Krogman v. Rice Bros.

135 N.E. 161, 241 Mass. 295, 1922 Mass. LEXIS 877
CourtMassachusetts Supreme Judicial Court
DecidedApril 21, 1922
StatusPublished
Cited by24 cases

This text of 135 N.E. 161 (Krogman v. Rice Bros.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Krogman v. Rice Bros., 135 N.E. 161, 241 Mass. 295, 1922 Mass. LEXIS 877 (Mass. 1922).

Opinion

Jenney, J.

On July 25, 1919, the plaintiff began an action of contract against Rice Brothers Company, a corporation organized under the law of Maine. Service was made upon the defendant by publication only and it has not “ appeared except specially, contesting jurisdiction.” Commonwealth Fisheries Company, a Massachusetts corporation hereinafter called the Fisheries Company, was summoned as trustee, and on October 29,1919, a special precept was issued by which the plaintiff attempted further attachment of the defendant’s property in possession of the Fisheries Company. The plaintiff, however, does not now urge that jurisdiction has been acquired except as tp property attached upen the original writ. Roberts v. Anheuser Busch Brewing Assoc. 215 Mass. 341.

The plaintiff contends that the Fisheries Company should be charged as trustee of the defendant, and the exceptions wholly concern that question and incidental proceedings. This contention is based upon the trustee’s amended answer and the evidence admitted in support of the plaintiff’s allegations of facts neither stated nor denied by the trustee. That answer included all facts disclosed by the original answer of the trustee and by the interrogatories to the trustee and its answers thereto.

From the amended answer the following facts appear:

In March, 1917, a contract theretofore made between the defendant and Alden A. Mills was assigned to the Fisheries Company, and assumed by it, and the defendant accepted that company as a party to the contract in place of Mills. The original contract provided for the building by the defendant of two seagoing vessels, one on or before December 1,1917, and the other on or before April 1, 1918. The first vessel was named the Louis M. Winslow, and is hereinafter designated as the Winslow. It was not delivered to the trustee until July 16, 1919. Simultaneously with its delivery, by written agreement, the defendant and the trustee adjusted all material differences relating to that vessel. It is not contended that the trustee should be charged because of any credits relating to the Winslow.

The second vessel was named the Alden A. Mills, and is hereinafter called the Mills. It was not delivered until November 8,1919. [299]*299When the original writ was served on the trustee, it was unfinished and the cost of its completion would have been at least $30,000, and there remained unpaid $78,179.09 on the contract relating to that vessel. Of this amount $30,000 was to be paid “within ten days after completion of the second vessel, acceptance of the same by the architects, and delivery to the Owner.” No claim is made that the trustee is chargeable for this amount. The plaintiff contends that he is entitled to an order charging the trustee because the contract further provided for the payment of fixed amounts within ten, thirty, sixty, ninety and one hundred and twenty days after" the completion and delivery of the Winslow; that as these were due absolutely and without contingency at the time of the service of the original writ, they were attachable before they became payable, although the trustee could not be compelled to pay before the times appointed by the contract; that the times so appointed having elapsed the defendant is now chargeable because of the amounts which became payable before the completion of the Mills and its acceptance by the trustee. See G. L. c. 246, § 24.

The contract provided that these payments were to be made “upon fulfilment of the conditions hereinafter specified,” which related to insurance, time of construction, freedom from liens as hereinafter set forth, and quality of steel.

The payments made before July 25, 1919, included all that possibly could become due until October 14, 1919, ninety days from the date of the delivery of the first vessel.

The answer states as a fact that the trustee was entitled to damages by reason of the delay of the defendant relating to the Mills, the contract providing that time was its “essence.”

Prior to November 8, 1919, although the trustee was ready and willing to accept delivery, the defendant and the receivers appointed over its property by the Supreme Judicial Court of Maine, had at all times informed the trustee that the Mills was not ready for delivery.

The contract further provided that no payments should be required “until and unless the Builders shall offer reasonable evidence that all reasonable claims for work, labor and material such as might constitute a lien on said vessels or either of them have first been paid and satisfied in full.” The trustee’s answer [300]*300explicitly alleges that the original contract had not been "abrogated, altered, amended, or otherwise changed,” or any of its terms waived except as set forth in the answer or provided in certain paper writings referred to therein.

On November 8, 1919, the receivers of the defendant and the Fisheries Company entered into a contract reciting the present action and the attachments by trustee process made or sought to be made therein, the completion of the Mills, and the willingness of the Fisheries Company to accept delivery under the contract, agreeing that the Fisheries Company should pay into the Chapman National Bank $63,000 in full payment for the Mills and for all claims arising under the contract for its construction, said amount to. be held in trust to await the entry of a final judgment in this case, and providing for the disposition of said amount in that event. The money was paid to the bank at the time this contract was executed.

The trustee was discharged. Assuming that this action was based wholly on the trustee’s answer, it was right. The burden was upon the plaintiff to show that the trustee should be charged. White v. Springfield Institution for Savings, 134 Mass. 232. Clearly there were contingencies which might arise after July 25, 1919, which might totally defeat the right of the defendant to the amounts specified to be payable upon days fixed with reference to the completion of the first ship, in case of a failure to insure, the possibility of liens, improper quality of materials, damages because of the failure to deliver the Mills on or before April 1, 1918, or in case the defendant should entirely abandon its contract.

> Money cannot be attached by trustee process unless when service is made on the trustee it is due absolutely and without any contingency except that of time. Potter v. Cain, 117 Mass. 238. Doyle v. Gray, 110 Mass. 206. Nutter v. Framingham & Lowell Railroad, 131 Mass. 231. Eddy v. O’Hara, 132 Mass. 56, 61. Cavanaugh v. Merrimac Hat Co. 213 Mass. 384. It is immaterial that there may eventually be something due from the trustee to the defendant or that it is probable that some amount may become payable. The trustee is chargeable only upon the facts existing when the writ was served on it. Godfrey v. Macomber, 128 Mass. 188. Knight v. Bowley, 117 Mass. 551. The trustee’s answer does not disclose a situation of disputed liability on then existing' [301]*301facts, and hence Thorndike v. De Wolf, 6 Pick. 120, and Wheeler v. Bowen, 20 Pick. 563, do not apply. See Capen v. Duggan, 136 Mass. 501.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thompson-Durkee Co. v. Express Plumbing & Heating Co.
1994 Mass. App. Div. 190 (Mass. Dist. Ct., App. Div., 1994)
Loyal Erectors, Inc. v. Hamilton & Son, Inc.
312 A.2d 748 (Supreme Judicial Court of Maine, 1973)
Philip Richenburg Insurance Agency, Inc. v. Ruscito Contracting Co.
35 Mass. App. Dec. 43 (Mass. Dist. Ct., App. Div., 1966)
R. L. Gourley Co. v. Middlesex Engineering & Equipment Corp.
25 Mass. App. Dec. 175 (Mass. Dist. Ct., App. Div., 1962)
Benison v. Wright
21 Mass. App. Dec. 68 (Mass. Dist. Ct., App. Div., 1961)
N. E. Tile Corp. v. Keleher
17 Mass. App. Dec. 139 (Mass. Dist. Ct., App. Div., 1958)
Plymouth Rock Transportation Corp. v. Saltman Bros. Inc.
13 Mass. App. Dec. 198 (Mass. Dist. Ct., App. Div., 1957)
Abbot Lumber & Building Supply Co. v. Cushing Construction Co.
112 N.E.2d 245 (Massachusetts Supreme Judicial Court, 1953)
Singarella v. City of Boston
5 Mass. App. Dec. 37 (Mass. Dist. Ct., App. Div., 1953)
Brady v. Lichter
102 N.E.2d 402 (Massachusetts Supreme Judicial Court, 1951)
Meunier's Case
66 N.E.2d 198 (Massachusetts Supreme Judicial Court, 1946)
Jordan v. Lavin
66 N.E.2d 41 (Massachusetts Supreme Judicial Court, 1946)
Jordan v. Clarence J. Lavin & Pilgrim Trust Co.
9 Mass. App. Div. 293 (Mass. Dist. Ct., App. Div., 1944)
Acushnet Saw Mills Co. v. St. Pierre
55 N.E.2d 900 (Massachusetts Supreme Judicial Court, 1944)
Donovan v. Fisher Bros., Inc.
6 Mass. App. Div. 428 (Mass. Dist. Ct., App. Div., 1941)
Wyatt Lumber Supply Company, Inc. v. Hansen
147 S.W.2d 366 (Supreme Court of Arkansas, 1940)
Curnane v. Curnane
27 N.E.2d 714 (Massachusetts Supreme Judicial Court, 1940)
Musolino, LoConte Co. v. Costa
23 N.E.2d 155 (Massachusetts Supreme Judicial Court, 1939)
Schlesinger v. Sheridan
2 Mass. App. Div. 553 (Mass. Dist. Ct., App. Div., 1937)
Godfrey Coal Co. v. Gray
5 N.E.2d 556 (Massachusetts Supreme Judicial Court, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
135 N.E. 161, 241 Mass. 295, 1922 Mass. LEXIS 877, Counsel Stack Legal Research, https://law.counselstack.com/opinion/krogman-v-rice-bros-mass-1922.