Lafarge Corp. v. Wolff, Inc.

977 S.W.2d 181, 1998 Tex. App. LEXIS 6017, 1998 WL 655515
CourtCourt of Appeals of Texas
DecidedSeptember 24, 1998
Docket03-97-00741-CV
StatusPublished
Cited by71 cases

This text of 977 S.W.2d 181 (Lafarge Corp. v. Wolff, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lafarge Corp. v. Wolff, Inc., 977 S.W.2d 181, 1998 Tex. App. LEXIS 6017, 1998 WL 655515 (Tex. Ct. App. 1998).

Opinion

POWERS, Justice.

Wolff, Incorporated sued Lafarge Corporation for breach of contract. A jury returned a verdict in favor of Wolff awarding Wolff $1,380,000 in actual damages and $207,000 in attorney’s fees. The trial court rendered judgment in favor of Wolff for $1,323,911 in actual damages, $63,000 in prejudgment interest, and $207,000 in attorney’s fees for a total of $1,593,911. We will reverse the judgment and remand the cause for a new trial.

THE CONTROVERSY

In 1980, Wolff entered into a “Clay Mining and Delivery Contract” with General Portland, Inc., Lafarge’s corporate predecessor. 1 The contract required Wolff to quarry clay from property owned by Lafarge and to deliver the clay to Lafarge’s cement manufacturing plant near New Braunfels. Wolff was required to provide its own equipment, materials, labor, machinery, and supplies. In addition to mining and hauling the clay, Wolff had to maintain the necessary haul roads and pump water out of the clay pits.

The contract was a requirements contract under which Lafarge was required to pay Wolff a monthly service charge equal to the greater of one of two calculations: either the “contract” price, or the “minimum” price. The contract price amounted to $3.59 per ton of clay mined and delivered. The minimum price amounted to $2.25 per ton plus an additional “base amount,” which was reached by adding a figure from a table. This figure was based on the amount of clay delivered in the preceding month. 2 The contract also provided:

Once the Base Amount has increased pursuant to the [included] schedule, it shall not be reduced even though the number of tons delivered to the Plant declines to a lower level.

Thus, if several months passed in which La-farge required little clay, Wolff could count on receiving at a minimum the “base amount.” At the time events giving rise to the controversy took place, the base amount *184 had reached $20,000 per month. The contract had a term of five years.

In 1985, the five years expired. The parties renewed the contract with changes. Nelson Wolff, president of Wolff, and J.T. Hill, the plant manager at Lafarge’s New Braunfels plant, negotiated the new terms. Under the new terms, Wolff was required to haul away the “by-pass dust” that was generated during the clay mining process at no extra charge and to make additional capital investments of about $375,000 for equipment and facilities at the site of the clay pit. In exchange for these added obligations, Wolff obtained from Lafarge a right to renew the contract for two additional five-year periods. 3

Hill sent the proposed contract to La-farge’s headquarters for approval. Hill’s superiors returned the document, having added the language emphasized in the following passage:

The contractor shall have the option to further renew the contract for two (2) additional five-year periods on the same terms and conditions by giving written notice. ... Notice to be given 90 days prior to the 28th day of May, 1995 to extend the contract to May 27, 2000, provided however that nothing contained herein shall obligate owner to continue operation of owner’s plant or the manufacture of cement.

After discussion, the parties signed the contract.

In September 1994 Lafarge sold the concrete plant to Sunbelt Cement. With no advance notice to Wolff, Lafarge sent a letter to Wolff stating that Wolffs services would no longer be needed. Lafarge stated simply that it had sold the plant and was therefore “terminating” the contract pursuant to the italicized proviso above. Sunbelt hired another hauler.

Wolff thereupon found itself with no contract and idle clay-hauling equipment it had purchased to perform the Lafarge contract. Wolff gave Lafarge notice it was exercising its second option to extend the contract to the year 2000, and demanded continued payment of the monthly $20,000 “base amount.” Lafarge refused to pay. This lawsuit ensued.

DISCUSSION AND HOLDINGS

Lafarge focuses on four issues on appeal. First, Lafarge contends it did not breach the contract. Second, Lafarge contends that even if it breached the contract, Wolff suffered no damages or the damages were improperly calculated. Third, Lafarge contends the evidence was insufficient to support the award of attorney’s fees. Finally, La-farge contends the trial court erred in rendering partial summary judgment in favor of Wolff on Lafarge’s counterclaim.

Breach

Lafarge argues in points of error six through eight that the evidence does not support a finding that it breached the contract. 4 Lafarge argues it had a right to terminate the contract unilaterally upon the sale of the plant. Lafarge relies on the contract proviso “that nothing contained herein shall obligate owner to continue operation of owner’s plant or the manufacture of cement.”

The trial judge found this clause to be ambiguous, and allowed the parties to testify as to their intent regarding the proviso. Whether a contract is ambiguous is a question of law that must be decided by examining the contract as a whole in light of the circumstances existing when the contract was made. National Union Fire Ins. Co. v. CBI Indus., Inc., 907 S.W.2d 517, 520 (Tex.1995); Coker v. Coker, 650 S.W.2d 391, 394 (Tex.1983). A contract is not ambiguous if it can be given a definite or certain meaning as a matter of law. CBI, 907 S.W.2d at 520; *185 Coker, 650 S.W.2d at 393; Universal C.I.T. Credit Corp. v. Daniel, 150 Tex. 513, 243 S.W.2d 154, 157 (Tex.1951). On the other hand, if the contract is subject to two or more reasonable interpretations after applying the pertinent rules of construction, the contract is ambiguous, which creates a fact issue regarding the parties’ intent. Columbia Gas Transmission Corp. v. New Ulm Gas, Ltd., 940 S.W.2d 587, 589 (Tex.1996); Daniel, 243 S.W.2d at 157; see also generally CBI, 907 S.W.2d at 520. If the instrument is ambiguous, the court may admit extraneous evidence to determine its true meaning. Enochs v. Brown, 872 S.W.2d 312, 319 (Tex.App.—Austin 1994, no writ); Connelly v. Paul, 731 S.W.2d 657, 660 (Tex.App.—Houston [1st Dist.] 1987, writ ref d n.r.e.).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rose v. Equis Equine
Fifth Circuit, 2025
Visa Inc. v. Sally Beauty Holdings, Inc.
Court of Appeals of Texas, 2021
Norhill Energy LLC v. McDaniel
517 S.W.3d 910 (Court of Appeals of Texas, 2017)
Daisy Wanda Garcia v. Thomas Lee Baumgarten
Court of Appeals of Texas, 2015
RSL-3B-IL, Ltd. v. Prudential Insurance Co. of America
470 S.W.3d 131 (Court of Appeals of Texas, 2015)
Jeffrey May v. Ticor Title Insurance
422 S.W.3d 93 (Court of Appeals of Texas, 2014)
ARV Offshore Company, Limited v. Con-Dive, L.L.C.
514 F. App'x 524 (Fifth Circuit, 2013)
Sharifi v. Steen Automotive, LLC
370 S.W.3d 126 (Court of Appeals of Texas, 2012)
WPS, Inc. v. Surface Productions Systems, Inc.
369 S.W.3d 384 (Court of Appeals of Texas, 2012)
Hicks v. Pilgrim Poultry, G.P.
299 S.W.3d 249 (Court of Appeals of Texas, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
977 S.W.2d 181, 1998 Tex. App. LEXIS 6017, 1998 WL 655515, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lafarge-corp-v-wolff-inc-texapp-1998.