Konkar Maritime Enterprises, S.A. v. Compagnie Belge D'Affretement

668 F. Supp. 267, 1989 A.M.C. 182, 1987 U.S. Dist. LEXIS 7881
CourtDistrict Court, S.D. New York
DecidedAugust 25, 1987
Docket87 CIV. 2915 (PKL)
StatusPublished
Cited by23 cases

This text of 668 F. Supp. 267 (Konkar Maritime Enterprises, S.A. v. Compagnie Belge D'Affretement) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Konkar Maritime Enterprises, S.A. v. Compagnie Belge D'Affretement, 668 F. Supp. 267, 1989 A.M.C. 182, 1987 U.S. Dist. LEXIS 7881 (S.D.N.Y. 1987).

Opinion

OPINION & ORDER

LEISURE, District Judge:

Petitioner moves, pursuant to 9 U.S.C. § 9, to confirm an arbitration award dated March 25, 1987. Respondent cross-moves, pusuant to 9 U.S.C. § 10, to vacate the award.

Factual Background

The parties entered arbitration to settle a dispute over $202,889.29 in charter hire which respondent, the charterer, withheld from petitioner, the owner of the “Konkar Pioneer” (the “ship”). 1 The withdrawal of one arbitrator and the illness and subsequent withdrawal of another arbitrator delayed the commencement of arbitration proceedings.

On March 15, 1985, petitioner submitted its preliminary statement of claim, 11 exhibits, and its motion for an interim award of withheld charter hire. Respondent subsequently requested that petitioner produce, among other documents, its file of telexes and correspondence relating to the prefixture negotiations and the ship’s logs for the period from January 15, 1981, through March 15,1981. In response, petitioner produced “those telexes constituting the prefixture negotiation between brokers____” See Exh. 12 to Affidavit of Douglas R. Burnett, Esq., sworn to on May 15, 1987 (the “Burnett Affidavit”). Petitioner refused to produce the ship’s logs because they had been stored in a warehouse in Greece. Id. Petitioner agreed, however, to produce the logs if the panel of arbitrators (the “Panel”) directed it to do so. Id. By letter dated September 13, 1985, respondent requested that the Panel order petitioner to produce the ship’s logs. Exh. 14 to the Burnett Affidavit.

On December 6, 1985, the Panel ordered petitioner to produce the ship’s logs for the period from January 15,1981, through February 9, 1981. The Panel also set a schedule for submission of the parties’ remaining papers. Respondent was ordered to submit its “proofs, evidence and brief” within 30 days after receiving the logs. Any reply briefs, by either or both parties, were to be exchanged within 10 days of respondent’s submission. Finally, the Panel ordered respondent to place $202,889.29 in an interest-bearing joint escrow account pending the final award. Exh. 18 to the Burnett Affidavit.

In a letter dated December 10, 1985, respondent protested the Panel’s order with respect to the escrow account. Exh. 19 to the Burnett Affidavit. In a letter dated December 20, 1985, the Panel refused to modify its prior order. Exh. 20 to the Burnett Affidavit. Respondent never deposited the required sum into the escrow *270 account, however. Exh. 2 to the Burnett Affidavit at 9.

On January 6, 1986, petitioner produced all documents required by the Panel’s order dated December 6, 1985. On February 7, 1986, respondent timely submitted its brief (the “Main Brief”) and supporting evidence with the Panel. Exh. 1 to the Affidavit of Peter M. Bellsey, Esq., sworn to on June 9, 1987 (the “Bellsey Affidavit”). By February 25, 1986, petitioner had voluntarily complied with respondent’s request for production of the ship’s logs for the period ending on February 22,1981, and not previously produced. Exh. 32 to the Burnett Affidavit.

After receiving respondent’s Main Brief, petitioner requested a 30-day extension of the deadline for filing its reply. Exh. 22 to the Burnett Affidavit. Respondent objected to the request. In an order dated February 14,1986, the Panel granted petitioner an extension to March 19, 1986. It stated that if petitioner submitted new evidence in reply, counsel for respondent would “be given an opportunity and sufficient time to review such documentation with his client and submit a reply brief should he so desire.” Exh. 25 to the Burnett Affidavit. Petitioner timely filed its reply brief with five new exhibits annexed thereto. Exh. 2 to the Bellsey Affidavit. Respondent filed its supplemental brief in response (the “Sur-reply”) with two additional exhibits annexed thereto on May 2, 1986. Exh. 6 to the Bellsey Affidavit. For the first time, respondent asserted a claim for lost profits in the amount of $15,191.93. Exh. 30 to the Burnett Affidavit at 19-20.

By letter dated May 8, 1986, petitioner urged the Panel to refuse to hear the new claim for losses contained in respondent’s Sur-reply. Exh. 27 to the Burnett Affidavit. 2 In a letter to the parties dated June 6, 1986, the Panel stated that respondent’s submission of exhibits with the Sur-reply was “contrary to acceptable and normal procedures.” Exh. 29 to the Burnett Affidavit. The Panel stated that, in reaching its final decision, it would ignore the exhibits annexed to the Sur-reply as well as all subsequent correspondence by the parties. Id. The Panel advised respondent that if “it wishes to submit a new claim, that would be a matter for a fresh arbitration with which this panel is not concerned____” Id.

The Panel issued its final decision on March 25, 1987, awarding petitioner the total amount of withheld hire plus interest. Exh. 2 to the Burnett Affidavit at 9. The Panel also assessed 85% of the arbitration fees against respondent and 15% against petitioner. Id. at 10. Respondent now contends that the award should be vacated pursuant to 9 U.S.C. §§ 10(b), 10(c), & 10(d).

With respect to § 10(d), respondent argues that: (1) the Panel exceeded its authority by ordering respondent to create an escrow account; and (2) it failed to issue a final and complete award. With respect to § 10(c), respondent argues that the Panel was guilty of four instances of misconduct. Respondent asserts that the Panel: (1) failed to provide notice and an opportunity to be heard before ordering respondent to create an escrow account; (2) failed to provide notice and an opportunity to be heard before assessing 85% of the arbitration costs against respondent; (3) refused to hear the new claim contained in respondent’s Sur-reply; and (4) failed to require petitioner to produce its ship’s logs and the file of its broker, Bingham & Bigotte, in a timely manner. As to § 10(b), respondent contends that the Panel was guilty of evident partiality.

Discussion

“It is not the function of a district court to review the record of an arbitration proceeding for mere errors of law or fact.” Dundas Shipping & Trading Co. v. Stravelakis Bros., 508 F.Supp. 1000, 1003-04 (S.D.N.Y.1981). “A federal court may vacate or modify an arbitration award only if one of the grounds specified in 9 U.S.C. §§ 10 & 11 is found to exist.” Diapulse Corp. of America v. Carba, Ltd., 626 F.2d *271 1108, 1110 (2d Cir.1980) (citations omitted). “Moreover, the showing required to avoid summary confirmation is high.” Ottley v. Schwartzberg, 819 F.2d 373, 376 (2d Cir. May 27, 1987).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Doctor's Associates, Inc. v. Searl
180 A.3d 996 (Connecticut Appellate Court, 2018)
Certain Underwriters at Lloyd's, London v. Argonaut Insurance
264 F. Supp. 2d 926 (N.D. California, 2003)
Banco De Seguros Del Estado v. Mutual Marine Offices, Inc.
230 F. Supp. 2d 362 (S.D. New York, 2002)
Papayiannis v. Zelin
205 F. Supp. 2d 228 (S.D. New York, 2002)
British Insurance Co. of Cayman v. Water Street Insurance
93 F. Supp. 2d 506 (S.D. New York, 2000)
Davidson v. Hensen
135 Wash. 2d 112 (Washington Supreme Court, 1998)
Areca, Inc. v. Oppenheimer & Co., Inc.
960 F. Supp. 52 (S.D. New York, 1997)
Cellular Radio Corp. v. OKI America, Inc.
664 A.2d 357 (District of Columbia Court of Appeals, 1995)
Charles Construction Co. v. Derderian
586 N.E.2d 992 (Massachusetts Supreme Judicial Court, 1992)
Sun Refining & Marketing Co. v. Statheros Shipping Corp.
761 F. Supp. 293 (S.D. New York, 1991)
Celtech, Inc. v. Broumand
584 A.2d 1257 (District of Columbia Court of Appeals, 1991)
Boston Celtics Limited Partnership v. Brian Shaw
908 F.2d 1041 (First Circuit, 1990)
Cotter v. Shearson Lehman Hutton, Inc.
126 F.R.D. 19 (S.D. New York, 1989)
Pompano-Windy City Partners, Ltd. v. Bear, Stearns & Co.
698 F. Supp. 504 (S.D. New York, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
668 F. Supp. 267, 1989 A.M.C. 182, 1987 U.S. Dist. LEXIS 7881, Counsel Stack Legal Research, https://law.counselstack.com/opinion/konkar-maritime-enterprises-sa-v-compagnie-belge-daffretement-nysd-1987.