WPS, Inc. v. Surface Productions Systems, Inc.

369 S.W.3d 384, 2012 WL 310937
Court of Appeals of Texas·Decided January 31, 2012·No. 01-10-00041-CV·Published·Cited by 2 cases

Opinions

OPINION

TERRY JENNINGS, Justice.

Appellant/cross-appellee, WPS, Inc. (“WPS”), challenges the trial court’s take-nothing judgment, entered after a jury trial, against it and in favor of appellee, Expro Americas, LLC (“Expro Americas”), in WPS’s suit against Expro Americas and its subsidiary, appellee/cross-ap-pellant, Surface Production Systems, Inc. (“SPS”), for breach of contract, quantum meruit, and promissory estoppel. In its sole issue, WPS contends that the trial court erred in granting Expro Americas judgment notwithstanding the verdict on the ground that there is no evidence supporting the jury’s findings against Expro Americas.

Expro Americas, in its cross-points,1 challenges the jury’s findings made against it, and it joins SPS, in SPS’s cross-appeal, challenging the trial court’s judgment entered against SPS on WPS’s claims. In eight issues, Expro Americas and SPS contend that there is no evidence that there was an enforceable contract between them and WPS for the purchase of specially made equipment, Expro Americas and SPS’s requirement in its purchase orders that they first issue a “release to proceed” before WPS was to make the “specialized equipment” rendered any promise “illusory,” the requirement of the issuance of a “release to proceed” constituted a “condition precedent,” the “progress payment and cancellation charges” awarded to WPS by the jury are not legally recoverable damages on WPS’s breach-of-eontract claim, the trial court erred “in commenting on the evidence and erroneously instructing the jury as to contract interpretation,” there is no evidence to support WPS’s quantum meruit or promissory estoppel claims, and the trial court erred in not admitting into evidence Expro Americas and SPS’s pretrial offers to WPS to “pay cancellation charges.”

[388]*388We reverse the trial court’s judgment notwithstanding the verdict in favor of Ex-pro Americas, and we render judgment in favor of WPS on its claims against Expro Americas. We affirm the remaining portions of the judgment.

Factual and Procedural Background

In early 2006, SPS, a wholly-owned subsidiary of Expro Americas, was involved in negotiations with Conoco Venezuela to work on the development of an oil and gas field in Venezuela. In furtherance of this proposed development, SPS solicited WPS, which was in the business of making gas compressors, for a proposal to construct three gas injection compressor packages to be installed at an offshore Interim Production Facility (the “IPF”) for the temporary processing of crude oil.

Following preliminary negotiations between the parties, Tom Caime, WPS’s engineering supervisor, submitted to SPS on April 10, 2006 a proposal for the delivery of three gas compressor packages with a total net price of $4,143,066 and an estimated “ship date” of “20-22 weeks after order acceptance by an officer of WPS.” Caime set forth detailed “terms of payment” with 10% of the purchase price due “[u]pon WPS[’s] acceptance of order,” a cancellation charge of “2% of contract value” if the order was cancelled “within 30 calendar days,” and separate charges payable to certain providers of component parts, including $27,000 for Reliance, the proposed supplier of the motors, and $107,000 for Dresser-Rand, the proposed supplier of the compressors. Caime noted that WPS’s proposal was subject to its “standard terms and conditions of sale,” which he attached, and the “Crine/Logic terms and conditions,” which had been previously provided to WPS by SPS, were “currently under review.”

On April 11, 2006, Kevin Galvin, SPS’s vice president, sent WPS a letter expressing “Expro’s” “intent to issue a Purchase Order” for the three injection compressors for a total price of $4,143,066, but requiring that delivery be “on or before September 5, 2006.” In regard to “[pjayment [tjerms,” Galvin provided that $217,361 would be paid “on submittal of mechanical installation drawings” and 10% would be paid upon obtaining a “Release to Proceed (to be before [May 11, 2006]).” Galvin noted that terms and conditions were “to be agreed” upon and a “[confirming [p]ur-chase [o]rder” would be issued “on or before ... April 17, 2006.”

On April 12, 2006, Caime, in response to “Expro’s” “letter of intent,” sent Galvin a reply e-mail stating that WPS needed an “immediate Release to Proceed” before it could begin work and “order the critical equipment without which the price and delivery of our supply will be extended.” Caime noted that “any delay in the purchase” would cause “the supply of [the] packages [to] suffer,” WPS could not order equipment without the Release to Proceed, and it could not “proceed very far with engineering and design without vendor drawings, studies, and data that are not forthcoming without our purchase of that equipment.” Caime explained that the Dresser-Rand compressor price that WPS used in its proposal was set to expire the next day, a price increase would apply afterwards, and other “vendor proposals” would also expire before the “suggested [May 11] date.” Caime requested other “modifications” to the letter of intent, including a shipping date calculated 20 to 22 weeks from acceptance of “written” and “firm” purchase order, “cancellation charges as noted in [WPS’s] proposal,” and terms of payment of 10% “with purchase order” and 10% on submittal of “approval drawings.” Caime requested an agree[389]*389ment “today,” so that WPS could place equipment orders the following day.

On April 12, 2006, Galvin, in a reply email to Caime, stated that WPS was “released to proceed on the order subject to” the conditions that “[i]f [the] order [is] cancelled on or before May 11, 2006, ... Expro’s financial liability is the cancellation charges per your proposal” and the terms and conditions “need to be agreed for the [purchase order].” Galvin agreed to “incorporate [WPS’s] payment terms into the [purchase order]” and noted that he “plan[ned] to issue” the purchase order the next day, but was “waiting” on “approval.” Caime immediately responded with an e-mail stating that WPS would “await [SPS’s] purchase order tomorrow” and “order the capital equipment immediately thereafter.”

Also on April 12, 2006, Griselda Ibarra, a SPS business analyst, sent Caime an email with an attached purchase order (the “first purchase order”). She stated that the first purchase order was being provided “to proceed with the purchase of the [g]as [i]njeetion [compressors.” The first purchase order provided for a delivery date of September 12, 2006, a total net price of $4,143,066 for the purchase of three gas injection compressor packages, a “[d]eposit to secure the delivery of the specified equipment in order to meet the Project schedule” in the amount of $414,307 (10% of the total purchase price) that would be payable “[u]pon [acceptance of this [o]rder,” and the payment of another 10% “[u]pon submittal of [djrawings and Release to Proceed (to be on or before [May 8, 2006]).” It further provided that the order would be “subject to mutual agreement of [t]erms and [conditions between WPS and Expro” and “valid until [May 8, 2006] unless Expro issue[d] a revised [p]urchase [o]rder to proceed.”

On April 13, 2006, Tom Sawyer, responding by e-mail to Galvin on behalf of WPS regarding the first purchase order, explained that WPS could not accept the first purchase order “in its present form and content” and the parties “must resolve these issues today before 2:00 p.m. or risk missing the deadline for the Dresser-Rand price increase.” Sawyer also forwarded Galvin an e-mail from Caime wherein he provided more detail about WPS’s concerns.

Free access — add to your briefcase to read the full text and ask questions with AI

WPS, Inc. v. Surface Productions Systems, Inc., 369 S.W.3d 384, 2012 WL 310937 (Tex. Ct. App. 2012).

369 S.W.3d 384 (WPS, Inc. v. Surface Productions Systems, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Rand Mintzer v. Houston Medical Testing Services, Inc.
417 S.W.3d 691 (Court of Appeals of Texas, 2013)