Lange v. Brinegar

625 F.2d 812, 14 ERC 2001
Court of Appeals for the Ninth Circuit·Decided April 28, 1980·No. No. 77-2223·Published·Cited by 12 cases

Opinion

ALARCON, Circuit Judge.

Appellants have appealed from the judgment of the trial court denying injunctive and declaratory relief in connection with the construction of a segment of interstate highway 1-82.

I

PRELIMINARY FACTS

Interstate Highway 1-82 was authorized by Congress primarily to connect interstate [814]*814highway 1-90 which runs from Seattle, Washington to Boston, Massachusetts, and interstate highway I-80N, which runs from Portland, Oregon to Salt Lake City, Utah. The portion of 1-82 between Ellensburg, and Yakima, Washington is now complete and is not an issue on this appeal. Appellants challenge the validity of the approval of the forty-two mile segment of 1-82 which runs from Yakima to Prosser.

The remaining portions of 1-82 have been segmented into two parts: one portion running from the City of Yakima to the City of Prosser, and the other running from Pros-ser to the end of 1-82 at Oregon near Stan-field. When interstate 1-82 was originally authorized by the Department of Commerce in 1958, it was described as follows:

“From Ellensburg southerly along the Yakima River to Yakima, thence following the river in a southeasterly direction through the Yakima Indian Reservation to a point east of Toppenish, thence on a grade from the valley floor to a summit due south of Mabton on the Horse Heaven Hills, thence in a southeasterly direction to the Oregon state line at a crossing of the Columbia River at Umatil-la on route to a junction with U.S. 30 at Stanfield Junction in Oregon.”

II

CONTENTIONS ON APPEAL

Appellants contend that in their approval of the Prosser segment of 1-82, the State of Washington and the Federal Government failed to comply with the terms of the National Environmental Policy Act of 1969, 42 U.S.C. § 4321 et seq. and that the Federal Government failed to participate sufficiently in the drafting of the environmental impact statement as required by the Federal-Aid Highway Act of 1968, 23 U.S.C. § 138.

III

DISCUSSION

Segmentation of the Environmental Impact Statement

Appellants contend that under the terms of the National Environmental Policy Act, it was the duty of the defendants-respondents to file a single environmental impact statement covering the entire course of 1-82 from its beginning in Yakima to its connection with I-80N near Stanfield. We are told that the trial court erred in permitting the Yakima-Prosser portion of the highway to go forward without a complete analysis of alternatives and environmental impacts for the entire route.

Appellants argue that a far better location for the challenged portion of 1-82 would be a northerly route, away from the irrigated farmlands. It is further contended that this route would have been chosen had all requisite planning required by the National Environmental Policy Act been completed.

In May, 1964, the state of Washington completed a reconnaissance report which placed 1-82 in a specific location. Alternate routes were proposed for the entire portion of 1-82 between Yakima and the Oregon State line. Prosser was not indicated as a control point.

The Washington State Department of Highways selected route C which ran from Yakima to Granger, to Prosser, then southwesterly crossing the Columbia at Plymouth-Umatilla. This route ran on the south side of Yakima River through the Yakima Indian Reservation. This route was approved for funding by the Federal Government on February 12,1964.

Ultimately, route C had to be abandoned. The Yakima Tribal Council protested the proposed route insofar as it crossed over the Yakima Indian Reservation — requiring the condemnation of approximately 1,000 acres of land. Conversely, interested persons from the Tri-Cities opposed route C because it did not pass close enough.

In 1968, the State of Washington received authorization for the construction of a spur route, called 1-182 which would link 1-82 with SR-395. The route of 1-182 was described as “from a juncture with FAI-82 in the vicinity of Prosser easterly to a june-[815]*815ture with SR-395 at Pasco.” As of December, 1968, the approved route for 1-82 ran from Yakima through the Indian reservation to Prosser, southwesterly to the Oregon border at Umatilla, with a spur route to the Tri-Cities. In 1969, the Federal Highway Administration approved the Tri-Cities spur.

In April, 1970, this Court decided that the Secretary of Transportation had no statutory authority to condemn Indian Tribal lands for the construction of 1-82 without (1) the approval of the Secretary of Interior, whose department holds title to such lands in trust for the benefit of confederated tribes and bands of the Yakima Indian Nation, or (2) the passage of four months without disapproval. (U. S. v. 10.69 Acres of Land, More or Less, in Yakima County, 425 F.2d 317 (9th Cir. 1970).)

The present route resulted from studies undertaken to construct 1-82 so as to avoid passing through Yakima Indian Tribal lands.

In determining that segmentation of the Yakima-Prosser portion of 1-82 was proper, for purposes of examining potential environmental impact, the trial court relied upon Daly v. Volpe, 514 F.2d 1106 (9th Cir. 1975). In Daly, this Court held that a comprehensive E.I.S. is not required for a segment of an interstate highway where the following criteria are met:

1. Under FHA Policy and Procedure Memorandum 90-1 (PPM) the highway section must be as long as practicable to permit consideration of environmental matters on a broad scope. A highway section is defined under PPM 90-1 as “a substantial length of highway between logical termini (major cross-roads, population centers, major traffic generators, or similar major highway control elements) as normally included in a single location study.” PPM 90-1 § 3(a).

2. The section in question must have independent utility.

3. The length of highway selected must assure adequate opportunity for the consideration of alternatives.

4. The segment under consideration should fulfill important state and local needs.

In determining whether the evidence was sufficient to establish compliance with the requirements for a valid E.I.S. for a segment of an interstate highway as set forth in Daly, we are bound by the findings of the trial court unless they are clearly erroneous, (Sessions, Inc. v. Morton, 491 F.2d 854, 858 (9th Cir. 1974)). We have examined the record. The findings of the trial court that the right procedures under the National Environmental Policy Act were followed and that there was a reasonable consideration of alternatives are supported by the evidence.

Each of the criteria for determining when a segment is adequate for consideration in an independent E.I.S. was properly considered and applied by appellees.

One. The Yakima-Prosser segment runs between logical termini.

Free access — add to your briefcase to read the full text and ask questions with AI

Lange v. Brinegar, 625 F.2d 812, 14 ERC 2001 (9th Cir. 1980).

625 F.2d 812 (Lange v. Brinegar) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Sierra Club v. Marsh
701 F. Supp. 886 (D. Maine, 1988)
Coalition on Sensible Transportation Inc. v. Dole
642 F. Supp. 573 (District of Columbia, 1986)
Sierra Club v. John O. Marsh, Jr.
769 F.2d 868 (First Circuit, 1985)
Thomas v. Peterson
753 F.2d 754 (Ninth Circuit, 1985)
Lange v. Brinegar
625 F.2d 812 (Ninth Circuit, 1980)