Kuswa & Associates, Inc. v. Thibaut Construction Co.

440 So. 2d 1338, 1983 La. App. LEXIS 9439
CourtLouisiana Court of Appeal
DecidedOctober 12, 1983
DocketNo. 82-CA-48
StatusPublished
Cited by3 cases

This text of 440 So. 2d 1338 (Kuswa & Associates, Inc. v. Thibaut Construction Co.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kuswa & Associates, Inc. v. Thibaut Construction Co., 440 So. 2d 1338, 1983 La. App. LEXIS 9439 (La. Ct. App. 1983).

Opinion

BOWES, Judge.

This case comes to us on cross-appeals filed by plaintiff and defendant, after a judgment by the trial court awarding plaintiff the sum of $2,921.50, and dismissing defendant’s reconventional demand. We reverse in part, affirm in part and amend.

Kuswa filed suit originally against Thi-baut Construction Company for alleged damages in the form of lost profits, resulting from Thibaut’s termination of various construction contracts with Kuswa. Thi-baut reconvened to recover costs it claimed it incurred in repairing work purportedly done improperly by Kuswa. Additionally, Thibaut asserted a claim for damages in an amount equal to the “unnecessary” interest expenses which it supposedly incurred on its interim construction loans “as a result of Kuswa’s unreasonable delay in performance of the contracts.” The district court’s dismissal of the reconventional demand was made without comment. However, the trial judge did state in his reasons for judg[1340]*1340ment that he found the contracts in question to have been made on a building-by-building basis, rather than “contingent” on plaintiffs performing the entire job. It is with this finding that we disagree.

On February 9, 1979, pursuant to a discussion with one Bill Christy (then supervisor of Thibaut Construction Company), Kuswa submitted a three-page “Proposal”, describing in detail the proposed work and the price — $2,850.00 per four-plex for painting and 14½ cents per square foot of sheet-rock.

At the top of the page in this particular document is this vital language on which this controversy hinges: “This bid is contingent on Kuswa & Associates, Inc., doing the same work on all four-plexes which are sixty-two (62) in number.”

This proposal, which states in the first sentence that it is a bid, was accepted by Thibaut, who, on March 28, 1979, entered into a “Sub-Contractor Base Agreement” with Kuswa, which agreement identifies this contract as one for painting and sheet-rock: “1) The work to be performed hereunder is generally described as Bid from Kuswa & Associates, Inc.”

Other than the standard form provisions, the only additional language refers to Price Lists, which state:

“See attachment schedule A
See attachment schedule B”

And, at the very top of the contract, above all other writing: ,

“See attachment I for the above (16) points.”

Attachment I, according to the trial testimony, evolved when Kuswa, uncomfortable about “vagueness” in some of the provisions (the “16 points”), elaborated on certain of them. For example, provision No. 12, formerly, provided:

12) From time to time under this agreement THIBAUT Construction Co., Inc. shall pay to Contractor upon completion and presentation of applicable Work Orders to the Superintendent in charge for his approval, sums in accordance with this agreement. Contractor expressly agrees in this context that he waives all rights to statutory or Constitutional liens on any job not fully performed by Contractor under this agreement.

Kuswa, in its attachment, added:

“12. Yes — with payment agreements made before building starts.”

Attachments A and B are merely payment schedules for painting and sheetrock —$200.00 to prime the exterior, $1,500 to complete the interior, etc. That base agreement, along with attachments I, A and B, were contended by Thibaut to constitute the entire initial contract, without reference to the February 9th proposal. Such, too, was the opinion of the trial judge. This contention is one which we find untenable.

This so-called initial agreement (dated March 28th) does not, in and of itself and including the attachments, sufficiently identify the work to be done. This “contract” makes no mention of the address of the property, and does not specify the quality of materials, detail of workmanship, etc.

Broadly considered, specifications of a contract can be or may be included within the body of the contract or agreement, or it may form the contents of a separate document properly identified with the contract itself. Generally, specifications have to do with spelling out in detail the quality, quantity, character or conditions under which the subject matter of the contract may be or shall be performed. Specifically, the specifications should be definite, certain, explicit and express, [emphasis supplied] Toye Bros. Yellow Cab Co. v. City of New Orleans, 264 So.2d 768 (La.App. 4th Cir.1972).

This court finds that the word “bid” referred to in the March 28th contract itself concerns the February 9, 1979 document, and thereby incorporates this document into the initial contract itself.

Contracts need not be imposed in a single instrument but may include documents by reference thereto. Calcon, Inc. v. Young Companies, Inc., 822 So.2d 883 (La.App. 1st Cir.1975). We find the wording of [1341]*1341the phrase “Bid from Kuswa & Associates, Inc.” sufficiently clear to describe the proposal of February 9th. We further find that incorporation of this bid (February 9th) is a necessary action in order to give sense to the contract as the February 9th instrument details the preparation, painting, staining, sheetrock size, quality of texture, etc.

The pay schedules and enlargement on the base provisions (the attachments) do not provide such specifications. We find therefore that the trial court was in error when it concluded that the word “bid” referred solely to the attachments “A” and “B”.

We are of the opinion that “bid” referred to the proposal of Kuswa dated February 9th as it delineated the specifications for the entire contract initially contemplated by the parties for painting and sheetrocking. Ergo, the Sub Contractor Base Agreement of March 28th, with attachments I, A, and B, and the February 9th proposal, comprise the entire original contract between Kuswa and Thibaut. The contract considered without the February proposal is not of itself meaningful within the contemplation of Civil Code articles 1951 and 1955.1

But an agreement must be interpreted as a whole and, where possible, effect should be given to all clauses of an agreement; and a construction will be preferred which gives a reasonable meaning to each clause of an agreement, rather than one which leaves any clause useless or inexplicable. Articles 1951, 1955, LSA-Civil Code, and jurisprudence thereunder. [emphasis supplied]. Green v. Southern Furniture Co., 94 So.2d 508 (La.App. 1st Cir.1957)

It fellows, therefore, from the wording of the February 9th bid, that the contract was for 62 four-plexes, contemplated by Mr. Thibaut, as the number of buildings yet to be constructed at the time of the contract.

Defendant argues that had the proposal in question been intended to be part of the March 28th contract, it would have been so identified as another attachment. Considering the rather vague manner with which business dealings between the parties was handled, the court finds this argument somewhat specious.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kuswa & Associates, Inc. v. Thibaut Const. Co.
463 So. 2d 1264 (Supreme Court of Louisiana, 1985)
Kuswa & Associates, Inc. v. Thibaut Construction Co.
445 So. 2d 428 (Supreme Court of Louisiana, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
440 So. 2d 1338, 1983 La. App. LEXIS 9439, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kuswa-associates-inc-v-thibaut-construction-co-lactapp-1983.