MG Building Materials, Ltd. v. Moses Lopez Custom Homes, Inc.

179 S.W.3d 51, 2005 WL 1774153
CourtCourt of Appeals of Texas
DecidedAugust 16, 2005
Docket04-04-00336-CV
StatusPublished
Cited by66 cases

This text of 179 S.W.3d 51 (MG Building Materials, Ltd. v. Moses Lopez Custom Homes, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MG Building Materials, Ltd. v. Moses Lopez Custom Homes, Inc., 179 S.W.3d 51, 2005 WL 1774153 (Tex. Ct. App. 2005).

Opinion

OPINION

Opinion by

PHYLIS J. SPEEDLIN, Justice.

MG Building Materials, Ltd. appeals a final judgment rendered against it in a suit by a homebuilder to foreclose the builder’s statutory mechanic’s lien and for damages based on breach of contract and promissory estoppel. Because we conclude the homebuilder had assigned all of its rights, privileges, and equities associated with the residential construction contract, we reverse the trial court’s judgment as to the mechanic’s lien and affirm the remainder of the judgment.

Factual and Procedural BACKGROUND

Douglas and Ana Gonzales (collectively, “Gonzales”) entered into a new home contract with Moses Lopez Custom Homes, Inc. (“Lopez”), a custom homebuilder, to purchase a lot and construct a new home for the total sales price of $120,740.00. The contract, although not dated, was executed on or about October 30, 2001, and specified that Lopez would complete all improvements in accordance with the homeowner’s blueprints, would complete construction within eight months, and would be allowed six draws for working capital and construction overhead.

Gonzales subsequently selected MG Building Materials, Ltd. (“MG”) to provide interim financing for the construction project. On November 20, 2001, Gonzales executed a series of documents. Gonzales signed a real estate hen note payable to MG in the amount of $143,740.00 to fund construction of the home. To secure the note, Gonzales signed a construction deed of trust and security agreement through which Gonzales transferred title to the home and real property to a trustee, with MG as the beneficiary. In addition, Gonzales executed a mechanic’s Ken contract with Lopez in the amount of $120,740.00, in which Lopez agreed “to furnish the materials and labor and to complete the Construction on the Property on or before the Completion Date.” The mechanic’s Ken contract further provided, “[t]o secure payment of the Note, Owner [Gonzales] grants to Contractor [Lopez] a mechanic’s, artisan’s and materialman’s Ken on the Property and on all improvements and fixtures on the Property at any time.” Finally, Lopez simultaneously executed an assignment of Ken in favor of MG which transferred and assigned to “the Lender [MG] all of Contractor’s [Lopez’s] rights, privileges and equities under and by virtue of the indebtedness, Ken and Mechanic’s Lien Contract.”

Lopez began construction on the Gonzales home in December 2001. Between *56 December 2001 and February 2003, Lopez submitted six draw requests to MG for payments to cover the completed stages of construction. All of these draw requests were processed and paid by MG. In March 2003, Lopez submitted his seventh and final draw request in the amount of $17,044.51 to cover the costs of completing the home. At the time the request was submitted, only $4,683.87 remained under the Gonzales’ note. MG issued a check for $4,683.87, but gave it to Alamo Title Company to hold in escrow until Lopez and Gonzales reached an agreement on payment of the final draw request in excess of the funds available under the note.

Because of their pending divorce, Mr. and Mrs. Gonzales never obtained permanent financing to close on the home and defaulted on their note to MG. As a result, MG never released the escrowed $4,683.87 to Lopez. MG posted the Gonzales residence for foreclosure, and foreclosed its deed of trust lien on April 1, 2003. Prior to that foreclosure, however, on March 28, 2003, Lopez filed an “Original Contractor Affidavit of Claim for Mechanic’s Lien” in the amount of its final draw request for $17,044.51. Lopez then filed suit on March 31, 2003, seeking foreclosure of the mechanic’s lien and damages against MG for breach of contract and promissory es-toppel. Prior to trial, Lopez successfully obtained a partial summary judgment foreclosing its lien against the removable improvements at the Gonzales’ residence. Lopez and MG then proceeded to trial before a jury on the remaining issues. The trial court submitted special issues to the jury on breach of contract, promissory estoppel, and Lopez’s attorney’s fees. The jury answered all questions in favor of Lopez.

The trial court entered judgment in favor of Lopez incorporating both the partial summary judgment and the jury’s verdict. MG now appeals from that final judgment claiming the trial court erred in foreclosing Lopez’s mechanic’s lien because the lien had been assigned to MG, and challenging the sufficiency of the evidence to support the jury’s verdict on breach of contract, promissory estoppel, and attorney’s fees.

PARTIAL SUMMARY JUDGMENT ON LlEN CLAIM

The first issue presented by MG is whether the trial court erred in granting partial summary judgment foreclosing Lopez’s statutory lien and ordering the sale of eight removable items located on the Gonzales property. Because rendition of summary judgment involves a question of law, we review the trial court’s decision de novo. Natividad v. Alexsis, Inc., 875 S.W.2d 695, 699 (Tex.1994). The movant for a traditional summary judgment must show that there are no genuine issues of material fact and that it is entitled to judgment as a matter of law on a ground expressly set forth in the motion. Tex.R. Civ. P. 166a(c); Nixon v. Mr. Prop. Mgmt. Co., 690 S.W.2d 546, 548-49 (Tex.1985). When reviewing a summary judgment, we take all evidence favorable to the non-movant as true. Nixon, 690 S.W.2d at 548-49. If the movant establishes its right to summary judgment as a matter of law, the burden then shifts to the non-movant to raise a fact issue that would preclude summary judgment. City of Houston v. Clear Creek Basin Auth., 589 S.W.2d 671, 678 (Tex.1979).

Lopez filed a traditional motion for partial summary judgment on the ground that it had perfected a statutory mechanic’s and materialman’s lien on the Gonzales residence and was entitled to foreclosure as a matter of law. In support of its motion, Lopez attached the affidavit of Moses Lopez, president of Moses Lopez Custom Homes, Inc., stating in relevant part that: (1) his company had entered into a “New *57 Home Contract” with Gonzales on October 30, 2001 to construct a residence in Atasco-sa County, Texas; (2) his company was owed $17,044.51 under the final draw request on the Gonzales residence (consisting of $12,044.51 in unreimbursed expenses and $5,000.00 in builder’s fees); (8) he had signed and timely filed in the Atas-cosa County real property records an “Original Contractor Affidavit of Claim for Mechanic’s Lien” on March 28, 2003; and (4) he was familiar with the Gonzales house and eight items were “installed at the Gonzales residence [that] can be removed without damage to the items themselves or to the residence.” 2 A “Certified Contractor Affidavit of Claim” was also attached as summary judgment evidence.

Lopez’s summary judgment motion, supporting affidavit, and affidavit of claim set forth its status as an original contractor under the Texas mechanic’s lien statute. See Tex. PhopUode Ann. § 53.021(a)(2)(Vernon Supp.2004-2005).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Discover Bank v. Marcus Miller
Court of Appeals of Texas, 2024
S. Williams v. Wells Fargo Bank, N.A., et a
884 F.3d 239 (Fifth Circuit, 2018)
Ambrose Claybar v. Samson Exploration, LLC
Court of Appeals of Texas, 2018
Elness Swenson Graham Architects, Inc. v. RLJ II-C Austin Air, LP
520 S.W.3d 145 (Court of Appeals of Texas, 2017)
Country Title , L.L.C. v. Morenike Jaiyeoba
Court of Appeals of Texas, 2015
Mirta Zorrilla v. Aypco Construction II, LLC and Jose Luis Munoz
421 S.W.3d 54 (Court of Appeals of Texas, 2013)
Lone Star Air Systems, LTD v. David Powers
401 S.W.3d 855 (Court of Appeals of Texas, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
179 S.W.3d 51, 2005 WL 1774153, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mg-building-materials-ltd-v-moses-lopez-custom-homes-inc-texapp-2005.