Koppers Co., Inc. v. Inland Steel Co.

498 N.E.2d 1247, 1986 Ind. App. LEXIS 3054
CourtIndiana Court of Appeals
DecidedOctober 20, 1986
Docket3-784A205
StatusPublished
Cited by17 cases

This text of 498 N.E.2d 1247 (Koppers Co., Inc. v. Inland Steel Co.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Koppers Co., Inc. v. Inland Steel Co., 498 N.E.2d 1247, 1986 Ind. App. LEXIS 3054 (Ind. Ct. App. 1986).

Opinion

GARRARD, Judge.

Inland Steel Company (Inland) and Kop-pers Company, Inc. (Koppers) entered into agreement for the design, engineering and construction of a blast furnace and a battery of sixty-nine coke ovens to be installed at Inland's Indiana Harbor premises.

Because of the magnitude of the project and to facilitate its construction the parties entered into what may be referred to as a design-build arrangement instead of the more traditional approach of completing the design and engineering phases and then utilizing the specifications to secure a firm bid. This arrangement contemplated that a variety of modifications or changes might occur before the project was completed. To accomplish their goal the parties entered into four separate agreements which undisputedly are to be integrated in their interpretation. They consist of the Engineering Contract, the Agency Agreement, the Field Erection Contract and the Bonus Penalty Agreement.

The project was completed and by all accounts constitutes a superior facility. However, the project took nearly two years beyond the estimated time of completion and cost $444 million rather than the estimated $267 million. Inland brought suit for breach of contract asserting that Kop-pers should be liable for much of the excess cost, and Koppers counterclaimed for the balance of its unpaid fee. The case was tried by jury. It found for Inland on its claim and assessed damages at $73,950, 000 and found for Koppers on its counterclaim with an award of $10,048,000. The court entered judgment on the verdict in favor of Inland for the net sum of $63,902,-000.

Koppers now raises a number of issues on appeal, but its front line position is that its liability for damages was strictly limited by the provisions of the Bonus Penalty Agreement as executed by the parties.

To examine that contention it is necessary to look at the various contracts which comprise the total agreement.

In the Engineering Contract Koppers agreed to furnish all design and detail engineering necessary to produce the facility. The scope of the work could be changed from time to time by written addenda agreed to and signed by the parties. In other salient provisions: (1) Koppers agreed to start work immediately and pur *1249 sue the work diligently to completion; (2) Koppers warranted the work should be free from all defects or faults of design or engineering and provided that any such errors should be corrected at no change in the contract price, "but Koppers shall have no other liability under the contract for such errors;" and (8) Koppers' liability for consequential damages was excluded.

The contract provided that if Koppers at any time refused, failed or neglected (except for causes beyond its reasonable control or Inland's breach of the contract) to prosecute the work with promptness and diligence or perform any of its other obligations, Inland could give written notice and terminate Koppers' right to proceed if it did not immediately take effective steps to cure the breach. Under such cireum-stances, if the aggregate cost of completing the contract exceeded the unpaid balance of the contract price, "Koppers shall be liable for and shall promptly pay the difference to Inland."

Finally, the contract provided that any failure to enforce or require the strict keeping of any of its terms or conditions:

" ... shall not constitute a waiver by Inland of such terms or conditions, and shall not affect or impair such terms or conditions in any way or the right of Inland at any time to avail itself of such remedies as it may have for any breach or breaches of such terms or conditions."

Under the Field Erection Contract Kop-pers was to furnish all small tools, labor and supervision necessary for construction of the entire project except for certain listed exclusions. This agreement contained provisions similar to those in the Engineering Contract on work changes, performing with diligence, warranting the work free of defects or faults, excluding consequential damages, giving Inland the right to cancel and secure damages if the cost of completion exceeded the contract price, and preserving Inland's rights to avail itself of remedies for breaches.

The Agency Agreement followed the same format and appointed Koppers as Inland's agent to purchase materials, rent or purchase equipment and place orders with contractors to provide field services for the project.

The fourth document, entitled Bonus Penalty Agreement, recited that Inland had entered into the three other agreements and wished to provide an incentive for Kop-pers to perform at the lowest possible cost.

This agreement then divided the costs to Inland under the three other contracts into (1) Construction Costs, and (2) Engineering and Material Costs. "Construction Costs shall mean field labor costs (whether performed by Koppers or others), construction equipment costs (whether purchased or rental) and other field costs." "Engineering and Material Costs shall mean costs for engineering, procurement, purchased materials and all overhead on all three contracts plus Koppers' entire fee on all three contracts."

This agreement then established "target costs" for each area as well as a provision for their adjustment to reflect certain specified actual costs and deviations agreed to during the work's progress. To the extent deviations resulted in an overall increase in cost exceeding eight million dollars, Kop-pers was to be paid an additional fee of 3%.

The agreement then provided the following concerning overruns and underruns:

"6. Overruns
If both Engineering and Material Costs and Construction Costs overrun their respective Target Costs, Koppers will be obliged to refund to Inland an amount equal to (a) that part of the overrun attributable to Construction Costs which does not exceed $1,500,000 plus 30% of the remaining portion of the overrun, if any; provided that, in no event will the refund be more than $4,800,000; plus (b) the amount of overrun attributable to Engineering and Material Costs.
7. Underruns
If both the Engineering and Material Costs and the Construction Costs under-run their respective Target Costs, Kop-pers will be entitled to additional compen *1250 sation over and above its total fee equal to 50% of the total underrun; provided that, in no event will the additional compensation exceed $6,800,000.
"8. Bonus or Penalty
If there is an underrun in either the Engineering and Material Costs or the Construction Costs, and an overrun in the other component, the underran and overrun will be netted. If the balance is an underrun, Koppers will be entitled to additional compensation computed in accordance with Section 7 above on such balance. If the balance is an overrun resulting from excess Construction Costs, Inland will be entitled to a refund computed in accordance with Clause (a) in Section 6 above on such balance. If the balance is an overrun resulting from excess Engineering and Material Costs, Inland will be entitled to a refund equal to such balance."

The Field Erection Contract is to be interpreted under Indiana law.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Swain v. State
870 N.E.2d 1058 (Indiana Court of Appeals, 2007)
Hildebrandt v. State
770 N.E.2d 355 (Indiana Court of Appeals, 2002)
Firstmark Standard Life Insurance v. Goss
699 N.E.2d 689 (Indiana Court of Appeals, 1998)
Curran v. State
675 N.E.2d 341 (Indiana Court of Appeals, 1996)
Hardebeck v. State
656 N.E.2d 486 (Indiana Court of Appeals, 1995)
Willie's Const. Co., Inc. v. Baker
596 N.E.2d 958 (Indiana Court of Appeals, 1992)
Matter of Estate of Kroslack
570 N.E.2d 117 (Indiana Court of Appeals, 1991)
Beatty v. State
567 N.E.2d 1134 (Indiana Supreme Court, 1991)
Layden v. New Era Corp.
575 N.E.2d 638 (Indiana Court of Appeals, 1990)
Saucerman v. State
555 N.E.2d 1351 (Indiana Court of Appeals, 1990)
Willoughby v. State
552 N.E.2d 462 (Indiana Supreme Court, 1990)
Eagle Signal Controls v. Midwestern Electric, Inc.
521 N.E.2d 967 (Indiana Court of Appeals, 1988)
Groves v. First National Bank of Valparaiso
518 N.E.2d 819 (Indiana Court of Appeals, 1988)
Durham v. State
510 N.E.2d 202 (Indiana Court of Appeals, 1987)
Evans v. Palmeter
509 N.E.2d 1130 (Indiana Court of Appeals, 1987)
Townsend v. State
498 N.E.2d 1198 (Indiana Supreme Court, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
498 N.E.2d 1247, 1986 Ind. App. LEXIS 3054, Counsel Stack Legal Research, https://law.counselstack.com/opinion/koppers-co-inc-v-inland-steel-co-indctapp-1986.