Kirk v. Rohan

187 P.2d 607, 29 Wash. 2d 432, 1947 Wash. LEXIS 387
CourtWashington Supreme Court
DecidedDecember 11, 1947
DocketNo. 30316.
StatusPublished
Cited by6 cases

This text of 187 P.2d 607 (Kirk v. Rohan) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kirk v. Rohan, 187 P.2d 607, 29 Wash. 2d 432, 1947 Wash. LEXIS 387 (Wash. 1947).

Opinion

*433 Schwellenbach, J.

This is an appeal by appellants, Rohan, (default judgment having been entered against defendant Denzler), from a judgment foreclosing a claim of lien and awarding judgment against appellants in the sum of $1,237.22, together with attorneys’ fees and costs, including title search fees, and other incidentals.

Respondent, Kirk, is a builder and contractor, working mostly for insurance companies in the city of Tacoma. He and Mr. Rohan met through mutual friends. Rohan wanted a garage built, and it was agreed that Kirk would do the work on a force account basis — that is, time and material— rather than for a stipulated contract price. Work was commenced August 5, 1945, and continued from time to time whenever Kirk’s men were free from other jobs. The actual days worked were August 5, September 25, October 1, 6, 8, 19, 22, 23, 24, 25, 26, 27, November 8, 9, 13, 14, 15, 16, and 19. Mr. Rohan then occupied the garage, and Mr. Kirk picked up his tools and equipment around the place and took away some lumber remaining there.

About the first of February, 1946, there was a particularly heavy rain storm, which caused water to back up from the street and flood the garage. On Sunday, February 3, 1946, Rohan called Mr. Smith (Kirk’s foreman), who came the following day, February 4th, with some men and remedied the defect.

The claim of lien was filed May 3, 1946. Appellants contend that the claim was not filed within ninety days from the completion of the work, which they assert was November 19th.

It is respondent’s contention that the job was not completed in November, and that it was anticipated that they would have to return at a later date to lay tile under the driveway and connect it with a downspout which extended from the back porch; that this was necessary because the driveway had not then been laid. However, under cross-examination he testified:

“Q. As a matter of fact, you were called back there, weren’t you, Mr. Kirk, because of the excessive rains that had taken place in the fore part of February, which had *434 flooded that garage? A. I should not be at all surprised. Q. Otherwise you would not have gone back? A. I would not be surprised.”

As to the telephonic conversation with Orville Smith on February 3rd, appellant Rohan testified:

“A. I complained that the water was flowing into the garage. We had several inches of water in the garage after this storm a few days before this. . . . And I suggested that in order to keep the water out of the garage it might be a good idea to put a strip of rubber or something, and I asked for suggestions from him as to what to do. Q- And what did he say? A. Well, he didn’t think much of that rubber idea, but that he would be back and work on this drain so that it would carry the water away.”

Mr. Smith testified that he was called by appellants on February 3rd to “finish up the job.” He said that the cement man had made a little depression or ditch across the driveway, but that it did not take care of the water. When he and his men came back February 4th, they attached the downspout from the roof to about thirty additional feet of newly laid drain tile. The record does not indicate that any further troubles were had or that any further complaints were made.

The first bill was sent to the Rohans on February 8th (no statement had been sent prior to this time). On April 2nd, Rohan wrote, asking for more details, which were furnished to him. On April 12th, he again wrote, complaining that the bill was excessive. At no time during these negotiations was there any intimation that the work was completed November 19th, rather than February 4th. It was not necessary for the appellants to raise this question, because the lien claimed was not filed until May 3rd. But at least it is an indication that both parties felt that the work done February 4th was to remedy a defect under the original contract.

Appellants rely on two cases, Ellsworth v. Layton, 37 Wash. 340, 79 Pac. 947, and Swensson v. Carlton, 17 Wn. (2d) 396, 135 P. (2d) 450. In the first case, there was testimony tending to show that the building was turned over *435 and accepted as completed in October. On January 6th, on demand of the owner, the contractor put metallic flashings over six windows that had been inadvertently omitted, and on February 13th, certain drain tile was relaid. This work was in the nature of repairs to remedy defects in the work which were not apparent at the time of acceptance of the building. In a per curiam opinion, we held:

“The court found that the liens filed by the appellants were not filed within the statutory time after the completion and acceptance of the work for which the liens were filed. The work having been completed and accepted during the first days of October, and the lien being filed on the 3rd day of April, the time at which the work on the building involved was completed is the question of fact which determines the appellants’ rights in this case. That fact was found against the appellants by the trial court, and, from an examination of the record, we are satisfied that such finding was justified by the testimony in the case, and that the rights of the parties were properly fixed by the judgment of the court.”

In thee latter case, the plaintiffs had a contract to veneer the house and build two fireplaces. They started work July 3, 1941.' They worked July 7, 8, 9, 10, 11, 24, 25, 28, 29, 30, 31, August 1, 4, 5, 7, 8, 11, and on October 11. On the latter day, they came back and cleaned the living room, working two hours. Swensson testified that as soon as they finished their work they left the job; that that was on August 11th. He testified that they did the work on October 16th for the purpose of extending the time for filing the lien. We held:

“The agreement between appellants and Carlton, or the request by Carlton that appellants clean the fireplace, was entirely distinct from, and had nothing to do with, the work to be performed by appellants under the McDonnell contract, and cannot be tacked onto the original contract to extend the time for filing a lien for the labor performed and materials furnished under the original contract. R. C. Mahon Co. v. Ford Motor Co., 256 Mich. 255, 239 N. W. 348. See 40 C. J. 200, § 237; also Pacific Manufacturing Co. v. Brown, 8 Wash. 347, 36 Pac. 273. In this connection, we find the following statement in 36 Am. Jur. 97, § 140:
*436 “ ‘As a general rule, after a contract is completed and closed, the time for filing a statement or claim of lien cannot be extended or the right revived by furnishing material or performing labor, upon a new contract, and tacking the same to the original contract.’
“It will be remembered that Mr. Swensson testified that the McDonnell contract was finished August 11th, and he attempted to get the money due on the contract both from Mr. McDonnell and from Mr. Carlton. According to his testimony, it was not until a few days before October 16th that Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brashear Electric, Inc. v. Norcal Properties, LLC
Court of Appeals of Washington, 2021
Gene McVety, Inc. v. Don Grady Homes, Inc.
581 P.2d 1132 (Arizona Supreme Court, 1978)
Stephenson v. Ketchikan Spruce Mills, Inc.
412 P.2d 496 (Alaska Supreme Court, 1966)
American Sheet Metal Works, Inc. v. Haynes
407 P.2d 429 (Washington Supreme Court, 1965)
Friis v. Brown
224 P.2d 330 (Washington Supreme Court, 1950)

Cite This Page — Counsel Stack

Bluebook (online)
187 P.2d 607, 29 Wash. 2d 432, 1947 Wash. LEXIS 387, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kirk-v-rohan-wash-1947.