Lake Charles Xxv, LLC v. United States

118 Fed. Cl. 717, 2014 U.S. Claims LEXIS 1098, 2014 WL 5180797
CourtUnited States Court of Federal Claims
DecidedOctober 15, 2014
Docket1:09-cv-00363
StatusPublished
Cited by6 cases

This text of 118 Fed. Cl. 717 (Lake Charles Xxv, LLC v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lake Charles Xxv, LLC v. United States, 118 Fed. Cl. 717, 2014 U.S. Claims LEXIS 1098, 2014 WL 5180797 (uscfc 2014).

Opinion

Contract Disputes Act; Excusable delay; Notice of delay; Waiver; No-waiver clause; Bad Faith

BRUGGINK, Judge.

OPINION

This is a breach of contract case brought pursuant to the Contract Disputes Act (“CDA”), 41 U.S.C. §§ 7101-7109 (2012). The case concerns a contract to design, build, and then lease to the government an office building in Louisiana. Plaintiff is appealing the Contracting Officer’s (“CO”) decision to terminate the contract for default. Defendant counterclaimed, asking the court to award it reprocurement costs and liquidated damages for the delay in project completion. Defendant moved for partial summary judgment that the termination for default was proper because plaintiffs delays were not excused and because plaintiffs bad faith claim is unfounded. Plaintiff cross-moved for summary judgment that the termination was wrongful because all of the delays were beyond its control and because defendant had an ulterior motive for terminating the contract. The motions are fully briefed. We heard oral argument on May 7, 2014, during which we asked for supplemental briefing on a question raised for the first time during oral argument. Because plaintiffs delays were not excused and because there is no evidence of bad faith, we grant defendant’s motion for partial summary judgment and deny plaintiffs cross-motion.

BACKGROUND

The General Services Administration (“GSA”) awarded contract GS07-B-16093 to Carotex Development, Inc. (“Carotex”) on May 31, 2006. Carotex agreed to design, build, and then lease to GSA a 12,733 renta-ble-square-feet office building in Lake Charles, Louisiana for use by the Social Security Administration (“SSA”). The specifications for the building exterior and the general floor plan were agreed upon and set forth specifically in the lease. The design and construction of much of the interior, especially improvements and finish elements, was anticipated by the parties to be a more iterative process.

The contract listed six steps for the design and construction of the more specific interior elements, which it termed “tenant improvements:” (1) the government would generate initial design intent drawings; (2) the government would finalize the design intent drawings and provide them to the lessor (contractor); (3) the lessor would create final working/construction drawings of the interior improvements in conformance with the design intent drawings; (4) the government would review the drawings, request any modifications, approve the drawings, and issue to the lessor the notice to proceed; (5) the lessor would construct the tenant improvements; (6) the government would inspect and then accept or reject the space. Def.’s App. 24 (solicitation for offers incorporated into the final contract). 1

The design intent drawings (“DIDs”) were “fully-dimensioned drawings of the leased space” and included information regarding finish elements such as furniture locations, telephone and data outlet locations, specifications for electrical and HVAC loads, and other “finish/color/signage selections.” Id. This information was used by the lessor to *719 prepare the construction drawings, which added all of the “mechanical, electrical, plumbing, fire safety, lighting, structural, and architectural improvements scheduled for inclusion” into the building. Id. Once the construction drawings were approved by GSA, it was to issue a notice to proceed, which would instruct the lessor to “obtain the necessary permits and ... commence construction of the space.” Id.

In a separate, earlier section, the contract stated that the parties would incorporate the final DIDs into the contract by a Supplemental Lease Agreement (“SLA”). Id. at 3 (paragraphs 13 and 14). This would begin a 180-day clock for completion of construction and delivery of the building to GSA/SSA. Id. After completion, the government would inspect the building, and, upon acceptance, the lease portion of the contract would begin with an annual rent of $287,766 for the first 10 years and $271,850 for five option years.

The lease incorporated by reference 48 C.F.R. § 552.270-18, the FAR’s default-in-delivery clause for GSA leases. 2 It provides in relevant part:

(a) With respect to Lessor’s obligation to deliver the premises substantially complete by the delivery date, time is of the essence. If the Lessor fails to work diligently to ensure its substantial completion by the delivery date or fails to substantially complete the work by such date, the Government may by notice to the Lessor terminate this lease.... The Lessor and the Lessor’s sureties, if any, are jointly and severally liable for any damages to the Government resulting from such termination, as provided in this clause....
(d) The Government shall not terminate this lease under this clause nor charge the Lessor with damages under this clause, if (1)the delay in substantially completing the work arises from excusable delays, and (2) the Lessor within 10 days from the beginning of any such delay (unless extended in writing by the Contracting Officer) provides notice to the Contracting Officer of the causes of delay. The Contracting Officer shall ascertain the facts and the extent of delay. If the facts warrant, the Contracting Officer shall extend the delivery date, to the extent of such delay at no additional costs to the Government. A time extension is the sole remedy of the Lessor.

48 C.F.R. § 552.270-18 (2014). 3 “Notice” is defined in the same FAR clause as “written notice sent by certified or registered mail, Express Mail or Comparable service, or delivered by hand. Notice shall be effective on the date delivery is accepted or refused.” Id. § 552.270-4(j).

The lease also incorporated a clause defining “excusable delays” as

(g) ... delays arising without the fault or negligence of Lessor and Lessor’s subcontractors and suppliers at any tier, and shall include, without limitation:
(1) acts of God or of the public enemy,
(2) acts of the United States of America in either its sovereign or contractual capacity,
(3) acts of another contractor in the performance of a contract with the Government,
(4) fires,
(5) floods,
(6) epidemics,
(7) quarantine restrictions,
(8) strikes,
(9) freight embargoes,
(10) unusually severe weather, or

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
118 Fed. Cl. 717, 2014 U.S. Claims LEXIS 1098, 2014 WL 5180797, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lake-charles-xxv-llc-v-united-states-uscfc-2014.