This text of 352 N.E.2d 468 (Kirbach v. Commonwealth Edison Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kirbach v. Commonwealth Edison Co., 352 N.E.2d 468, 40 Ill. App. 3d 587, 1976 Ill. App. LEXIS 2808 (Ill. Ct. App. 1976).

Opinion

Mr. PRESIDING JUSTICE KARNS

delivered the opinion of the court:

Plaintiff-appellant, Ronald Lee Kirbach, appeals from a judgment of the Circuit Court of Madison County entered upon a jury verdict in favor of defendant-appellee Commonwealth Edison Company.

Plaintiff, an employee of Babcock and Wilcox Company, a general construction contractor engaged by defendant, filed a complaint in two counts, one alleging violation of the Illinois Structural Work Act (Ill. Rev. Stat. 1975, ch. 48, par. 60 et seq.), and one alleging negligence on the part of the defendant. The suit arose from an injury allegedly sustained by plaintiff when he fell from a ladder while working inside a boiler apparatus owned by the defendant.

Plaintiff argues on this appeal that defendant was liable under the Structural Work Act as a matter of law because the contract with Babcock and Wilcox Company provided in effect that defendant was in charge of the work; that the court erred in refusing to give plaintiff’s tendered instruction that liability under the Structural Work Act could attach if defendant had “charge of, or the right to be in charge of” the structural work; that the court erred in refusing to permit plaintiff to demonstrate that Babcock and Wilcox Company had an indemnity contract with defendant and was thus the real party in interest; and that the verdict was contrary to the manifest weight of the evidence.

Defendant operates an electricity generating plant near Kincaid, Illinois, where several boilers are used to produce electricity by the use of steam. Adjacent to each boiler are “cyclones,” circular arrangements of tubing which provide heat to the water in the boiler to precipitate the production of steam. Slag builds up on the surface of the tubes and periodically must be removed by using pneumatic hammers and chisels. The cyclones are approximately 10 feet high and 13 feet long, and the men removing the slag are unable to reach the entire surface area of the cyclone without the use of scaffolds. When he fell, plaintiff was on a wooden ladder that had no protective shoes on the bottom. The bottom surface of the cyclone is not flat but is a configuration of tubing which constitutes part of the circular structure of the cyclone.

Under the contract between defendant and Babcock and Wilcox Company, defendant had the power to inspect all work and have it done again if not satisfactory; to order work stopped if done in an unsafe or improper manner; to have any employee removed whom defendant felt to be unfit or incompetent; to disapprove any subcontractor; and to require the removal of any employee of any subcontractor.

The testimony showed that while defendant’s employees did periodically “look in” on the work being done, there was no detailed inspection. If defendant's employees had a complaint about the work, they would go to defendant’s maintenance engineer or master mechanic who in turn would talk to the erector, Babcock and Wilcox’ chief man on the job. The erector would consult the general foreman who would talk to the crew foreman who would in turn see that the work was then properly performed. The testimony of defendant’s superintendents and engineers was that they would not allow Commonwealth Edison employees to use ladders inside the cyclone, as it was unlikely that the. configuration of the cyclone would provide a steady base for the ladder. Instead it was defendant’s practice to erect wooden or aluminum scaffolding inside the cyclone on which the men could stand. In any event no ladders without protective shoes would be used.

Plaintiff and another workman testified that ladders and scaffolding were used inside the cyclones and that they did not consider the use of ladders to be unsafe, even when not equipped with safety shoes or nonslip devices. Plaintiff testified that a ladder was necessary to do part of the work and was more convenient than scaffolding. There was scaffolding present in the cyclone when plaintiff was injured, and there was evidence that this scaffolding was sufficient to perform the work. There was also evidence that the ladder in question was owned by Babcock and Wilcox and had been modified by its employees by cutting off a part of a longer ladder.

Plaintiff contends that as a matter of law defendant had the right to be in charge of the work and thus was in “charge of the work” creating liability under the Structural Work Act. (See e.g., Larson v. Commonwealth Edison Co., 33 Ill. 2d 316, 211 N.E.2d 247 (1965).) But whether or not the contract provisions could be construed to give defendant the right to be in charge of the work, we cannot say as a matter of law that defendant was in “charge of the work.” Whether defendant or Babcock and Wilcox was in charge of the work was a question for the jury to decide. (Schultz v. Ericsson Co., 264 Ill. 156, 106 N.E. 236 (1914); Mundt v. Ragnar Benson, Inc., 18 Ill. App. 3d 758, 310 N.E.2d 633 (1st Dist. 1974); Moulton v. Shell Oil Co., 38 Ill. App. 3d 524, 347 N.E.2d 825 (5th Dist. 1976).) And even were we to accept plaintiff’s contention, we could not say that defendant is liable as a matter of law under the Structural Work Act. The jury may well have believed that defendant did not fail to furnish a safe and suitable scaffold, or that the failure to furnish a proper scaffold was not the proximate cause of plaintiff’s injury. In Moulton, the question before us was whether defendant Shell Oil Company or the contractor was in charge of the work. We stated, “(t]he jury returned a general verdict indicating that they found for the defendants and against the plaintiff. The jury found, then, that the defendants either were not in charge of the work, or if they were that they had not violated the Structural Work Act, or that defendants were neither in charge of the work nor violated the Structural Work Act. These choices were for the jury which found in favor of both defendants and we will not set that finding aside.” We believe the same principle to be applicable here.

Nor can we say that the verdict was against the manifest weight of the evidence. There were sufficient conflicts in the evidence for the jury to resolve that we cannot say that the verdict was “unreasonable, arbitrary and unsupported by the evidence.” Stringer v. McHugh, 31 Ill. App. 3d 720, 722, 334 N.E.2d 311, 312 (5th Dist. 1975); Moulton v. Shell Oil Co.

Plaintiff next contends that the court erred in refusing to modify IPI Nos. 180.01 and 180.02 by adding “or the right to be in charge of” the work as an alternative to having charge of the work. Two issues instructions and two non-IPI instructions containing this language were also refused. In Larson v. Commonwealth Edison Co., 33 Ill. 2d 316, 211 N.E.2d 247 (1965), the court held to be error the modification of “having charge of” with the words “by retaining control and supervision of such work.” The court held that “having charge of” is a phrase of common usage and meaning and should not be modified. This ruling has been incorporated in IPI No. 180.16.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Golden v. Kishwaukee Community Health Services Center, Inc.
269 Ill. App. 3d 37 (Appellate Court of Illinois, 1994)
Golden v. KISHWAUKEE COM. HEALTH SERV.
645 N.E.2d 319 (Appellate Court of Illinois, 1994)
Bargman v. Economics Laboratory, Inc.
494 N.E.2d 231 (Appellate Court of Illinois, 1986)
Galliher v. Holloway
474 N.E.2d 797 (Appellate Court of Illinois, 1985)
Zuelsdorf v. Montgomery Ward & Co.
380 N.E.2d 1130 (Appellate Court of Illinois, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
352 N.E.2d 468, 40 Ill. App. 3d 587, 1976 Ill. App. LEXIS 2808, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kirbach-v-commonwealth-edison-co-illappct-1976.