Brashear Electric, Inc. v. Norcal Properties, LLC

CourtCourt of Appeals of Washington
DecidedMarch 11, 2021
Docket37379-7
StatusPublished

This text of Brashear Electric, Inc. v. Norcal Properties, LLC (Brashear Electric, Inc. v. Norcal Properties, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brashear Electric, Inc. v. Norcal Properties, LLC, (Wash. Ct. App. 2021).

Opinion

FILED MARCH 11, 2021 In the Office of the Clerk of Court WA State Court of Appeals, Division III

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON DIVISION THREE

BRASHEAR ELECTRIC, Inc., a ) No. 37379-7-III Washington Corporation, ) ) Appellant, ) ) v. ) ) NORCAL PROPERTIES, LLC, a ) Washington limited liability company; ) COLUMBIA STATE BANK, a ) Washington chartered bank; BLUE ) PUBLISHED OPINION BRIDGE PROPERTIES, LLC, a ) Washington limited liability company, ) ) Respondents, ) ) WHEATLAND BANK, a Washington ) chartered bank; NELSON ROOFING ) ENTERPRISES, INC., an Oregon ) Corporation d/b/a PALMER ROOFING ) COMPANY, ) ) Defendants. )

LAWRENCE-BERREY, J. — To secure payment for an “improvement” of real

property, RCW 60.04.091 requires a contractor to record a notice of a claim of lien not

later than 90 days after ceasing to furnish labor, professional services, materials, or

equipment, or the last date on which employee benefit contributions were due.

“Improvement” includes repairing real property. No. 37379-7-III Brashear Elec., Inc. v. Norcal Props., LLC

The question we answer today is whether the 90 days to record a claim of lien is

extended by a contractor performing warranty work—that is, work performed after

substantial completion to correct nonconforming work. We strictly construe “repairing”

to exclude a contractor’s correction of its own work and conclude that performing

warranty work does not extend the 90 days to record a claim of lien.

FACTS

Norcal Properties, LLC and Blue Bridge Properties, LLC own adjacent properties.

Under separate contracts, the owners hired prime contractor Vandervert Construction,

Inc. to construct a commercial retail building on each property. The relevant provisions

of each contract are identical. Vandervert hired subcontractors, including Brashear

Electric, Inc. to work on both projects.

Vandervert’s contracts with the owners required it, for a period of one year after

substantial completion, to promptly correct work not conforming to the contract

requirements. The contracts required Vandervert to bear the cost of correcting its work.

Vandervert’s contracts with Brashear required Brashear to assume all warranty

obligations applicable to its work under Vandervert’s contracts with the owners.

Brashear completed work on the Norcal project on June 28, 2017, and sent a

final invoice to Vandervert on August 17, 2017. Brashear completed work on the Blue

2 No. 37379-7-III Brashear Elec., Inc. v. Norcal Props., LLC

Bridge project on September 29, 2017, and sent a final invoice to Vandervert on

October 26, 2017. The owners fully paid Vandervert.

On January 8, 2018, a tenant of the Norcal building notified Vandervert that the

roof was leaking. An initial inspection indicated that the leak was due to Brashear’s

improper installation of the air conditioning unit. In accordance with the contractual

warranty provision, Vandervert directed Brashear to send an electrician to fix the leak.

On January 17, Jerry Peal, a Brashear electrician, applied caulking to temporarily

fix the leak until a roofing contractor could make a permanent repair. Closer inspection

revealed that Brashear was not at fault for the leak.

While Mr. Peal was on the Norcal property, Vandervert directed him to repair a

loose connection in a light fixture at the Blue Bridge building. Mr. Peal fixed the loose

connection.

On January 30, Brashear recorded a claim of lien against the Norcal property for

$12,830.81, the amount Vandervert owed it on that project. The next day, Brashear

recorded a claim of lien against the Blue Bridge property for $36,278.50, the amount

Vandervert owed it on that project. On February 2, 2018, Vandervert filed for

receivership.

3 No. 37379-7-III Brashear Elec., Inc. v. Norcal Props., LLC

In June 2018, Brashear commenced this action to foreclose its claims of liens

against the two properties. Eventually, the parties filed cross motions for summary

judgment. The trial court orally ruled in favor of the owners, determining that the

warranty work did not extend the 90 day period for recording Brashear’s claims of liens.

It later entered written orders. Brashear timely appealed.

ANALYSIS

PARTIES’ ARGUMENTS

Brashear contends the trial court misinterpreted RCW 60.04.091 and the

surrounding statutory scheme. It argues the pertinent statutes are unambiguous and

require a conclusion that its warranty work was “labor” that extended the time to record

its claims of liens. Alternatively, if the pertinent statutes are ambiguous, it argues we

must give them a liberal construction and reach a similar conclusion.

The owners argue the trial court properly strictly construed the pertinent statutes

when it ruled that the warranty work did not extend the time to record the claims of liens.

The owners cite Wells v. Scott, 75 Wn.2d 922, 454 P.2d 378 (1969), for the proposition

that warranty work, especially minor warranty work, does not extend the time to record a

claim of lien.

4 No. 37379-7-III Brashear Elec., Inc. v. Norcal Props., LLC

Brashear responds that Wells was decided before enactment of chapter

60.04 RCW. See LAWS OF 1991, ch. 281. It argues Wells no longer is controlling

because RCW 60.04.900 requires provisions of the mechanics’ lien statutes “to be

liberally construed to provide security for all parties intended to be protected by their

provisions.”1

We first discuss whether our analysis is governed by rules of strict or liberal

construction. We then construe the pertinent statutory scheme.

A. STRICT OR LIBERAL CONSTRUCTION

Prior to 2011, the law was unclear as to what extent courts were required to strictly

construe the mechanics’ lien statutes. The confusion was aptly summarized in

Lumberman’s of Washington, Inc. v. Barnhardt, 89 Wn. App. 283, 286, 949 P.2d 382

(1997):

Although RCW 60.04.900 states that the lien statutes are to be liberally construed to provide security for all parties intended to be protected by their provisions, case law has established that mechanics’ and materialmen’s liens are creatures of statute, in derogation of common law, and therefore must be strictly construed to determine whether a lien attaches.

1 Brashear also relies on Kirk v. Rohan, 29 Wn.2d 432, 187 P.2d 607 (1947), to support its argument that warranty work extends the time to record a claim of lien. Kirk is easily distinguishable on the basis that the contractor returned to perform warranty work and original contract work. Id. at 433-34.

5 No. 37379-7-III Brashear Elec., Inc. v. Norcal Props., LLC

In Williams v. Athletic Field, Inc., 172 Wn.2d 683, 261 P.3d 109 (2011), the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wells v. Scott
454 P.2d 378 (Washington Supreme Court, 1969)
Lumberman's of Washington, Inc. v. Barnhardt
949 P.2d 382 (Court of Appeals of Washington, 1997)
Williams v. ATHLETIC FIELD, INC.
261 P.3d 109 (Washington Supreme Court, 2011)
Sanders v. State
207 P.3d 1245 (Washington Supreme Court, 2009)
State v. Flores
186 P.3d 1038 (Washington Supreme Court, 2008)
Kirk v. Rohan
187 P.2d 607 (Washington Supreme Court, 1947)
State v. A.M.R.
51 P.3d 790 (Washington Supreme Court, 2002)
State v. Flores
164 Wash. 2d 1 (Washington Supreme Court, 2008)
Sanders v. State
166 Wash. 2d 164 (Washington Supreme Court, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
Brashear Electric, Inc. v. Norcal Properties, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brashear-electric-inc-v-norcal-properties-llc-washctapp-2021.