Guidry & Swayne v. Miller

47 So. 2d 721, 217 La. 935, 1950 La. LEXIS 1038
CourtSupreme Court of Louisiana
DecidedJune 30, 1950
DocketNo. 39517
StatusPublished
Cited by11 cases

This text of 47 So. 2d 721 (Guidry & Swayne v. Miller) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Guidry & Swayne v. Miller, 47 So. 2d 721, 217 La. 935, 1950 La. LEXIS 1038 (La. 1950).

Opinion

HAWTHORNE, Justice.

Plaintiff instituted this suit seeking to recover damages for the breach of a building contract to construct a dwelling in the City of New Orleans, the amount of damages prayed for being the expenses incurred for labor, materials, supplies, and extras by it in the work and the profit which it alleged it would have made if it had been permitted to complete the work according to the contract.

Defendant, the owner of the dwelling, in his answer denied that he had breached the building contract and alleged that it [943]*943bad been breached by the plaintiff, and reconvened for the sum of $11,497.14 alleged to be the cost of completing the construction of the dwelling as a consequence of the alleged breach of the contract on the part of the plaintiff.

After trial on the merits the trial judge rendered judgment for plaintiff in the sum of $2,315.76, of which amount $1,115.76 was for labor, materials, supplies, and extra work furnished by plaintiff, and $1,200 for loss of profit. Defendant has appealed, and plaintiff has answered the appeal, praying that the amount of the judgment be increased to $2,960.60.

Plaintiff, a partnership engaged in the contracting business, composed of Clarence M. Guidry and William M. Swayne, entered into an agreement with the defendant, Leander C. Miller, to construct for him as owner a residence for the sum of $9,497, the plaintiff agreeing to furnish all materials and labor. Of the total consideration, $1,-600 was to be paid upon the execution of the contract. An additional 20 per cent, or $1,899.40, was to be paid when the foundation was laid and the house completely framed and roughed in, if this amount was essential for the payment of materials purchased by the contractors in the construction of the dwelling. The balance of the consideration was to be paid upon completion of the work and acceptance by the owner.

After hearing all the testimony, the trial judge concluded that, when the house was completely framed and roughed in, the plaintiff called upon the defendant to pay the 20 per cent payment of $1,899.40 as stipulated in the contract, and that this payment was essential for payment on materials ; that the defendant refused to make this payment and insisted upon the plaintiff’s furnishing a performance bond, which was not called for or mentioned in the contract; that, upon plaintiff’s failing to furnish such bond, the defendant locked the toolhouse on the job, and placed a sign on the property reading “no trespassing”. Under these facts the trial judge reached the conclusion that the defendant had breached the contract. After reading the entire record, we find that his conclusion is supported by the testimony and the evidence adduced at the trial.

Article 2765 of the Civil Code provides that “The proprietor has the right to cancel at pleasure the bargain he has made, even in case the work has already been commenced, by paying the undertaker for the expense and labor already incurred, and such damages as the nature of the case may require”. With the provisions of this article in mind, we shall now consider the question of the amount or quantum due plaintiff.

Plaintiff has proved to our satisfaction the following items of expense and amount for labor paid by it or for which it is liable, to-wit:

[945]*945Atlas Foundation Co. foundation $ 338.00
Basile carpentry 325.00
Jeff’s Mill Works millwork 1000.00
Jahncke Service concrete 31.02
Jahncke Service reinforcing steel 18.85
Woodward Wight Co. sash balances 63.96
Owens & Sons rough hardware 43.66
American Sheet Metal Works termite shielding 55.27
Total $1875.76

The only item in this list which the defendant seriously contended was not due is that of $1,000 for millwork done by Jeff’s Mill Works, but we think plaintiff has proved this item and is entitled to recover therefor.

Plaintiff contends that there is also due it an item for labor in the amount of $825, which was over and above the amount paid to Basile for carpentry work. In the condition of the record at the present time, however, we do not think that the proof is sufficient for us to allow this claim; but, since we have concluded to remand the case in the interest of justice, plaintiff will be permitted to prove this item by competent evidence, if it can, and, in the event such proof is made, the total amount expended by plaintiff for expenses and labor will be increased from $1,875.76 to $2,700.76.

One of the partners testified that the defendant paid directly to Basile $210 which was due this carpenter under his contract with the plaintiff, and the plaintiff is not attempting to recover for this item of expense. The other items for labor and materials contended for by plaintiff were shown to have been paid by the defendant or for his credit by a building and loan association after he took over the construction of the dwelling, and plaintiff is not entitled to recover for them.

Upon remand, without considering plaintiff’s claim for profit which it would have made had it been permitted to complete the contract and its claim for alleged extras for which it is liable, plaintiff would' be entitled to a judgment in the sum of $1,-875.76 less the sum of $1,600 paid upon execution of the contract, or a total of $275.-76, plus whatever amount the lower court may ascertain to be due it under the labor item for which it is claiming $825.

The lower court awarded to plaintiff $1,200 for loss of profit. In our opinion the condition of the record doe's not justify such an award. To recover an award for profit lost by the plaintiff, it is necessary that the proof of the amount of the profit be made with reasonable certainty, and the proof should not be theoretical and speculative. Although the plaintiff contends that its profit on the job would have amounted [947]*947to $1,200, the testimony discloses that this was merely an estimated profit.

This court in Dugue v. Levy, 114 La. 21, 37 So. 995, 999, in construing Article 2765 had this to say: “ * * * Our article requires him [the proprietor] to pay, over .and above the expenses and labor already incurred, ‘such damages as the nature of the case may réquire.’ * * * the proprietor, on the one hand, shall have the legal right to put an end to the contract, .and the contractor, on the other hand, should be placed in as good a position as he would have been if he had been permitted to complete the contract.” (Italics ours.)

The record in the instant case establishes that the defendant, after the breach of the contract, completed the dwelling, and expended a large sum over and above the amount expended by the plaintiff and the amount for which it was liable, these items being as follows:

New Orleans Tent & Awning canvas for upstairs porch $ 22.80
J. E. Weber & Sons labor 440.00
Square Lumber Co. lumber 1900.00
Kirby Stansbury finish floors 185.00
Peter Judlin, Inc. sheetrock & concrete 329.00
Jno. Worner & Sons hardware 91.00

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mac Sales, Inc. v. E.I. du Pont de Nemours & Co.
24 F.3d 747 (Fifth Circuit, 1994)
Harrington v. Oliver
459 So. 2d 111 (Louisiana Court of Appeal, 1984)
Kuswa & Associates, Inc. v. Thibaut Construction Co.
440 So. 2d 1338 (Louisiana Court of Appeal, 1983)
Tom Black & Associates, Inc. v. Thibaut Construction Co.
420 So. 2d 1150 (Louisiana Court of Appeal, 1982)
Autrey v. Williams & Dunlap
343 F.2d 730 (Fifth Circuit, 1965)
Fontenot v. Benoit
128 So. 2d 815 (Louisiana Court of Appeal, 1961)
Housecraft Division of Southern Siding Co. v. Jones
120 So. 2d 662 (Louisiana Court of Appeal, 1960)
Roland v. American Casualty Co.
80 So. 2d 387 (Supreme Court of Louisiana, 1955)
Western Union Tel. Co. v. R. J. Jones & Sons
211 F.2d 479 (Fifth Circuit, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
47 So. 2d 721, 217 La. 935, 1950 La. LEXIS 1038, Counsel Stack Legal Research, https://law.counselstack.com/opinion/guidry-swayne-v-miller-la-1950.