Kimiko Toma v. Utah Power & Light Company

365 P.2d 788, 12 Utah 2d 278, 1961 Utah LEXIS 237
CourtUtah Supreme Court
DecidedOctober 26, 1961
Docket9402
StatusPublished
Cited by19 cases

This text of 365 P.2d 788 (Kimiko Toma v. Utah Power & Light Company) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kimiko Toma v. Utah Power & Light Company, 365 P.2d 788, 12 Utah 2d 278, 1961 Utah LEXIS 237 (Utah 1961).

Opinions

NELSON, District Judge.

In this action, the plaintiff, as adminis-tratrix of the Estate of Fred R. Shook, Jr., deceased, seeks judgment against the defendant for the death of the said decedent, alleging he was killed because of the negligence of the defendant.

The burden of proving negligence is on the plaintiff. The lower court held, by its judgment for directed verdict, that the plaintiff had failed to produce evidence sufficient to discharge this burden.

On appeal from a directed verdict we must review the evidence in the light most favorable to the losing party.1 This, however, does not mean we must ignore undisputed facts which may be favorable to the prevailing party.

The record shows: Fred R. Shook, Jr. was killed on September 5, 1956, at about the hour of 5 :30 p. m. He was 27 years of age, and that at that time he was working as a labor foreman for the Mountain-States Construction Company. This company had previously contracted with the Bureau of Reclamation to construct a diversion dam across the Weber River at Slaterville, in a rural area west of Ogden, Utah. Work had commenced in July, 1956. The construction area was in close proximity to high tension wires owned and maintained by the defendant. From the-last week in July, 1956, until the day of his death, Shook had labored around and about these wires.

The job required diverting the river so-the dam could be built across the river bed. It involved excavating for the dam, putting' in cut-off walls on the sides of the banks, making the forms and footings and pouringcement of which the dam was constructed.

The work proceeded during July and'. August. The north half of the dam was. poured without incident. During August,. Lawrence L. Trumbo, a sub-contractor,, brought in a toll rig to place cement foundations for the cut-off walls on the north and south sides of the river bed.

The Utah Power & Light Company installed hot tops which could be used to de-energize the hot wires. When Mr. Trumbo-commenced work he requested the Utah Power & Light Company to place a pole-in the river bed to lift power lines, and at another time he requested the Utah Power [281]*281•& Light Company to turn the power off. In each instance the Utah Power & Light Company complied with the request. The record further shows two telephone numbers of defendant’s offices were posted on property of Mountain States Construction Company to be used for making requests to turn off power.

At 7:00 a. m. on September 6, 1956, the Mountain States Construction Company started to pour cement on the south side of the dam. The method of pouring was by ■a crane with a 55-foot boom placed at the southern corner of the damsite approximately 20 feet east of the dam. Ira Whitney, the crane operator’s helper, estimated the crane was 50 feet west of the lines ■and Warren Thompson, crane operator, estimated crane was 30 feet west of power lines. Trucks loaded with ready-mix cement backed into an area northeast of ■crane and deposited the cement into a half-yard bucket placed on the ground at the rear of the trucks. The trucks were parked •at an angle facing northeast so that part of the truck would probably be under the wire (this is disputed fact). After the truck unloaded the ready mix into the bucket, the crane picked up the filled cement bucket, then swung the bucket to the west and dropped the cement on the damsite. Then the boom swung back eastward toward the truck and toward the power line and deposited the bucket on the ground in its original position. Plaintiff’s evidence (controverted by other evidence) is that the position of the bucket when picked up by the boom would be 10 to 12 feet west of the spot directly under the power lines. At all times the boom was in the vicinity of the wires and to go from one side of the wire to the other it was necessary to lower the boom. This occurred as often as several times a day.

Some time prior to 5 :30 p. m. on September 6, 1956, Shook was directed to take a truck and request the operating engineer to put the bucket of the crane on the body of the truck. He backed into the spot (disputed) that a truck had used all day. The operator raised the bucket and placed it on the truck, and in so doing the cable of the boom either contacted or came so close to the hot wire as to cause the electricity to arc contacting the truck, killing Shook, who was standing at the side of the truck.

Loren Kay Waldren, project engineer for the Mountain States Construction Company, testified that three or four days prior to date of accident he requested by telephone the Utah Power & Light Company to de-energize the lines and the one answering the phone said the Utah Power & Light Company refused to do so. The Utah Power & Light Company denies any such phone call was made and their witness testified all requests made by the Mountain States Construction Company to turn off power had been granted. Both the plaintiff and the defendant were fully aware of the [282]*282construction area, the proximity of the wires to the damsite and the nature and types of equipment being used. Both knew that at all times after the 1st of August, 1956, there were three cranes in the construction area with booms 65, 45 and 40 feet long. Both knew the wires carried 12,500 volts with 7,200 volts to the ground and that they were at least 30 feet high; that at least 6 feet of pole was buried so that the wire including sag would be approximately 23 feet above the ground. One 45-foot pole was placed in the stream which was 14 to 15 feet lower than the bank. This provided a maximum clearance over the bed of 39 feet.

On this record the lower court granted a motion for a directed verdict for the defendant and took the case from the jury.

Plaintiff’s appeal raises two major questions :

1. Was the trial court correct in refusing to submit the issue of defendant’s alleged negligence to the jury?

2. Was the trial court correct in deciding that the sole' proximate cause of the death of Fred R. Shook, Jr. was the negligence of certain employees of the Mountain States Construction Company?

If the answer is yes to either or both of the questions, then the trial court should be affirmed. Only if the answer is no to both questions should the lower court be reversed. After a careful review of the record we conclude the answer to question one is no and the answer to question two is yes.

Our reasons for so holding are hereinafter set out. This is an action based on alleged tort. A tort is a legal wrong committed by one against the person or property of another. It is the violation of a duty imposed by law. Three elements of every tort action are (1) existence of a legal duty from defendant to plaintiff; (2) breach of that duty; (3) damage as a proximate result.2 It may arise by the violation of the duty in a given transaction, or by invasion of some public duty by which damages accrue to the individual.3

The defendant in this case was engaged as a public utility in furnishing electric power to a large number of customers. It was furnished various persons under different and peculiar circumstances. In all cases it is required to exercise the degree of care that a person of ordinary prudence would under the circumstances. It is well known that one dealing with electricity deals with a force of dangerous character and that there is a constant risk of injury to persons or property if not [283]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Green
770 S.E.2d 424 (Court of Appeals of South Carolina, 2015)
Williams v. Melby
699 P.2d 723 (Utah Supreme Court, 1985)
Godesky v. Provo City Corp.
690 P.2d 541 (Utah Supreme Court, 1984)
Little America Refining Co. v. Leyba
641 P.2d 112 (Utah Supreme Court, 1982)
Unthank v. United States
533 F. Supp. 703 (D. Utah, 1982)
Cooke v. Mortensen
624 P.2d 675 (Utah Supreme Court, 1981)
Massey v. Utah Power & Light
609 P.2d 937 (Utah Supreme Court, 1980)
Alvin H. Wright v. United States of America
568 F.2d 153 (Tenth Circuit, 1978)
Amoss v. Broadbent
514 P.2d 1284 (Utah Supreme Court, 1973)
Smith v. Alfred Brown Company
493 P.2d 994 (Utah Supreme Court, 1972)
Denney v. St. Mark's Hospital
442 P.2d 944 (Utah Supreme Court, 1968)
Hall v. Blackham
417 P.2d 664 (Utah Supreme Court, 1966)
Matilde Colón Widow of Dávila v. Puerto Rico Water Resources Authority
90 P.R. 316 (Supreme Court of Puerto Rico, 1964)
Velasquez v. Greyhound Lines, Inc.
366 P.2d 989 (Utah Supreme Court, 1961)
Kimiko Toma v. Utah Power & Light Company
365 P.2d 788 (Utah Supreme Court, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
365 P.2d 788, 12 Utah 2d 278, 1961 Utah LEXIS 237, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kimiko-toma-v-utah-power-light-company-utah-1961.