Kinden Corp. v. Guam Healthcare Dev, Inc. DBA GRMC. DCK Worldwide, LLC and DOES I-III

CourtSuperior Court of Guam
DecidedNovember 4, 2019
DocketCV0040-16
StatusUnknown

This text of Kinden Corp. v. Guam Healthcare Dev, Inc. DBA GRMC. DCK Worldwide, LLC and DOES I-III (Kinden Corp. v. Guam Healthcare Dev, Inc. DBA GRMC. DCK Worldwide, LLC and DOES I-III) is published on Counsel Stack Legal Research, covering Superior Court of Guam primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kinden Corp. v. Guam Healthcare Dev, Inc. DBA GRMC. DCK Worldwide, LLC and DOES I-III, (superctguam 2019).

Opinion

FILED 1 ZUIg NOV —LI MI) 8 2 SUPERIOR COURT 3 OF GUAM

IN THE SUPERIOR COURT OF GUAM 5

6 K1NDEN CORPORATION, 7 Plaintiff, 8 Civil Case No. CVOO4O-16 9 vs. 10 GUAM HEALTHCARE DEVELOPMENT, INC. DBA GUAM REGIONAL MEDICAL 12 CITY, DCK PACIFIC GUAM, LLC. DCK DECISION AND ORDER WORLDWIDE, LLC AND DOES I-Ill, 13

14 Defendants.

17 INTRODUCTION 18 This matter is before the Honorable Judge Michael J. Bordallo. Plaintiff Kinden 19 Corporation (hereinafter “Kinden”) is represented by Attorney Louie I. Yanza. Defendant Guam 20 Regional Medical City (hereinafter “GRMC”) is represented by Attorney Vanessa L. Williams. 21 On September 13, 2018, GRMC filed a Motion for Summary Judgement (hereinafter “Motion”) 22 on Kinden’s foreclosure of mechanic’s lien, unjust enrichment, and quantum meruit claims. 23

24 Kinden filed an opposition on May 21, 2019. GRMC filed a reply on June 4, 2019. After having

25 received and reviewed the papers, arguments, and the file herein, the Court holds that GRMC’s

26 Motion for Summary Judgment is GRANTED in PART and DENTED in PART.

Page lofl7 . . BACKGROUND 2 This matter arises out of Kinden’s Verified Complaint and Demand for Jury Trial

(hereinafter “Complaint”) filed on January 19, 2016. Multiple trial dates were set in this matter

and then continued for various reasons, including attempts at mediation. The parties engaged in 5 mediation from January 2018-April 2018, but such efforts broke down and the parties continued 6 to move toward trial. On September 7, 2018, the Court granted leave for GRMC to file a Motion 7 for Summary Judgment, despite GRMC missing the deadline for filing dispositive motions. At a 8 hearing on September 4, 2018, the Court told Kinden it would have three weeks to file an 9 opposition to any motion for summary judgment. GRMC filed its Motion on September 13, 10 2018. Three weeks passed, and Kinden did not file an opposition. Four days later, on October 8,

12 2018, the Court took GRMC’s Motion under advisement.

13 After having reviewed GRMC’s Motion in a light most favorable to Kinden, coupled

14 with the fact that Kinden did not file an opposition, the Court granted GRMC’s Motion on

15 December 20, 2018. On January 2, 2019, Kinden filed a Motion to Reconsider the Court’s 16 Decision and Order, arguing the Court never set a deadline for Kinden to file an opposition, and 17 if the Court believes that it did set a deadline, the manner in which the Court set the opposition 18 deadline was unclear and confusing. On April 30, 2019, the Court granted Kinden’s Motion for 19 Reconsideration and allowed Kinden to file an opposition to the Motion for Summary Judgment. 20 Kinden filed an opposition on May 21, 2019. On June 4, 2019, GRMC filed a Reply Brief. The 21 Court took the issue of Summary Judgement under advisement on August 12, 2019. 22

23 FACTS

24 • GRMC initiated a new hospital construction project (hereinafter “Project”), selecting

25 DCK Pacific Guam LLC and DCK Worldwide LLC (collectively and hereinafter

26 “DCK”) to serve as the general contractor of the Project. Compl. p. 2.

Page 2 of 17 1 2. Kinden entered into a subcontract with DCK on or about September 10, 2012, to provide

2 labor and materials for the Project. Compi. p. 3.

3. In the summer of 2014, the Project was delayed for a variety of reasons, including major

cracks in the structure of the building following a seismic event in September 2014. 5 Deci. of Keith L. Farrell ¶9[ 3-4. 6 4. To compound things, DCK failed to pay its subcontractors, and many subcontractors 7 walked off the Project in December 2014. IdJ 4. 8 5. It was not until March 28, 2015, months later, that a solution was found and remediation 9 work could begin. It took another three months for DCK to complete remediation in 10

11 June2Ol5.Id.

12 6. Kinden alleges that as a result of these delays, it incurred extended overhead expenses.

13 Compl. p. 3.

14 7. Kinden alleges that during the course of the construction, both GRMC and DCK

15 instructed Kinden to make change orders resulting in Kinden incurring further expenses. 16 Compl. p. 4. 17 Kinden alleges that the expenses related to extended overhead and change orders were 18 not included in Kinden’ s scope of work. Id. 19 9. On or about June 11, 2015, Kinden provided preliminary notice of a mechanic’s lien to 20 GRMC. Compl. p.5. 21 10. On June 25, 2015, DCK sent a “cease work” letter to all workers and subcontractors, 22 ordering them to immediately cease work, remove tools and equipment, and secure their 23

24 work areas until further notice. Decl. of Keith L. Farrell ¶ 10.

25 11. On October 19, 2015, Kinden recorded with the Department of Land Management a

26 claim of mechanic’s lien against the property of GRMC. Compi. Ex. 2.

Page 3 of 17 1 12. In the mechanic’s lien, Kinden claimed the amount of $2,841,309.88 as the reasonable

2 value of all labor, materials, services, and equipment on the Project. Id.

13. On January 19, 2016, Kinden brought a complaint for foreclosure of mechanic’s lien and

unjust enrichment against GRMC and breach of contract and unjust enrichment against 5 DCK. Compi. pp. 4-7. 6 14. In August 2016, GRMC determined that $1,900,999.03 of Kinden’s $2,841,309.88 7 mechanic’s lien was for Kinden’s Payment Applications, all amounts claimed under 8 retention, and a percentage of the Requests for Equitable Adjustments (hereinafter

“REA”), which GRMC did not dispute, and therefore settled by paying Kinden 10

11 $1,900,999.03. This left a remaining amount of $766,744.96, representing Kinden’s

12 remaining REA Claims, Standby Manpower Claims, and Payment Application #26 for

13 $170,836.00, all of which GRMC disputes. Deci. of Margaret A. Bengzon ¶ 8.

14 15. On September 28, 2016, Kinden reduced its lien amount to $337,188.60 and filed an

15 Amended Lien. Id. ¶9. 16 16. GRMC claims that upon its payment to Kinden of $1,900,999.03 in August 2016, it 17 satisfied its debt to Kinden and properly settled the mechanic’s lien. Kinden continues to 18 claim $170,836.00 against GRMC for services performed and billed in Payment 19 Application #26. Mot. For Summary Judgment pp. 13-14. 20 17. The parties mutually agreed to have the case mediated starting in January 2018, but by 21 April 2018, it became apparent that mediation efforts were failing and both parties 22 stayed arbitration pending this lawsuit. Opp. Mot. For Summary Judgment. p. 6. 23

24 ISSUES

25 1. Whether Kinden exhausted all available legal remedies.

26 2. Whether Kinden’s Mechanic’s lien is valid.

Page 4 of 17 1 3. Whether DCK was an agent of GRMC.

2 4. Whether Kinden may recover for labor and materials supplied to GRMC under the

doctrine of quantum meruit and unjust enrichment.

PRINCIPLES OF LAW 5 I. Motion for Summary Judgment 6 Summary judgment is regulated by Rule 56 of the Guam Rules of Civil Procedure. 7 Guam R. Civ. P. 56. Summary Judgment is appropriate if the pleadings, deposition, 8 interrogatories, and admissions on file together with the affidavits, if any, show that there is no 9 genuine issue as to any material fact and that the moving party is entitled to judgment as a 10 matter of law. Guam R. Civ. P. 56(c); Izuka Corp. v. Kawasho International, (Gttam), Inc., 1997 11 Guam 10 ¶ 7. In addition, 12

13 a party seeking summary judgment always bears the initial responsibility of informing the district court of the basis for its motion, and identifying those 14 portions of “the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any,” which it believes demonstrate the 15 absence of a genuine issue of material fact.

16 Celotex Corp. V.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Losli v. Foster
222 P.2d 824 (Washington Supreme Court, 1950)
Forest Oil Corp. v. Tenneco, Inc.
626 F. Supp. 917 (S.D. Mississippi, 1986)
Grigsby v. Hagler
78 P.2d 444 (California Court of Appeal, 1938)
Maloney v. Therm Alum Indus. Corp.
636 So. 2d 767 (District Court of Appeal of Florida, 1994)
Corn v. Greco
694 So. 2d 833 (District Court of Appeal of Florida, 1997)
Aladdin Const. Co. v. John Hancock Life Ins. Co.
914 So. 2d 169 (Mississippi Supreme Court, 2005)
Clapp v. Goffstown School District
977 A.2d 1021 (Supreme Court of New Hampshire, 2009)
Truestone, Inc. v. Simi West Industrial Park II
163 Cal. App. 3d 715 (California Court of Appeal, 1984)
Lambert v. Superior Court
228 Cal. App. 3d 383 (California Court of Appeal, 1991)
Kim v. JF ENTERPRISES
42 Cal. App. 4th 849 (California Court of Appeal, 1996)
Angino v. Jeffrey R. Lessin & Associates
131 A.3d 502 (Superior Court of Pennsylvania, 2016)
C.A. MacOmber v. L. M. Bigelow
58 P. 312 (California Supreme Court, 1899)
Burnett v. Glas
97 P. 423 (California Supreme Court, 1908)
Bivens v. Salt Lake City Corp.
2017 UT 67 (Utah Supreme Court, 2017)
Dynamex Operations W., Inc. v. Superior Court of L. A. Cnty.
416 P.3d 1 (California Supreme Court, 2018)
Time Warner City Cable v. Adelphi University
27 A.D.3d 551 (Appellate Division of the Supreme Court of New York, 2006)
G.K. Alan Associate Inc. v. Lazzari
66 A.D.3d 830 (Appellate Division of the Supreme Court of New York, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
Kinden Corp. v. Guam Healthcare Dev, Inc. DBA GRMC. DCK Worldwide, LLC and DOES I-III, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kinden-corp-v-guam-healthcare-dev-inc-dba-grmc-dck-worldwide-llc-and-superctguam-2019.