Kentucky Power Co. v. Huelsmann

352 F. Supp. 2d 777, 2005 U.S. Dist. LEXIS 1339, 2005 WL 121734
CourtDistrict Court, E.D. Kentucky
DecidedJanuary 18, 2005
DocketCIV.A.3:03-47-JMH
StatusPublished
Cited by3 cases

This text of 352 F. Supp. 2d 777 (Kentucky Power Co. v. Huelsmann) is published on Counsel Stack Legal Research, covering District Court, E.D. Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kentucky Power Co. v. Huelsmann, 352 F. Supp. 2d 777, 2005 U.S. Dist. LEXIS 1339, 2005 WL 121734 (E.D. Ky. 2005).

Opinion

MEMORANDUM OPINION AND ORDER

HOOD, District Judge.

This matter is before the Court on two separate but interrelated motions. Plaintiffs, Louisville Gas and Electric Company (“LG & E”), Kentucky Utilities Company (“KU”), and Kentucky Power Company (“Kentucky Power”), filed motions for summary judgment [Record Nos. 30 and 74, respectively]. In support of their motions, Plaintiffs filed memorandums of law [Record Nos. 31 and 75, respectively]. All of the Defendants, Gary W. Gillis, Martin J. Huelsman, and Robert E. Spurlin, in their official capacities as Commissioners of the Kentucky Public Service Commission (“PSC”), the Kentucky Attorney General, Albert B. Chandler (“AG”), and Midwest Independent Transmission System Operator, Inc. (“Midwest ISO” or “MISO”) filed responsive memorandums of law [Record Nos. 36 & 82, 80, and 85, respectively], LG & E, KU, and Kentucky Power replied [Record Nos. 83 and 86, respectively]. Having considered all the filings, and being otherwise sufficiently advised, the Court deems this matter ripe for review.

RELEVANT PROCEDURAL BACKGROUND

On July 18, 2003, Plaintiffs, LG & E, KU, and Kentucky Power, initiated two separate actions. Both actions sought judgments declaring KRS 278.214 facially invalid under the Commerce Clause to the United States Constitution, and preempted by federal law. These actions were filed against the commissioners of the Public Service Commission of Kentucky (“PSC”) *780 in their official capacities, 1 the PSC itself, the Attorney General of the Commonwealth of Kentucky in his official capacity, and Kentucky Industrial Utility Customers, Inc. (“KIUC”). The two actions were consolidated for all purposes by Order filed October 27, 2003.

The PSC, the Attorney General, and KIUC subsequently moved to dismiss Plaintiffs’ complaints on the ground of abstention — Plaintiffs were simultaneously challenging the validity of KRS 278.214 in a Kentucky state court proceeding. In addition, in the LG & E/KU-initiated case, the PSC, the Attorney General, and KIUC filed cross-motions for summary judgment. On December 18, 2003, before ruling on the summary judgment motions, this Court dismissed Plaintiffs’ actions without prejudice, citing the abstention doctrine set out in Younger v. Harris, 401 U.S. 37, 91 S.Ct. 746, 27 L.Ed.2d 669 (1971). Plaintiffs responded by filing motions to vacate. This Court granted Plaintiffs’ motions and reinstated the actions explaining that abstention was not warranted because the case ultimately dealt with a federal question, ie., whether KRS 278.214 was facially preempted by federal law.

On March 25, 2004, Plaintiffs filed a First Amended Complaint, naming Midwest ISO and the Federal Energy Regulatory Commission (“FERC”) as additional defendants. Midwest ISO answered, denying that LG & E and KY were entitled to the declaratory judgment they sought and stating that it was unaware of any actualized conflict between KRS 278.214 and federal law or Midwest ISO’s tariff. FERC moved to dismiss the First Amended Complaint for failure to state a claim upon which relief against it could be granted. The Court granted FERC’s motion on August 5, 2004, and dismissed the agency from this case.

RELEVANT FACTUAL BACKGROUND

Electric Energy

As the electric utility industry developed in the United States, transmission lines first built to transport energy from point (generation source) to point (distribution substations) began to be interconnected with each other, forming networks in which there were alternative routes between generation and consumption points. This process eventually created three major networks, or power grids. These networks consist of extra-high-voltage connections designed to permit the transfer of electrical energy from one part of the network to another. The three networks are: (1) the Eastern Interconnection consisting of the eastern two-thirds of the United States; (2) the Western Interconnection consisting primarily of the Southwest and areas west of the Rocky Mountains; and, (3) the Texas Interconnection. The Texas grid is not connected with the other two (except by certain direct current lines), and the other two networks have only limited connections to each other. Through these three major grids, every utility in the 48 contiguous states is interconnected with at least one other utility. The transmission grids make it possible “for power companies to transmit electric energy over long distances at a low cost.” New York v. FERC, 535 U.S. 1, 7-8, 122 S.Ct. 1012, 152 L.Ed.2d 47 (2002). This technical ability supported increased competition among power suppliers, however, particular power suppliers were still prevented from effectively competing due to their competitors’ refusal to provide equal *781 access to transmission. lines. Id. at 8-9, 122 S.Ct. 1012.

FERC Order 888

FERC investigated these impediments to competition and, on April 24, 1996, issued Order 888, 2 which became final and effective on July 9, 1996. The stated purpose of Order 888 was to promote competition in the wholesale electricity market by ensuring equal access to transmission services. See New York v. FERC, at 5-11, 122 S.Ct. 1012. Briefly, Order 888 requires utilities owning controlling or operating facilities used for transmitting electric energy in interstate commerce to treat their own use of those transmission facilities under the same transmission, tariffs, they apply to others. To implement the policy of nondiscriminatory access, Order 888 directed all such utilities to file open access nondiscriminatory transmission tariffs (“OATT”), specifying the terms and conditions of transmission service applicable to all eligible customers. FERC’s authority to issue and enforce Order 888 was recently upheld by the United States Supreme Court in New York v. FERC. 3

Order 888 includes a pro forma OATT that sets non-price minimum terms and conditions of nondiscriminatory transmission service. Paragraph 13.6 of the pro forma OATT addresses the procedure for curtailment ■ or interruption of electricity service in response to a transmission capacity shortfall. Specifically, Paragraph 13.6 mandates nondiscriminatory pro rata curtailment of electricity. 4

Through Order 888, FERC encouraged transmission-owning utilities such as LG &

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Transcontinental Gas Pipe Line Corp. v. Louisiana Tax Commission
23 So. 3d 329 (Louisiana Court of Appeal, 2009)
In Re the Appeals of CIG Field Services Co.
112 P.3d 138 (Supreme Court of Kansas, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
352 F. Supp. 2d 777, 2005 U.S. Dist. LEXIS 1339, 2005 WL 121734, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kentucky-power-co-v-huelsmann-kyed-2005.