Kinnebrew v. CM Trucking & Construction, Inc.

6 P.3d 1235, 102 Wash. App. 226
CourtCourt of Appeals of Washington
DecidedAugust 28, 2000
DocketNo. 44511-1-I
StatusPublished
Cited by1 cases

This text of 6 P.3d 1235 (Kinnebrew v. CM Trucking & Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kinnebrew v. CM Trucking & Construction, Inc., 6 P.3d 1235, 102 Wash. App. 226 (Wash. Ct. App. 2000).

Opinion

Appelwick, J.

— CM Trucking & Construction, Inc. (CM Trucking) and Joseph E. Kinnebrew entered into a time and materials contract. Kinnebrew contested the billing and failed to pay under the contract. CM Trucking filed a claim of lien on the property based on chapter 60.04 RCW. Kinnebrew filed an action to dismiss the lien and CM Trucking counterclaimed to foreclose the lien. Unable to obtain financing, Kinnebrew requested a lien release, and CM Trucking agreed to release the lien in return for a surety deposit into the court registry. CM Trucking conditioned the lien release on a reservation of a right to claim attorney fees under chapter 60.04 RCW Kinnebrew contends attorney fees do not apply where the lien was released prior to trial and that the reservation was unilateral. We find that CM Trucking is entitled to attorney fees because the dispute is related to the lien foreclosure. We also find Kinnebrew acquiesced to the reservation and is therefore estopped from contesting attorney fees. Reverse and remand.

FACTS

CM Trucking is a Washington corporation engaged in construction work, excavation, trucking, and sale of rock. [229]*229Joseph E. Kinnebrew is the owner of real property in Skagit County, Washington. On October 14, 1997, Kinnebrew and CM Trucking entered into an oral contract to modify Kinnebrew’s driveway in return for $75 for one hour of equipment time. On November 3,1997, Kinnebrew and CM Trucking entered into a written “Time and Materials” contract. Kinnebrew agreed to pay CM Trucking for time and materials expended on the property at Kinnebrew’s request and CM Trucking promised to provide fill material for free.

CM Trucking performed work under the time and materials contract between November 3, 1997, and January 14, 1998. The work included digging ponds on site, digging a ditch at the base of a contemplated waterfall, loading excavated rock onto trucks, moving rock to various areas on the site, landscaping, placing clay in ponds, moving garbage piles, and burying a propane tank. CM Trucking and Kinnebrew disputed the time and materials contract billings. Kinnebrew did not pay CM Trucking for its work.

On March 31, 1998, CM Trucking filed a labor and materials lien for $5,968.62. Kinnebrew alleged that the lien prevented him from obtaining construction financing. On May 5,1998, Kinnebrew filed suit against CM Trucking to have the lien dismissed, disputing the amount due under the time and materials contract, making a claim on the contractors bond, and alleging damages from impaired financing. On June 18, 1998, CM Trucking answered Kinnebrew’s complaint and counterclaimed to foreclose on the lien, making a demand for attorney fees and costs pursuant to RCW 4.84.185 and RCW 4.84.250.

Kinnebrew’s counsel sent a letter to CM Trucking on July 9,1998, requesting a lien release because the lien impaired Kinnebrew’s construction financing. Kinnebrew offered to interplead the disputed lien amount into court in exchange for release of the lien. The interplead amount would provide a fund that could be litigated between the parties, and the release of the lien would allow Kinnebrew to obtain construction financing.

[230]*230In a July 13, 1998 letter, CM Trucking agreed to release the lien after Kinnebrew deposited the disputed lien amount to the court. The letter stated that “by signing the release of lien, we are not giving up any of our rights under the lien statute to recover court costs and attorneys’ fees, or any claim amounts in excess of the amount of the lien, as set forth in our counterclaim.” Kinnebrew never responded to or acknowledged CM Trucking’s statement regarding attorney fees. Kinnebrew deposited $5,968.62 into the court registry and recorded the lien release.

A five-day trial commenced on November 23, 1998, in the Skagit County Superior Court. The trial court ruled against Kinnebrew on all claims and entered judgment in favor of CM Trucking on its counterclaim in the amount of $5,562.12.

On February 5, 1999, the trial court held a hearing for entry of findings of fact, a request for sanctions against Kinnebrew’s counsel, and a request for CM Trucking’s attorney fees. The court concluded that CM Trucking’s release of the lien took the matter outside the lien foreclosure statute, precluding recovery of costs and attorney fees under RCW 60.04.181. The court reasoned that absent an affirmative agreement by Kinnebrew, he was not estopped from arguing that the release of the lien precluded an award of attorney fees. The court stated that “denial of costs and [attorney] fees is contrary to intent of the statute,” and that “this is a case where [the court] would otherwise be very inclined to award attorney fees.”

CM Trucking’s motion for reconsideration was denied. The court ruled that “once the lien is released by the lien claimant, there is no longer any lien to foreclose and the action cannot thereafter be characterized as a lien foreclosure action.” CM Trucking now appeals.

ANALYSIS

CM Trucking raises three issues on appeal: (1) whether it is entitled to attorney fees under RCW 60.04.181; (2) [231]*231whether Kinnebrew is estopped from denying that CM Trucking is entitled to attorney fees; and (3) whether attorney fees should be awarded on appeal.

Standard of Review

A superior court has no power to award attorney fees unless authorized by statute, contract, or on equitable grounds. Bongirno v. Moss, 93 Wn. App. 654, 657, 969 P.2d 1118 (1999). The trial court is given broad discretion in fixing attorney fees. Schmidt v. Cornerstone Invs., Inc., 115 Wn.2d 148, 169, 795 P.2d 1143 (1990).

Interpretation and construction of a statute is a question of law to be reviewed de novo. Lumberman’s of Wash., Inc. v. Barnhardt, 89 Wn. App. 283, 286, 949 P.2d 382 (1997). Appellate courts should construe a statute according to its plain language, and where a statute is unambiguous, statutory construction is improper. Id. at 286. Lien statutes should be liberally construed to protect those within the scope of the statute. RCW 60.04.900. But one claiming the benefit of a statutory lien must show that they have strictly complied with the provisions of the law that created it. Id.; Pacific Gamble Robinson Co. v. Chef-Reddy Foods Corp., 42 Wn. App. 195, 198, 710 P.2d 804 (1985).

Attorney Fees under RCW 60.04.181

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Casey v. Chapman
98 P.3d 1246 (Court of Appeals of Washington, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
6 P.3d 1235, 102 Wash. App. 226, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kinnebrew-v-cm-trucking-construction-inc-washctapp-2000.