Kray Cabling Co. v. County of Contra Costa

39 Cal. App. 4th 1588, 46 Cal. Rptr. 2d 674
CourtCalifornia Court of Appeal
DecidedNovember 13, 1995
DocketA067805
StatusPublished
Cited by14 cases

This text of 39 Cal. App. 4th 1588 (Kray Cabling Co. v. County of Contra Costa) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kray Cabling Co. v. County of Contra Costa, 39 Cal. App. 4th 1588, 46 Cal. Rptr. 2d 674 (Cal. Ct. App. 1995).

Opinion

Opinion

HANING, J.

The Division of Labor Standards Enforcement (DLSE) appeals a judgment by court trial in favor of respondent Kray Cabling Company, Inc., on the DLSE’s action for wage deficiencies. It contends the trial court erred in concluding its action was time barred, and in awarding respondent attorney fees under Code of Civil Procedure section 1028.5. We affirm.

*1591 Facts

The facts are not disputed. On July 8, 1992, Contra Costa County (County) issued a purchase order to Data General Corporation for computer hardware and its installation at Merrithew Hospital, a County facility. On September 9, 1992, Data General entered into a contract with Premises One for the installation. In November 1992 Premises One subcontracted the installation to respondent. During installation the California Office of Statewide Health Planning and Development (State) determined that the hospital’s existing electrical system was inadequate to support the new computer system. On February 25, 1993, the County issued a purchase order directly to respondent to bring the electrical system up to state requirements.

The State required the County to engage an approved inspector to monitor the electrical work and verify its completion. On May 31, 1993, Joe Fliutzi, the inspector so hired, accepted the work as complete. On July 8, 1993, the County accepted the computer project as complete.

While the computer installation and accompanying electrical work were taking place, the DLSE determined that the electrical work was a public works project as defined by Labor Code sections 1720 and 1771 1 —construction, alteration, demolition or repair costing more than $1,000 and paid from public funds. Employees engaged in such projects are required to be paid the prevailing wage for the county in which the project is located.

On September 24, 1993, the DLSE issued respondent a “Notice of Payment Due” for underpayment of prevailing wages paid to its electrical work employees. On October 19, 1993, it filed the instant action for wage deficiencies and penalties. 2 The trial court ruled the action was barred by the statute of limitations set forth in section 1775, insofar as it was not brought within 90 days after the County’s acceptance of respondent’s electrical work.

Discussion

I

The DLSE contends the applicable statute of limitations had not expired when it filed its action against respondent. Section 1775 provides *1592 that a public works contractor engaged for a public works project shall pay the state or political subdivision a penalty when its workers are paid less than the prevailing rates. If there is insufficient money due a contractor from the political subdivision awarding the project to cover such penalties, “the awarding body shall notify the [DLSE] of the violation and the [DLSE] . . . may maintain an action in any court of competent jurisdiction to recover the penalties and the amounts due provided in this section. This action shall be commenced not later than 90 days after the filing of a valid notice of completion in the office of the county recorder in each county in which the public work or some part thereof was performed, or not later than 90 days after acceptance of the public work, whichever last occurs.”

The DLSE’s action was filed 103 days after the County accepted the computer installation, of which the electrical work—albeit a separate purchase order—was an integral part, and 141 days after respondent’s work was accepted by Inspector Fliutzi. No notice of completion was ever recorded in the County. The DLSE argues that section 1775’s phrase “whichever last occurs” requires that both filing a valid notice of completion and an acceptance of the work must occur for the 90-day limitation period to start running. It then argues that insofar as the completion notice was never filed, there has not yet been a “last” occurrence to trigger the running of the 90 days, because “last” means the final event in a series of events, so in fact the statute has “not even begun to run.” Respondent’s position is that either event triggers the statute.

We conclude the statute is ambiguous, and therefore requires judicial interpretation. The ambiguity is caused by the phrase “whichever last occurs” in conjunction with the disjunctive “or” interposed between the two events triggering the statute of limitations: (1) “filing of a valid notice of completion” and (2) “acceptance of the public work.”

“The fundamental objective of statutory interpretation is to ascertain and effectuate the legislative intent. [Citation.] In determining such intent we look first to the words of the statute themselves, giving them their usual and ordinary meaning. [Citation.]” (City of Santa Cruz v. Municipal Court (1989) 49 Cal.3d 74, 90 [260 Cal.Rptr. 520, 776 P.2d 222].) “ ‘When used in a statute [words] must be construed in context, keeping in mind the nature and obvious purpose of the statute where they appear.’ [Citations.] Moreover, the various parts of a statutory enactment must be harmonized by considering the particular clause or section in the context of the statutory framework as a whole. [Citations.]” (Moyer v. Workmen’s Comp. Appeals Bd. (1973) 10 Cal.3d 222, 230-231 [110 Cal.Rptr. 144, 514 P.2d 1224].)

*1593 The ordinary, familiar meaning of “or” is a delineation of alternatives. (See Webster’s New Collegiate Dict. (1981) p. 800.) The use of this disjunctive reflects a legislative intent that either event, standing alone, may trigger the statute of limitations. The phrase “whichever last occurs” is included so that if both events have taken place, the potential parties will know which of them applies for limitation purposes.

That the Legislature did not intend both a notice of completion and acceptance of the work to be a prerequisite for the commencement of the statute of limitations may be inferred by a comparison of section 1775 to section 1730. These two sections were amended and added, respectively, by the same enactment (Stats. 1992, ch. 1342) and are contained in the same chapter of the Labor Code. (§ 1720 et seq. [Public Works].) “Where the same word or phrase might have been used in the same connection in different portions of a statute but a different word or phrase having different meaning is used instead, the construction employing that different meaning is to be favored. [Citations.]” (Playboy Enterprises, Inc. v. Superior Court (1984) 154 Cal.App.3d 14, 21 [201 Cal.Rptr. 207].) Section 1730 requires a public entity to transfer all wages and penalties withheld from a contractor for failure to pay the prevailing wage to the Labor Commissioner “within 90 days after the completion of the contract and formal acceptance of the job” (italics added) whenever the contractor fails to bring an action against the public entity for recovery of such wages and penalties.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Yes In My Back Yard v. City of Culver City
California Court of Appeal, 2023
Von Herrmann v. Super. Ct.
California Court of Appeal, 2022
People v. Bilbrey
California Court of Appeal, 2018
People v. Bilbrey
236 Cal. Rptr. 3d 381 (California Court of Appeals, 5th District, 2018)
Stevens v. TRI COUNTIES BANK
177 Cal. App. 4th 236 (California Court of Appeal, 2009)
In Re Hovanski
174 Cal. App. 4th 1517 (California Court of Appeal, 2009)
Juarez v. Arcadia Financial, Ltd.
61 Cal. Rptr. 3d 382 (California Court of Appeal, 2007)
Martin v. Szeto
114 Cal. Rptr. 2d 618 (California Court of Appeal, 2002)
Kobzoff v. Los Angeles County Harbor/UCLA Medical Center
968 P.2d 514 (California Supreme Court, 1998)
DEPARTMENT OF INDUS. REL. v. Fidelity Roof Co.
60 Cal. App. 4th 411 (California Court of Appeal, 1997)
Department of Industrial Relations v. Seaboard Surety Co.
50 Cal. App. 4th 1501 (California Court of Appeal, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
39 Cal. App. 4th 1588, 46 Cal. Rptr. 2d 674, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kray-cabling-co-v-county-of-contra-costa-calctapp-1995.