Kurtzman-Violette Htg. v. Konover Const., No. Cv 940543571 (May 26, 1995)

1995 Conn. Super. Ct. 5853, 14 Conn. L. Rptr. 352
CourtConnecticut Superior Court
DecidedMay 26, 1995
DocketNo. CV 940543571
StatusUnpublished

This text of 1995 Conn. Super. Ct. 5853 (Kurtzman-Violette Htg. v. Konover Const., No. Cv 940543571 (May 26, 1995)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kurtzman-Violette Htg. v. Konover Const., No. Cv 940543571 (May 26, 1995), 1995 Conn. Super. Ct. 5853, 14 Conn. L. Rptr. 352 (Colo. Ct. App. 1995).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]MEMORANDUM OF DECISION In this case, plaintiff Kurtzman-Violette Heating and Air Conditioning Company, Inc. ("Kurtzman-Violette") has sued defendant Konover Construction Corporation ("Konover") to recover sums allegedly due for work it claims to have performed for Konover on a State construction project. In the First Count of its three-count Complaint dated October 21, 1994, the plaintiff claims that Konover issued a subcontract agreement to the plaintiff for mechanical work on State of Connecticut Project MD-93-23-B, Camp Weicker, Niantic, Connecticut. Complaint, Count I, ¶¶ 3-4. The CT Page 5854 plaintiff alleges that the adjusted contract price was $39,900.00; id. Count I, ¶ 4; that it completed all of its work under the contract; id. ¶ 5; and that it is now owed a balance of $18,480.00 under the contract. Id., ¶ 6.

In the Second Count of its Complaint, the plaintiff realleges the foregoing allegations from the First Count and contends that Konover's failure to pay it the remainder of the contract price within thirty days of receiving funds from the State for that purpose violates the provisions of General Statutes § 49-41c. Id., Count II ¶¶ 6-8.

In the Third Count of the Complaint the plaintiff claims that the defendant has been unjustly enriched by receiving the benefit of its work on the above-described project without fully paying it for that work, and thus that it must now pay the plaintiff for the reasonable value of its work. Id., Count III, ¶¶ 4-6. The Third Count does not allege that the work for which it seeks to be paid was performed under the terms of a contract, nor does it allege that any contract for such work was ever abandoned, superseded or set aside.

The defendant has moved this Court to strike the Second and Third Counts of the Complaint on the ground that they fail to state claims upon which relief can be granted. The defendant claims, in particular, that the Second Count must be stricken because the statute under which it is brought does not afford the plaintiff a private cause of action, and that the Third Count must be stricken because it fails to state all the elements essential to a cause of action for unjust enrichment. Both parties have filed briefs and supplemental memoranda of law in support of their respective positions on the motion.

I
A motion to strike challenges the legal sufficiency of a pleading. Conn. Prac. Book § 152; Wesson v. City ofMilford, 5 Conn. App. 369, 372 (1985). Although the allegations of the challenged pleading are to be construed in a manner most favorable to the non-moving party, a court cannot look beyond the pleadings for facts not alleged therein. Cavallo v. Derby Savings Bank, 188 Conn. 281,285-86 (1986). Moreover, a motion to strike admits facts CT Page 5855 only. It does not admit legal conclusions or the truth or accuracy of opinions stated in the pleadings. Quimby v.Kimberly Clark Corp., 28 Conn. App. 660, 664, (1992);Wesson, 5 Conn. App. at 372. On a motion to strike, the court must examine the complaint, assuming the truth of all well-pleaded facts, to determine whether the plaintiff has stated a legally sufficient cause of action. Id. A motion to strike must be granted if the complaint falls to state a claim upon which relief can be granted or if the plaintiff has alleged legal conclusions unsupported by facts. Mora v. Aetna Life Ins. Cas. Co., 13 Conn. App. 208,211 (1988).

II
In the Second Count of its Complaint, the plaintiff seeks to recover damages from the defendant under General Statutes § 49-41c, which provides as follows:

Sec. 49-41c. State contractor to make payment to subcontractor within thirty days. Any such person contracting with the state shall make payment to any subcontractor employed by such contractor within thirty days of payment by the state to the contractor for any work performed or, in the case of any contract entered into on or after October 1, 1986, for materials furnished by such subcontractor, provided such contractor may withhold such payment if such contractor has a bona fide reason for such withholding and if such contractor notifies the affected subcontractor, in writing, of his reasons for withholding such payment and provides the state board, commission, department, office, institution, council or other agency through which such contractor had made the contract, with a copy of the notice, within such thirty-day period.

In support of this claim, plaintiff duly alleges: (1) that it performed work on the project here at issue as a CT Page 5856 subcontractor of defendant Konover; (2) that defendant Konover's general contract for the project was with the State of Connecticut; (3) that the plaintiff completed all the work that was required of it under the terms of its subcontract; (4) such work was approved by the project architect; (5) that the defendant was paid by the State for the work the plaintiff performed on the project; and (6) that despite due demand, the defendant has not paid in the full for its work although the State paid the defendant for that work more than thirty days before the plaintiff filed this lawasuit [lawsuit]. See Complaint, Count II.

The defendant has moved to strike the Second Count on the ground that Section 49-41c does not afford the plaintiff a private cause of action. Instead, it claims, Section 49-41 is merely a notification statute which requires any general contractor who does not intend to make payments under a subcontract on a State project, within thirty days of its own receipt of State monies for the work to give timely, written notification of his intention to withhold such payments and of his reasons therefor both to the affected subcontractor and to the relevant State board, commission or agency which issued the general contract for the work.

In support of this position, the defendant relies principally upon the failure of the General Assembly, in passing the statute in question, to provide explicitly that a subcontractor whose rights under the statute have been violated may bring suit to enforce those rights. For the following reasons, the Court agrees with the defendant that the Second Count of plaintiff's Complaint must be stricken.

When the legislature intends to create a private cause of action, it typically does so expressly. Middletown v.Hartford Electric Light Co., 192 Conn. 591, 596 (1984).See also Connecticut Assoc. Builders Contractors Electrical Mechanical Contractors Inc. v. Saint FrancisHospital Medical Center, No. CV 94-0704940S (Conn.Super.) (Allen, J.) (July 29, 1994) (no implied private cause of action for violation of a regulatory Statute; Blondin v.Connecticare, No. CV93-0063828 11 Conn. L. Rptr. 305

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Covino v. Pfeffer
276 A.2d 895 (Supreme Court of Connecticut, 1970)
Cavallo v. Derby Savings Bank
449 A.2d 986 (Supreme Court of Connecticut, 1982)
DeMello v. Town of Plainville
368 A.2d 71 (Supreme Court of Connecticut, 1976)
City of Middletown v. Hartford Electric Light Co.
473 A.2d 787 (Supreme Court of Connecticut, 1984)
Holly Hill Holdings v. Lowman
628 A.2d 1298 (Supreme Court of Connecticut, 1993)
Wesson v. City of Milford
498 A.2d 505 (Connecticut Appellate Court, 1985)
Mora v. Aetna Life & Casualty Insurance
535 A.2d 390 (Connecticut Appellate Court, 1988)
Quimby v. Kimberly Clark Corp.
613 A.2d 838 (Connecticut Appellate Court, 1992)
Polverari v. Peatt
614 A.2d 484 (Connecticut Appellate Court, 1992)
Holly Hill Holdings v. Lowman
619 A.2d 853 (Connecticut Appellate Court, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
1995 Conn. Super. Ct. 5853, 14 Conn. L. Rptr. 352, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kurtzman-violette-htg-v-konover-const-no-cv-940543571-may-26-1995-connsuperct-1995.