Kittyhawk Landing Apartments III v. Anglin Construction Co.

737 S.W.2d 90, 1987 Tex. App. LEXIS 8105
CourtCourt of Appeals of Texas
DecidedAugust 20, 1987
DocketB14-86-500-CV
StatusPublished
Cited by15 cases

This text of 737 S.W.2d 90 (Kittyhawk Landing Apartments III v. Anglin Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kittyhawk Landing Apartments III v. Anglin Construction Co., 737 S.W.2d 90, 1987 Tex. App. LEXIS 8105 (Tex. Ct. App. 1987).

Opinion

OPINION

ELLIS, Justice.

Kittyhawk Landing Apartments III (Kit-tyhawk) and Wildwood Construction Company, Inc., (Wildwood) appeal a joint and several judgment for $32,914.70, plus prejudgment interest and attorney’s fees, in favor of Anglin Construction Company, Inc. (Anglin). The judgment includes a decree that Anglin hold a constitutional lien for labor and materials against property involved in the suit and an order that Ang-lin shall have judicial foreclosure on that lien. A supersedeas bond has been filed by appellants.

The suit arises out of a construction project in which Wildwood, as the general contractor, contracted with Anglin to do site preparation work in constructing Kitty-hawk Landing Apartments III, a 268-unit complex, for a “total contract amount” of $36,000. In the section labeled “scope of work” the contract stated:

The work to be performed by this SubContractor under this contract shall include, but not be limited to: Cut all streets and parking areas to Plus-or-Minus 10th. Construct Building Pads in 6" lifts to plus-or-minus 10th and compacting to 95% proctor. Haul in and place 6000 cu. yards of fill. Any and all large vegetation will be removed from site. The rest of the stripping will be stock piled in areas selected by the general contractor to be used by others for landscaping later.

The contract was signed by Herbert J. Zieben as president of Wildwood, and Bill Knollenberg for Anglin. Kittyhawk Landing Apartments III is a Texas general partnership comprised of Herbert J. Zieben and Mary Lou Zieben. Shortly after the project began, Barry Kern became the project supervisor for Wildwood.

After Anglin spread 6,000 cubic yards of fill, the site was still too low. A conversation between Knollenberg, Zieben and Kern took place. After the conversation Anglin continued to provide more fill for a total of approximately 15,000 cubic yards, and do certain other jobs that were not expressly set out in the project. Anglin submitted invoices for the additional dirt. The invoices were approved by Barry Kern and some were paid by Wildwood’s accountant even after the $36,000 contract price was exceeded. A total of $93,434.20 had been invoiced by Anglin of which $57,911 was paid. Knollenberg attempted to collect for invoic *92 es that were not paid, and eventually filed suit. At trial Knollenberg recognized some mistakes in his billing and sought and recovered $32,914.70.

One difficulty in this appeal stems from the fact that it was pleaded and tried as a suit on written and oral contracts, with quantum meruit as an alternative theory of recovery against Kittyhawk, but the jury was submitted only damages issues with instructions limited to the law of quantum meruit.

In their first point of error appellants contend that the trial court erred in entering judgment on appellee’s quantum me-ruit claim because a written contract between Wildwood and Anglin governed the subject matter of the work performed. 1

The right to recover in quantum meruit does not grow out of contract, but is based upon the promises implied by law to pay for beneficial services rendered and knowingly accepted. Davidson v. Clearman, 391 S.W.2d 48, 50 (Tex.1965).

The existence of an express contract does not preclude recovery in quantum meruit for the reasonable value of services and materials not covered by a contract. Black Lake Pipe Line Co. v. Union Construction Co., 538 S.W.2d 80, 86 (Tex.1976).

The central issue is whether providing the “extra” 9,000 cubic yards of fill was required in the contract. If providing the fill was part of the contract, then appellee must look to the contract for compensation. Id. “In determining whether the work was required by the contracts we must determine (1) whether the work was extra and (2) whether the contracts made provision for the type of extra work performed.” Id.; Wood v. Texas Farmers Insurance Co., 593 S.W.2d 777, 781 (Tex.Civ.App.—Corpus Christi 1979, no writ); General Homes, Inc. v. Denison, 625 S.W.2d 794 (Tex.Civ.App.—Houston [14th Dist.] 1981, no writ).

The contract is composed of twenty-five pages of General Conditions of the Contract for Construction (AIA Document A201 1976), five pages of particular terms dealing with the relationship between the contractor Wildwood and the sub-contractor Anglin, and an addendum giving specifications for compacting fill. The description of the work quoted above is found in the five-page segment. Paragraph 5 of this second segment states:

The Contractor shall be liable to pay in accordance herewith only for work and materials furnished by the Sub-Contractor at the direction of the Contractor pursuant to the terms hereof; and the Sub-Contractor shall not be entitled to payment or damages in connection with any work not done or material not furnished though included herein; the Contractor may order changes in the work, the contract sum being increased or decreased accordingly. All orders and adjustments for any extra work of any kind must be in writing and signed by the Contractor. Sub-Contractor shall have no claim for extra work unless an order in writing is secured from the Contractor, signed by their authorized agent pri- or to commencement of the work for which such extra charge is claimed, setting forth the exact cost or basis of cost to be allowed for extra work. Any unit price or prices which may be stipulated herein shall govern in determining the *93 value of such additions, substitutions and/or omissions to which said units apply. In case of disagreement as to the adjustment of the contract price, the SubContractor shall proceed with the work pending the determination of such amount.

Appellee contends that the written contract is for work of cutting streets and parking areas and constructing building pads and material amounting to 6,000 cubic yards of fill. Therefore, the extra 9,000 cubic yards were materials provided outside the contract. Appellee reads paragraph 5 as requiring written orders for extra work, not extra materials. Thus, under appellee’s construction of the contract, his claim for payment for the 9,000 “extra” yards of fill can be based on quantum meruit.

We cannot accept appellee’s construction of the contract. Reading the contract as a whole, it is clear that the “work” to be provided by appellee included fill.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rand Mintzer v. Houston Medical Testing Services, Inc.
417 S.W.3d 691 (Court of Appeals of Texas, 2013)
Walton v. Hoover, Bax & Slovacek, L.L.P.
149 S.W.3d 834 (Court of Appeals of Texas, 2004)
Jensen Construction Co. v. Dallas County
920 S.W.2d 761 (Court of Appeals of Texas, 1996)
Williams v. Olivo
912 S.W.2d 319 (Court of Appeals of Texas, 1995)
George Grubbs Enterprises, Inc. v. Bien
881 S.W.2d 843 (Court of Appeals of Texas, 1994)
Sullivan v. Booker
877 S.W.2d 370 (Court of Appeals of Texas, 1994)
Moody v. EMC Services, Inc.
828 S.W.2d 237 (Court of Appeals of Texas, 1992)
Noble Exploration, Inc. v. Nixon Drilling Co., Inc.
794 S.W.2d 589 (Court of Appeals of Texas, 1990)
Ramirez Co. v. Housing Authority of City of Houston
777 S.W.2d 167 (Court of Appeals of Texas, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
737 S.W.2d 90, 1987 Tex. App. LEXIS 8105, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kittyhawk-landing-apartments-iii-v-anglin-construction-co-texapp-1987.