This text of 54 N.E.2d 505 (L. E. Myers Co. v. Sanitary District) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
L. E. Myers Co. v. Sanitary District, 54 N.E.2d 505, 386 Ill. 542 (Ill. 1944).

Opinion

Mr. Justice Murphy

delivered the opinion of the court

In an action started by The L. E. Myers Company in the superior court of Cook county, a writ of mandamus was issued which commanded the officials of the defendant, the Sanitary District of Chicago, “forthwith to pay the sum of * * * ($5,885.23) of the funds of The Sanitary District of Chicago to the plaintiff, The L. E. Myers Company, a corporation.” The Appellate Court affirmed the judgment and the sanitary district’s petition for leave to appeal to this court was granted. The Myers company will be referred to as plaintiff and the sanitary district as defendant.

As grounds for reversal, defendant contends (a) that plaintiff has not shown a clear legal right to a writ of mandamus; (b) that the action was barred by the statute of limitations, and (c) that the judgment and writ were erroneous in directing defendant to pay generally when no appropriation had been made to meet such payment.

In March, 1924, the parties hereto entered into a written contract Whereby plaintiff was to furnish all the material, equipment and labor necessary to the removal of certain spoil banks, the property of the defendant. The contract is not in evidence but, from admissions contained in the pleadings and the evidence, it appears that plaintiff’s compensation was to be determined on a yardage basis of $1.32 per cubic yard for a part of the work, and 32 cents per cubic yard for the remainder. The work was started in May and completed in October. Defendant accepted the same October 16, 1924, and prior to acceptance or immediately thereafter paid plaintiff $41,196.50. Plaintiff did not reduce its claim to judgment but, in 1941, instituted this suit for a writ of mandamus to command the defendant to pay $5885.23. The action is not founded on the written contract in the sense that the issuance of a writ of mandamus would, in effect, direct specific performance of some of the provisions of the contract but it is based on the theory that defendant, being liable to pay said amount, has officially recognized such liability and taken action in reference to it. which must be given the legal effect and conclusiveness of a judgment. Whether defendant has so obligated itself is one of the maih controversial points in the case.

We are not concerned with a question of the liability of defendant to pay a sum greater than $5885.23, but whether official action of the representatives of the defendant has been such as to bring plaintiff’s claim for said amount within the rule which permits the issuance of a writ of mandamus to coerce the payment of a claim which has not been reduced to judgment. The rule is well established that mandamus will not lie on behalf of á petitioner until it has been shown that he has a clear legal right to the writ. (People ex rel. Rude v. County of La Salle, 378 Ill. 578; People ex rel. Mason v. Reddick, 181 Ill. 334; People ex rel. German Ins. Co. v. Getzendaner, 137 Ill. 234.) In the application of this rule it was said in the Reddick case, that “mandamus will only lie to enforce the payment of a claim ascertained to be due. Ordinarily this ascertainment is by way of a judgment. Doubtless where a municipality, by its legally constituted authorities, ascertains a claim to be due and unconditionally orders it paid, that order has the same effect as a judgment; but so long as the order is a-conditional one mandamus will not aid parties to collect it, unless an offer is made to comply with the conditions imposed.” In Hooper v. Snow, 325 Ill. 53, it was held that if the right of the petitioner must first be fixed or the duty of the officer sought to be coerced must first be determined, mandamus is not the proper remedy. See also People ex rel. Comrs. Big Lake Dist. v. Dixon, 346 Ill. 454.

The evidence shows that soon after the defendant accepted the work, October 16, 1924, "a difference arose between the parties as to the yardage that should be paid for at $1.32 per cubic yard. In plaintiff’s letter, dated November 5, 1924, addressed to defendant, it called attention to certain demands it was making and, on the basis of them, plaintiff claimed there was $35,266 due it. On November 30, 1925, plaintiff directed another letter to defendant in which it stated: “We wish to call to your attention that the last estimate which we received from you was dated October 1,1924, and showed 95% completion. The amount that had been reserved as per contract, I2j4% of payments, amounted to $5,885.23. The total estimated balance to be received by us under the contract being estimated at $9,203.43. We had heard indirectly that on or about October nth, your Engineering Department had made a final estimate but we never received this final estimate of the contract nor never received the 12%% retained. We subsequently rendered a claim for extra yardage which so far as we know has not been acted upon.” If defendant made any reply to said letters, it does not appear in the record.

The record does not disclose that plaintiff did anything after sending the letter of November 30, 1925, until October 1, 1941, when, by its attorney, it sent a letter making demand for “that which the records of the District show to be due.” It also stated in the letter that “It [the Myers company] has refused to make claim for the entire amount which it once regarded as being due.” Soon after the transmission of this letter to defendant the instant suit was started. In its petition plaintiff set up the making of the contract, its performance, defendant’s acceptance of the work on October 16, 1924, the payment of $41,196.57 on the contract, and alleged “that there is still due and owing from the defendant to your petitioner on account of said work done and performed as aforesaid the sum of Five Thousand Eight Hundred Eighty Five Dollars and Twenty-three cents ($5,885.23,) which said sum represents the moneys retained by the defendant pending final completion and acceptance of the said work specified in said written agreement.”

It will be noted that in plaintiff’s letter of November 30, 1925, it is stated that the $5885.23 withheld is 12*4% of the amount due on the estimate of the work completed to October 1, 1924, which, it was said, was 95% of the entire contract job. It may be inferred that, soon after October 1, 1924, plaintiff completed the work which, according to its letter of November 30, 1925, would entitle it to $9203.43 in addition to the $41,196.57 already paid. In the letter of October 1, 1941, no reference is made to the difference between $9203.43 and the $5885.23 or for the extra allowance of $35,266 referred to in the letter of November 5, 1924.

From the facts related, it is obvious that from the completion of the work to the sending of the letter of October 1, 1941, the amount due from defendant to plaintiff was not fixed. It is shown that defendant withheld $5885.23, but the terms and conditions under which the same was withheld do not appear in the record and, in the absence of the same or of some explanation, it can not be determined whether defendant was liable for the payment of said sum so long as plaintiff had its demands pending for a greater amount.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Durham v. Barrett
305 N.E.2d 201 (Appellate Court of Illinois, 1973)
People Ex Rel. Miller v. City of Granite City
231 N.E.2d 272 (Appellate Court of Illinois, 1967)
People Ex Rel. Bourne v. Johnson
199 N.E.2d 68 (Appellate Court of Illinois, 1964)
Thornton v. Ramsey
165 N.E.2d 65 (Appellate Court of Illinois, 1960)
Betebenner v. Board of Education
84 N.E.2d 569 (Appellate Court of Illinois, 1949)

Cite This Page — Counsel Stack

Bluebook (online)
54 N.E.2d 505, 386 Ill. 542, Counsel Stack Legal Research, https://law.counselstack.com/opinion/l-e-myers-co-v-sanitary-district-ill-1944.