Summit Global Contractors, Inc. v. Enbridge Energy, Limited Partnership and Enbridge Gathering (North Texas) L.P.

CourtCourt of Appeals of Texas
DecidedDecember 10, 2019
Docket14-18-00052-CV
StatusPublished

This text of Summit Global Contractors, Inc. v. Enbridge Energy, Limited Partnership and Enbridge Gathering (North Texas) L.P. (Summit Global Contractors, Inc. v. Enbridge Energy, Limited Partnership and Enbridge Gathering (North Texas) L.P.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Summit Global Contractors, Inc. v. Enbridge Energy, Limited Partnership and Enbridge Gathering (North Texas) L.P., (Tex. Ct. App. 2019).

Opinion

Affirmed and Majority and Concurring Opinions filed December 10, 2019.

In The

Fourteenth Court of Appeals

NO. 14-18-00052-CV

SUMMIT GLOBAL CONTRACTORS, INC., Appellant

V. ENBRIDGE ENERGY, LIMITED PARTNERSHIP AND ENBRIDGE GATHERING (NORTH TEXAS) L.P., Appellees

On Appeal from the 215th District Court Harris County, Texas Trial Court Cause No. 2013-69313

MAJORITY OPINION

This appeal involves two agreements for the fabrication of pipes called “spools” used in the oil and gas industry. Summit Global Contractors, Inc., brought breach of contract and quantum meruit claims against Enbridge Energy, Limited Partnership (Enbridge Energy) and Enbridge Gathering (North Texas) L.P. (Enbridge Gathering). After a bench trial, the trial court found that the Enbridge parties did not breach the contracts and concluded that Summit’s quantum meruit claim was precluded by the express contracts. Summit challenges the sufficiency of the evidence in support of the trial court’s findings and challenges the trial court’s conclusion regarding the quantum meruit claim. We affirm.

Background

The Enbridge parties began construction of a natural gas processing plant in Wheeler, Texas. International Alliance Group (IAG) was hired to solicit bids for the project. IAG in turn placed Summit on its potential vendor list. IAG sent Summit a “Pipe Fabrication Inquiry Requisition” form requesting a bid for “pipe spool fabrication.” The scope of work was to include “all labor, material (exclud[ing] items furnished by customer), small tools, consumables, storage, overheads, etc.” The requisition form also required the fabricator to “quote Lump Sum.”

Summit offered an initial “Lump Sum proposal” including overtime but also specifying that “[a]ny down time will be handled on a Time and Material basis.” “Extra Work” was to be billed for materials at cost plus 15% and labor at $85 per hour. Summit’s owner, Rich Miller, testified that “lump sum” means a “fixed price” for everything in the scope of the contract, which includes some overtime. “Time and material” pricing, on the other hand, is based on the time expended and the materials used for the job. Miller also specified that payment terms would be “NET 30” from invoice date, meaning payment was due within 30 days of invoicing. The first bid included a price quote from a pipe supplier called Wolseley.

Summit was awarded the job, and a purchase order was issued that incorporated Summit’s bid terms and called for a 20% advanced payment. Enbridge Energy was identified as the party to be billed. Enbridge was also

2 required to provide valves for Summit to use in the spool fabrication.1 The purchase order stated, “PRICE(S) ARE FIRM” and “PRICING AND AVAILABILITY CONFIRMED WITH Rich Miller.”

By the time Summit was awarded the job, however, Wolseley’s price quote—upon which Summit’s bid was based—had expired. Two days after the purchase order was issued, Summit issued a $10,847.54 change order request based on an increase in Wolseley’s price. Approximately two weeks later, Summit submitted another change order request for a materials price increase from Wolseley of $87,113.10, which included the amount of the prior request for $10,847.54.

IAG’s representative contacted a representative from Wolseley regarding the price increase. The Wolseley representative informed the IAG representative that Wolseley’s price quote included in Summit’s bid package had been valid for only 15 days and Wolseley received the order past its quote validity date. Following negotiations, Wolseley agreed to decrease its increased price from $87,113.10 to $44,365.53. The purchase order was revised to reflect the $44,365.53 price increase. The record does not reflect which Enbridge entity paid that price increase, but it was paid.

Summit submitted its second “Lump Sum proposal” on June 12, 2012 “to provide labor, material, equipment & delivery necessary to fabricate Pipe Stools.” Payment terms, again, were to be “NET 30 from invoice date,” and “[a]ny down time [would] be handled on a Time and Material basis.” The proposal included overtime. A second purchase order was issued, again with Enbridge Energy identified as the party to be billed. That purchase order incorporated Summit’s

1 The purchase order does not specify which Enbridge party was required to provide the valves.

3 terms and again required a 20% advanced payment. The second purchase order was issued on June 22, 2012. Summit submitted an invoice for the advanced payment on the same day. That invoice was paid on July 13, 2012.

Summit met its first deadline for delivering spools. Summit then fell behind on meeting its remaining delivery deadlines, which were extended. According to Summit, one or both Enbridge parties caused the late deliveries due to delays in making the second advanced payment, negotiating the price decrease with Wolseley, and delivering the valves. Summit contends that it incurred expenses for unexpected overtime and other overhead due to the delays. Summit submitted change order requests after the job was completed totaling $390,088.95 for the purported delays. Representatives from Summit, the Enbridge parties, and IAG met to discuss the change order requests. The Enbridge parties and IAG concluded the requested change orders were not justifiable.

Summit filed an affidavit of lien against Enbridge Energy for $390,088.95 and filed this lawsuit, bringing claims, in relevant part, for breach of contract, quantum meruit, and promissory estoppel. In its petition, Summit alleged that both Enbridge Energy and Enbridge Gathering were parties to the relevant purchase orders. Referring to the Enbridge parties collectively as “Enbridge,” Summit alleged that Enbridge breached the contracts. Summit also asserted quantum meruit and other alternative liability claims against both Enbridge parties.

The Enbridge parties answered and filed counterclaims in which they also referred to themselves collectively as “Enbridge.” Although both purchase orders identify Enbridge Energy as the party to be billed, the Enbridge parties did not dispute that both defendants were bound by the purchase orders.2

2 The purchase orders specified that bills would be sent to Enbridge Energy and identified the “Purchaser” as “the Enbridge entity identified on the face of the Order.” The letterhead on 4 After a bench trial, the trial court found that (1) as to the first purchase order, it incorporated Summit’s bid terms for a lump sum contract; the payment terms were net 30, and the prices were firm; despite this, the price for materials in Summit’s bid had increased; and Summit made its first delivery on time but made subsequent deliveries late; (2) as to the second purchase order, it incorporated Summit’s bid terms for a lump sum contract; (3) “Enbridge” paid Summit the entire amount due under both purchase orders plus “over $30,000 that resulted from drawing changes, material price increases, and the like”; and (4) Summit’s change order requests totaling $390,088.95 were “untimely and unsupported.” The trial court concluded that (1) the purchase orders were valid and enforceable “lump-sum bid contracts”; (2) “Enbridge” did not breach the contracts; (3) Summit is not entitled to recover damages for breach of contract or attorney’s fees; and (4) Summit’s quasi contract and promissory estoppel claims are precluded by express contract. The trial court referred to both Enbridge parties collectively as “Enbridge” in its findings and conclusions, as did the parties in their proposed findings and conclusions. The court signed a take nothing judgment in favor of the Enbridge parties.

Discussion

In four issues, Summit challenges the legal sufficiency of the evidence in support of the trial court’s findings and rulings on Summit’s breach of contract and quantum meruit claims.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Golden Eagle Archery, Inc. v. Jackson
116 S.W.3d 757 (Texas Supreme Court, 2003)
BMC Software Belgium, NV v. Marchand
83 S.W.3d 789 (Texas Supreme Court, 2002)
Dow Chemical Co. v. Francis
46 S.W.3d 237 (Texas Supreme Court, 2001)
Stavinoha v. Stavinoha
126 S.W.3d 604 (Court of Appeals of Texas, 2004)
Marathon Corp. v. Pitzner
106 S.W.3d 724 (Texas Supreme Court, 2003)
2900 Smith, Ltd. v. Constellation Newenergy, Inc.
301 S.W.3d 741 (Court of Appeals of Texas, 2009)
Catalina v. Blasdel
881 S.W.2d 295 (Texas Supreme Court, 1994)
Barrientos v. Nava
94 S.W.3d 270 (Court of Appeals of Texas, 2002)
Dardas v. Fleming, Hovenkamp & Grayson, P.C.
194 S.W.3d 603 (Court of Appeals of Texas, 2006)
Stuckey Diamonds, Inc. v. Harris County Appraisal District
93 S.W.3d 212 (Court of Appeals of Texas, 2002)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Continental Casing Corp. v. Siderca Corp.
38 S.W.3d 782 (Court of Appeals of Texas, 2001)
Vickery v. Commission for Lawyer Discipline
5 S.W.3d 241 (Court of Appeals of Texas, 1999)
Schwartz v. Pinnacle Communications
944 S.W.2d 427 (Court of Appeals of Texas, 1997)
Albert G. Hill, Jr. v. Shamoun & Norman, Llp
544 S.W.3d 724 (Texas Supreme Court, 2018)
Peterson v. NCNB Texas National Bank
862 S.W.2d 182 (Court of Appeals of Texas, 1993)
Gotham Insurance Co. v. Warren E & P, Inc.
455 S.W.3d 558 (Texas Supreme Court, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Summit Global Contractors, Inc. v. Enbridge Energy, Limited Partnership and Enbridge Gathering (North Texas) L.P., Counsel Stack Legal Research, https://law.counselstack.com/opinion/summit-global-contractors-inc-v-enbridge-energy-limited-partnership-and-texapp-2019.