Keystone Building Corp. v. Lincoln Savings and Loan Ass'n

360 A.2d 191, 468 Pa. 85, 1976 Pa. LEXIS 661
CourtSupreme Court of Pennsylvania
DecidedJuly 6, 1976
Docket181
StatusPublished
Cited by57 cases

This text of 360 A.2d 191 (Keystone Building Corp. v. Lincoln Savings and Loan Ass'n) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Keystone Building Corp. v. Lincoln Savings and Loan Ass'n, 360 A.2d 191, 468 Pa. 85, 1976 Pa. LEXIS 661 (Pa. 1976).

Opinion

OPINION OF THE COURT

ROBERTS, Justice.

This case involves a dispute over an alleged breach of contract by appellant Lincoln Savings and Loan Association. The controversy between Lincoln and appellee Keystone Building Corporation has been the subject of protracted litigation including an earlier appeal to this Court, 439 Pa. 444, 266 A.2d 648 (1970). On remand, the trial court held that a decree entered by consent of the parties is res judicata on the issue of Lincoln’s liability for breach of contract. The Superior Court affirmed and we granted the petition for allowance of appeal. 1 We find that there was no determination of Lincoln’s liability, reverse the order and remand for further proceedings.

The Keystone Building Corporation, the Lincoln Savings and Loan Association and the Manufacturers Life Insurance Company of Canada entered into a construction loan agreement on October 7, 1968. Under the terms of the agreement Lincoln agreed to lend Keystone the funds necessary to finance Keystone’s construction of an apartment complex and Manufacturers agreed to be the permanent mortgagee for the project.

In May 1969, approximately two months after construction had begun, a dispute arose between Lincoln and Keystone over the terms and conditions under which Lincoln was obligated to advance the necessary funds. The dispute revolved around the nature and sufficiency of the *88 proofs of expenditure which Keystone was required to present to Lincoln as a precondition for payment. Keystone believed it was submitting the vouchers in the proper form. Lincoln refused payment contending that the vouchers were not in accordance with the contract requirements. After protracted negotiations, Keystone commenced a suit in equity on July 3, 1969, asking that Lincoln be compelled to advance the requisitioned loan proceeds and that money damages be assessed against Lincoln for its asserted breach of contract.

On July 18, 1969, the court entered a consent decree based on an agreement between counsel for both parties. 2 The decree sought to resolve the dispute between Keystone and Lincoln concerning the form of the vouchers necessary to authorize payments. The decree provided that Keystone had to support its present and future requisitions for loan proceeds in a specified manner and that Lincoln had to advance the amounts thus requisitioned promptly. Unfortunately, Keystone and Lincoln could not agree on the implementation of the decree and the dispute continued unabated. On August 5, Keystone petitioned for and was granted a rule to show cause why Lincoln should not be held in contempt for failing to comply with the July 18 decree.

A lengthy hearing was held and, on October 6, the court decreed that although Lincoln had not been in contempt, it was obligated to provide Keystone with the funds properly qualified under the construction loan agreement and to advance all sums properly requisitioned thereafter. The court found that certain other expenses were not payable because they were beyond the terms of the construction loan agreement. The October 6 decree did not address whether Keystone was entitled to damages caused by Lincoln’s alleged breach of the contract. There is no indication that either the court or the *89 parties focused on anything other than how the vouchers should be submitted and which amounts were properly included for payment.

Lincoln did not make the payments immediately and, on October 10, Keystone again petitioned for and was granted a rule to show cause why Lincoln should not be held in contempt. Lincoln filed a motion to dismiss the rule contending it was premature. It argued that Pa.R. Civ.P. 1518 allows twenty days to file exceptions to the October 6 order and that the twenty days had not yet run. The trial court ruled that Lincoln was not entitled to file exceptions to the October 6 decree because that decree “only interprets the final decree of the Court of July 18,1969.” Appeal was taken to this Court.

During the pendency of the appeal Manufacturers took an assignment from Lincoln of all its interest in the agreement. Lincoln then petitioned this Court to dismiss the appeal or remand the case to the trial court with directions to dismiss the action. Lincoln argued that because Manufacturers had assumed all of the responsibility for payment of the vouchers the case had become moot. Keystone replied that, although the question of payment on the vouchers may have been mooted by the assignment, the case was not moot because Keystone had sought other relief. Keystone had sought damages in its original complaint for the costs of interim financing and other expenses incurred as a result of Lincoln’s alleged breach.

On July 2, 1970, this Court held that the action in equity would not be dismissed because, even though one of the central issues in the case was moot, Keystone had also sought damages for a breach of contract. We concluded:

“[S]ince there is still the possibility that the court could grant Keystone some sort of relief, the question whether further relief should be granted is initially for the trial court to decide.”

*90 439 Pa. at 448, 266 A.2d at 650. We remanded the case for further proceedings.

On October 14, 1971, on remand, the trial court found that there were no grounds for the award of equitable relief and that there was an adequate remedy at law. The case was transferred to the law side of the court for further proceedings. Keystone then filed its complaint on the law side of the court seeking damages from Lincoln for the alleged breach of the construction loan agreement. Lincoln answered, denying liability.

On April 22, 1975, without motion or petition by either party, Judge Louik entered an order that the case proceed solely on the issue of damages. The trial court stated, referring to the July 18 decree, that there had been a decree of the trial which was “not reversed, and therefore, the prior proceedings should be considered as res adjudicata on the question of [Lincoln’s] liability.” The trial court certified the question for appeal. 3 The Superior Court affirmed in an opinion by Judge Jacobs.

Lincoln raises two arguments on this appeal. First, it argues that the July 18 consent decree — further interpreted by the October 6 decree — acted as a complete settlement or final judgment on Keystone’s cause of action on the contract. 4 Keystone’s action sought specific performance and damages for Lincoln’s alleged failure to perform timely. Although the July 18 and October 6 decrees were directed only to the issue of performance — the payment of the vouchers — Lincoln argues that the entire *91 action on the contract constituted one cause of action 5 which was extinguished by the consent decree.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ANDERSON v. BARITZ
E.D. Pennsylvania, 2025
In Re: Amy Donaghy v.
Third Circuit, 2021
IN RE: AMY CHRISTINE DONAGHY
E.D. Pennsylvania, 2020
Est. of Theodore R. Flint v. Giansante, L.
Superior Court of Pennsylvania, 2019
Moranko, F. v. Downs Racing
118 A.3d 1111 (Superior Court of Pennsylvania, 2015)
R&j Holding Co v. The Redevelopment Authority Of
670 F.3d 420 (Third Circuit, 2011)
RHJ Medical Center, Inc. v. City of DuBois
754 F. Supp. 2d 723 (W.D. Pennsylvania, 2010)
Laird v. Clearfield & Mahoning Railway Co.
916 A.2d 1091 (Supreme Court of Pennsylvania, 2007)
Krentz v. Consolidated Rail Corp.
910 A.2d 20 (Supreme Court of Pennsylvania, 2006)
Laird v. Clearfield & Mahoning Railway Co.
846 A.2d 118 (Superior Court of Pennsylvania, 2004)
State Farm Fire & Casualty Co. v. Bellina
264 F. Supp. 2d 198 (E.D. Pennsylvania, 2003)
McKenna v. Sosso
745 A.2d 1 (Superior Court of Pennsylvania, 1999)
Soto v. PNC Bank (In Re Soto)
221 B.R. 343 (E.D. Pennsylvania, 1998)
Roberts v. Estate of Pursley
700 A.2d 475 (Superior Court of Pennsylvania, 1997)
Coover v. Saucon Valley School District
955 F. Supp. 392 (E.D. Pennsylvania, 1997)
SHIRLEY BY SHIRLEY v. Javan
684 A.2d 1088 (Superior Court of Pennsylvania, 1996)
Generali-U.S. Branch v. Genesis Insurance
925 F. Supp. 224 (S.D. New York, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
360 A.2d 191, 468 Pa. 85, 1976 Pa. LEXIS 661, Counsel Stack Legal Research, https://law.counselstack.com/opinion/keystone-building-corp-v-lincoln-savings-and-loan-assn-pa-1976.