American Plumbing & Steam Supply Co. v. Alavekiu

282 P. 917, 154 Wash. 436, 1929 Wash. LEXIS 775
CourtWashington Supreme Court
DecidedDecember 5, 1929
DocketNo. 22108. Department One.
StatusPublished
Cited by3 cases

This text of 282 P. 917 (American Plumbing & Steam Supply Co. v. Alavekiu) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Plumbing & Steam Supply Co. v. Alavekiu, 282 P. 917, 154 Wash. 436, 1929 Wash. LEXIS 775 (Wash. 1929).

Opinion

*437 Beals, J.

Defendants, in December, 1926, being tbe owners of a large, old-fasbioned dwelling in tbe city of Tacoma wbicb they desired to remodel and make into a rooming bouse, retained, by written contract, L. O. Stacy (plaintiff’s assignor) to install a beating plant and a plumbing system. Tbe beating system was to be installed for not to exceed $1,300. For tbe plumbing, Mr. Stacy was to be compensated on tbe basis of time and material furnished. By tbe middle of March, 1927, both jobs were finished and accepted by defendants, who forthwith leased tbe premises to Mr. and Mrs. James S. Irvine, who took possession about April 1.

Tbe beating system was unsatisfactory and Mr. Stacy made several attempts to remedy it. Mr. and Mrs. Irvine, being unsuccessful in their attempt to conduct tbe premises as a lodging bouse, abandoned tbe same May 27, 1927, and made an assignment for tbe benefit of their creditors. During tbe succeeding month, Mr. Stacy, in an endeavor to remedy tbe defects in tbe beating system, delivered on tbe premises a new boiler wbicb was installed during tbe following August, Mr. Stacy making no charge for labor and material in connection with what be did at that time, save a charge for material under date August 29 in tbe sum of $6.91 and one under date September 8 for material in tbe sum of ninety-four cents. November 18 following, Mr. Stacy filed for record in tbe office of tbe auditor of Pierce county a notice of claim of lien for tbe sum of $1,199.33, wbicb stated that tbe labor and material for wbicb tbe lien was claimed consisted of

“ . . . plumbing and plumbing supplies and fixtures and the labor in tbe installation of tbe same . . . ; that tbe performance of said labor and tbe furnishing of said material ceased on tbe 22d day of August, 1927.”

*438 The claim of lien being assigned to plaintiff, this action was brought to foreclose the same.

The defendants answered, admitting that plaintiff’s assignor had furnished labor and material on their order, and pleading affirmatively that the work had been completed on or about March 15, 1927; that the materials used by plaintiff’s assignor in installing the heating system were so defective and poorly installed that the plant would not heat the house to the degree required by the contract; that, pursuant to repeated demands and requests by defendants, plaintiff’s assignor installed a new boiler purchased by defendants, which installation was completed on or about June 22; that defendants, on or about March 1, 1927, leased the premises to one Irvine for three years at a rental of $125 per month; that possession under this lease was taken March 15, 1927, and that, because of the defective condition of the heating system, defendants’ tenants abandoned the premises June 15 following. Defendants concluded their answer with an allegation that defendants were entitled to a set-off against any claim that plaintiff might have by way of damages suffered by defendants in the loss of their tenants.

In connection with this answer, it may here be stated that on the trial defendants admitted that they owed a balance of $1,199.33 on account of the work and labor referred to in plaintiff’s complaint, but denied that plaintiff was entitled to any lien therefor, and claimed a set-off against this account for damages as alleged in their answer.

Plaintiff filed its reply, alleging that Mr. Stacy’s agreements with defendants amounted in fact to one contract for plumbing and heating, and that,

“If there is any seeming conflict between this allegation and any allegation of the complaint, said complaint is hereby amended and sought to be amended to *439 conform hereto and to first item in the bill of particulars herein furnished to defendants and filed herein.”

The trial court refused to allow plaintiff any lien, basing its ruling upon the ground that the notice of claim of lien was filed too late, but granted plaintiff judgment against defendants for $1,199.33, allowing against the same a set-off in favor of the defendants in the sum of five hundred dollars by way of damages as claimed by defendants. From the judgment of the court in favor of plaintiff in the sum of $699.33, plaintiff appeals on the ground that the five-hundred-dollar set-off should not have been allowed, and upon the further ground that plaintiff should have been allowed a lien for the full amount which it claimed together with attorneys’ fees and costs; and defendants cross-appeal, claiming that they should have been allowed a set-off in a greater sum.

To avoid confusion, appellant will be referred to as plaintiff and cross-appellants will be referred to as defendants.

Neither the notice of claim of lien or plaintiff’s complaint made any reference to the charges for material furnished under dates August 29 and September 8 above referred to. After the taking of testimony in the case had closed, plaintiff’s counsel stated to the court, “The complaint should have been amended to conform to the proof as to the different items added and which were left out by inadvertence.” Upon objection by defendants’ counsel that the application came too late, the court refused to allow any amendment.

Defendants contend that, under certain decisions of this court, the trial court properly denied to plaintiff the right to maintain a lien. While the notice of claim of lien filed by plaintiff’s assignor refers only to plumbing and plumbing supplies and fixtures, we *440 are of the opinion that, under the present liberal rules providing for the allowance of amendments, and in view of the allegations of plaintiff’s reply, above referred to, which was not moved against by the defendants, the notice of claim of lien is sufficient to support a recovery thereon for the labor and material which the evidence showed was furnished by plaintiff’s assignor,

A more serious question is presented by defendants’ contention that the notice of claim of lien was not timely filed. In support of this point, defendants cite the cases of Ellsworth v. Layton, 37 Wash. 340, 79 Pac. 947, and Yundt v. Schultz-Degginger Co., 62 Wash. 308, 113 Pac. 760. In the earlier case, this court by a per curiam opinion simply approved a finding of the trial court to the effect that the lien filed by the appellant was not filed within the time limited by law after the completion and acceptance of the work. An examination of the record indicates that the appellant claimed a right to maintain a lien because the claim of lien was filed within the statutory period after a few small items of material which had been inadvertently omitted were supplied, and some defects remedied. In the later of the two cases above referred to, the claimant, after installing a heating system which proved defective, on the owner’s order supplied a pump for the purpose of remedying the defect, and claimed a lien for the value of the pump and of the labor expended in installing the same. The owner of the property had, prior to the installation of the pump, paid the full contract price for the heating plant. It was held that the lien could not be maintained, as the pump was installed to remedy a defect for which the claimant was liable under a guaranty.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kirk v. Rohan
187 P.2d 607 (Washington Supreme Court, 1947)
Swensson v. Carlton
135 P.2d 450 (Washington Supreme Court, 1943)
Flint v. Bronson
86 P.2d 218 (Washington Supreme Court, 1939)

Cite This Page — Counsel Stack

Bluebook (online)
282 P. 917, 154 Wash. 436, 1929 Wash. LEXIS 775, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-plumbing-steam-supply-co-v-alavekiu-wash-1929.