v. St. Louis Carterville Coal Co.
158 S.W. 420 (Missouri Court of Appeals, 1913)
Smith v. Means
155 S.W. 454 (Missouri Court of Appeals, 1913)
Kirkeby v. White
153 S.W. 279 (Missouri Court of Appeals, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
126 S.W. 969, 147 Mo. App. 497, 1910 Mo. App. LEXIS 572, Counsel Stack Legal Research, https://law.counselstack.com/opinion/laswell-v-national-handle-co-moctapp-1910.