KICC-Alcan General, Joint Venture v. Crum & Forster Specialty Insurance Co.

242 F. Supp. 3d 869, 2017 WL 1030372, 2017 U.S. Dist. LEXIS 37560
CourtDistrict Court, D. Alaska
DecidedMarch 16, 2017
DocketCase No. 3:15-cv-00255-SLG
StatusPublished
Cited by4 cases

This text of 242 F. Supp. 3d 869 (KICC-Alcan General, Joint Venture v. Crum & Forster Specialty Insurance Co.) is published on Counsel Stack Legal Research, covering District Court, D. Alaska primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
KICC-Alcan General, Joint Venture v. Crum & Forster Specialty Insurance Co., 242 F. Supp. 3d 869, 2017 WL 1030372, 2017 U.S. Dist. LEXIS 37560 (D. Alaska 2017).

Opinion

ORDER RE CROSS MOTIONS FOR SUMMARY JUDGMENT

Sharon L. Gleason, UNITED STATES DISTRICT JUDGE

Before the Court are Defendant’s' and Plaintiffs Cross Motions for Summary Judgment, at Dockets 34 and 37, respectively. The motions are fully briefed,1 and. the Court heard oral argument on November 1, 2016.2

BACKGROUND

The parties have largely stipulated to the relevant facts.3

Plaintiff KICC-Alcan General (KICC) is an Alaskan joint venture that provides general contracting and construction management services. In May 2012, KICC entered a contract with the U.S. Army Corps of Engineers to-construct two buildings at Joint Base Elmendorf-Richardson.4 KICC entered into two subcontracts with three businesses collectively operating as the Superior Group to perform HVAC, electrical, and plumbing work on the project,5 Pursuant to the first subcontract, the Superior Group would perform certain HVAC and plumbing work in exchange for a lump sum of $3,991,545.6 Under the second subcontract, the Superior Group would perform certain electrical work in exchange for a lump sum of $3,635,468.7

As often happens, the project encountered a series of delays. Consequently, it was not substantially complete until April 2014 — over three months after the initially projected completion date.8 According to the Superior Group, their work was “repeatedly delayed by the actions of [KICC].”9 The Superior Group maintained that, by the end, all the “delays, acceleration, and related impacts caused an increase in the cost- of performance” for the Superior Group, resulting in claimed damages to the Superior Group of nearly $2 million dollars.10

[871]*871To account for its increased costs, the Superior Group tendered a “Request for Equitable Adjustment” (REA) to KICC in August, 2014.11 In federal' contracting, an REA is the opening salvo in a negotiation for a modification to the contract — usually in response to a directed or constructive change by the government.12 In this case, KICC was acting as the general contractor for a federal contract, and so the Superior Group presented the REA to KICC. In order to obtain the desired equitable adjustment, the Superior Group had to show a change to its contractual obligations that was caused by KICC and which harmed the Superior Group.13 Thus, the REA asserted that the initial delays had not been “managed by KICC-Alcan in a. fair and transparent manner” and that the “lack of communication” between KICC and the Superior Group and “the failure of KICC-Alcan to mitigate the effects of the various schedule delays” directly damaged the Superior Group.14 After some limited discussion between .KICC and the Superior Group, KICC rejected the REA.15

The Superior Group then sued.16 Its complaint recounted the allegations about KICC’s mismanagement of the project, and asserted that KICC “continued to direct the [Superior Group] to complete the work according to the original Project schedule.”17 The Superior Group made two specific claims.18 First, the Superior Group alleged “breach of express contract,” contending that the Superior Group “did supply the services and labor required by Superior’s subcontract with KICC-Alcan, which services and labor were accepted by KICC-Alcan and incorporated into the Project, but KICC-Alcan has failed to pay [the Superior Group] in full for the services and labor provided.”19 Second, the Superior Group alleged “quantum meruit,” contending that the Superior Group “provided valuable labor and services to KICC-Alcan” and that KICC “has failed and refused to pay the [Superior Group] for the labor and services referenced herein.” 20

During the relevant period, KICC had insurance from Defendant Crum & Forster Specialty Insurance Company (Crum & Forster) which provided coverage for “ ‘damages’ ,.. because of a ‘wrongful act’ to which this insurance applies.”21 A “wrongful act” is defined in the policy as “an act, error or omission in the rendering or failure to render ‘professional services’ by any insured.”22 And the contract defines “professional services” as “those functions performed for others by you or [872]*872by others on your behalf that are related •to your practice as a consultant, engineer, architect, surveyor, laboratory or construction manager.”23 Read together, then, the contract provided coverage for “damages” caused by “an act, error or omission” in KICC’s rendering or failure to render” its “functions ... that are related to [its] practice as a ... construction manager.”24

Faced with the Superior Group’s lawsuit, KICC tendered the complaint to Crum & Forster, seeking defense and indemnity.25 There was apparently some confusion as to whether Crum & Forster initially accepted defense of the matter,26 but on June 9, 2015 Crum & Forster unequivocally denied coverage for and defense of the lawsuit.27 KICC therefore proceeded with its own defense, and ultimately settled with the Superior Group before trial.28

In the present suit, KICC asserts three causes of action: first, that Crum & Forster breached its duty to defend; second, that Crum & Forster breached its duty to indemnify; and third, Crum & Forster’s refusal to defend or indemnify breached its duty of good faith.29 The parties have stipulated to the facts relevant to liability, and agree that the issue of liability is appropriate for summary judgment.30

DISCUSSION

I. Jurisdiction

The Court has jurisdiction pursuant to 28 U.S.C. § 1382 because there is complete diversity of citizenship and the amount in controversy exceeds $75,000.

II. Standard for Summary Judgment

Federal Rule of Civil Procedure 56(a) directs a court to “grant summary judgment if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” The burden of showing the absence of a genuine dispute of material fact lies with the moving party.31 If the moving party meets this burden, the non-moving party must present specific factual evidence demonstrating the existence of a genuine issue of fact.32 The non-moving party may not rely on mere allegations or denials.33 Rather, that party must demonstrate that enough evidence supports the alleged factual dispute to require a finder [873]*873of fact to make a determination at trial between the parties’ differing versions of the truth.34

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
242 F. Supp. 3d 869, 2017 WL 1030372, 2017 U.S. Dist. LEXIS 37560, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kicc-alcan-general-joint-venture-v-crum-forster-specialty-insurance-co-akd-2017.