Wyatt Lumber Supply Company, Inc. v. Hansen

147 S.W.2d 366, 201 Ark. 534, 1940 Ark. LEXIS 393
CourtSupreme Court of Arkansas
DecidedDecember 9, 1940
Docket4-6121
StatusPublished
Cited by7 cases

This text of 147 S.W.2d 366 (Wyatt Lumber Supply Company, Inc. v. Hansen) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wyatt Lumber Supply Company, Inc. v. Hansen, 147 S.W.2d 366, 201 Ark. 534, 1940 Ark. LEXIS 393 (Ark. 1940).

Opinion

Smith, J.

On August 25, 1938, Otto Hansen entered into a building contract with M. Friedman to remodel the latter’s residence in the city of El Dorado. This contract was upon the consideration of $2,400, to be paid after the completion of the work. Friedman resided in the house to be remodeled, and continued to live in it while the remodeling work was in progress. During the progress of the work Friedman advanced Hansen- $200, but made him no other payment. The contract did not require this payment until the. work was completed. ■

The contract detailed the work to be done, but provided that “The owner may, at any time during the progress of the work, alter, or. change, or subtract from or add to the plans and specifications, without violating the contract, or the terms thereof, provided, that, if the cost of the work be increased by any such change or alteration, the amount of such increase shall be added to the contract - price herein agreed upon and paid upon the completion of the work.” Various changes and additions were made to the plans and specifications, but, under the provisions of the building contract above copied, they became a part of the contract.

While the parties were operating under this contract, the Wyatt Lumber & Supply Company, Inc., hereinafter referred to as the Wyatt Company,, furnished the building materials required. These amounted "to the sum of $1,267.36. Hausen, the contractor, was unable to meet his labor payrolls, and the Wyátt Company furnished Hansen money for this purpose in the sum of $1,263.32. The .advances of money and the sales of materials occurred ¡between the dates of September 19th and December 3rd, .1938, on which-last-named date Hansen quit the job.

Included in the extra work which Hansen was directed to do,’ and agreed to do, was the erection of a new .garage and the construction of a concrete driveway leading thereto, as the place of the erection of the new garage Tendered the driveway leading to the old garage unavailable. The floor of the old garage was demolished and the garage was rendered unusable, and was not replaced by Hansen, nor did he construct the new driveway.

After Hansen quit the job, Peters & Cramer, building contractors, were employed to make an estimate of the cost of the unfinished work and the cost of the extra "work not called for in the original contract which Hansen lad done. This estimate amounted to $469.52, and represented work, which Hansen was expected and had agreed to do and to be paid the cost of any part thereof not Included in the original contract, in addition to the $2,400.

About January 1, 1939, a leak developed in the roof Valley, and the manager of the Wyatt Company testified that the Friedmans called upon that company to complete the job Hansen had contracted to perform. The roof was repaired, at a cost of $14.37, of which $8.37 was for materials, and $6 for labor.

Upon the allegation that this work was a continuation ■of the Hansen job, being a repair upon a job otherwise substantially completed, the Wyatt Company filed suit to collect this $14.37 item, together with its bill for materials furnished and for labor paid for the account of' Hansen. All of this account, except the item of $14.37, bad been charged on the books of the Wyatt Company .against Hansen, and, for identification, was referred to ■on the books as the “Friedman Job.”

Hansen had left the State, and constructive service by the publication of a warning order was had against him. Friedman and his wife were served with summons. In addition, a writ of garnishment was issued against Friedman, in which it was sought to impound any balance-due by him to Hansen. Interrogatories were propounded to Friedman, in which, he was required to answer what money, if any, he owed Hansen. Friedman filed an answer-containing a general denial of indebtedness, in which he-reserved the right to answer in greater detail, and thereafter he filed an amendment to his answer in which he-set out the substance of the defense which he interposed at the trial.

There was no denial of the garnishee’s amended answer, as required by § 6125, Pope’s Digest. It was held' in the case of Beasley v. Haney, 96 Ark. 568, 132 S. W. 646, that this denial must be in writing, and that the answer of a garnishee must be taken as prima facie true, and, if not controverted, or if no issue is taken thereon,, it will not be presumed to be absolutely true. And in the case of Southwestern Gas & Electric Co. v. W. O. Perkins & Sow, 185 Ark. 830, 49 S. W. 2d 606, it was said that unless there was a denial of the garnishee’s answer entered of record, the presumption as to the truth of its-allegations becomes conclusive. See, also, Hoxie Lumber Co. v. Chidester, 184 Ark. 612, 43 S. W. 2d 69; Bank of Shirley v. Bonds, 178 Ark. 1079, 13 S. W. 2d 816.

Another reason why relief by way of garnishment, may not be awarded the Wyatt Company is that the building contract was not fully completed. It is argued that there had been a substantial compliance with the-original written building contract. But the court made-a specific finding to the contrary; and we cannot say that this finding is contrary to the preponderance of the evidence. But, even so, by the terms of the written contract, additions thereto became a part thereof.

In Friedman’s brief, twelve items' are enumerated in respect to all of which it is insisted that the contract was incomplete, but, if performed at all, had not been performed in a “good and workmanlike manner,” as the contract required should be done. The most important of these relates to the failure to install a red clay tile roof, tbe cost of which, would be $500. Other items relate to faulty construction, which the Wyatt Company insists could be remedied at small cost.

The building to be remodeled was an old one, and the Wyatt Company insists that the performance of the contract in a “good and workmanlike manner” relates to the manner of performing the remodeling, and not to the sufficiency of the job after it is completed. But there are several, at least, of these items, embraced in the original contract, which the undisputed testimony shows were improperly constructed, and will require replacement. The owner could demand that this be done before being required to pay the. contract price for the work.

There is an extended annotator’s note to the case of McKendall v. Patullo, 52 R. I. 258, 160 Atl. 202, 82 A. L. R. 1111, and the annotator cites many cases in support of the following note: “It is held that, in order that a garnishee may be charged, there must be an existing debt at the time of the service of the garnishment, and not a mere conditional or contingent liability. So, in the case of a construction contract, where the employer is not to become indebted to the contractor until performance in all particulars, there is. no indebtedness owing to the contractor which may be reached in a garnishment proceeding until the terms of the contract have been performed. ”

Here, as has been said, the contract price for the work was payable “Upon the completion of the work.”

In the case 'of Medley v. American Radiator Co., 27 Tex Civ. App. 354, 66 S. W.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thompson v. Bank of America
157 S.W.3d 174 (Supreme Court of Arkansas, 2004)
Able Distributing Co. v. James Lampe
773 P.2d 504 (Court of Appeals of Arizona, 1989)
Christy v. Nabholz Supply Co., Inc.
546 S.W.2d 425 (Supreme Court of Arkansas, 1977)
Coward v. Barnes
334 S.W.2d 894 (Supreme Court of Arkansas, 1960)
Wood v. Bennett
176 F. Supp. 205 (W.D. Arkansas, 1959)
Long-Bell Lumber Co. v. Auxer
255 S.W.2d 163 (Supreme Court of Arkansas, 1953)

Cite This Page — Counsel Stack

Bluebook (online)
147 S.W.2d 366, 201 Ark. 534, 1940 Ark. LEXIS 393, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wyatt-lumber-supply-company-inc-v-hansen-ark-1940.