Kelley v. Bluff Creek Oil Company

309 S.W.2d 208, 158 Tex. 180, 1 Tex. Sup. Ct. J. 136, 1958 Tex. LEXIS 528
CourtTexas Supreme Court
DecidedJanuary 8, 1958
DocketA-6230
StatusPublished
Cited by86 cases

This text of 309 S.W.2d 208 (Kelley v. Bluff Creek Oil Company) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kelley v. Bluff Creek Oil Company, 309 S.W.2d 208, 158 Tex. 180, 1 Tex. Sup. Ct. J. 136, 1958 Tex. LEXIS 528 (Tex. 1958).

Opinions

Mr. Justice Garwood

delivered the opinion of the Court.

Our petitioner Kelley brought this action in his own behalf to recover primarily upon a release bond executed pursuant to Art. 5472c, Vernon’s Texas Civ. Stats., by the respondents-defendant Bluff Creek Oil Company as principal and Commercial Standard Insurance Company as surety for the release of the petitioner’s alleged mechanic’s and materialman’s lien against three Montague County oil leases. Said Art. 5472c prescribes a limitation period of one year for the bringing of such suits, and this suit was filed within the year. However, during all of the year a bank held the lien under a collateral assignment from the petitioner to secure a debt of the latter in an amount somewhat smaller than that of his lien claim, the bank not ever having been made a party to this suit and having reassigned to the petitioner only well after expiration of the year in question. Our principal holding is that, notwithstanding these latter facts, the action is not barred. Other matters decided relate to the contentions of the respondents-defendant, Bluff Creek and Commercial Standard, that under a further provision of Art. 5472c, supra, action upon the bond was precluded by the petitioner’s failure to bring suit within thirty days following his receipt of notice of the bond, as well as by the invalidity of his claimed lien itself; and the contention of Bluff Creek alone (as a petitioner in this Court to that extent) that the Court of Civil Appeals erred in recognizing a personal right of action of Kelley against Bluff Creek, apart from the bond and lien, for the price of the same materials and services which are the basis of the [182]*182alleged lien and were allegedly furnished by Kelley to Bluff Creek as operator of the leases in question.

For the opinion of the Court of Civil Appeals, see 298 S.W. 2d 263.

The case arose as follows:

On January 5th, 1951, the petitioner-plaintiff, seeking a mechanic’s and materialman’s lien against the leases in question, filed an affidavit and annexed account for some $2500 with the county clerk. He thereafter assigned the claim to Wichital National Bank of Wichita Falls by written instrument of March 29th, 1951, reciting a consideration of “Ten ($10.00) Dollars, and other good and valuable considerations” and otherwise purporting to be a complete transfer of ownership “with full power and authority to collect and receipt therefor,” although, as above indicated and as shown without contradiction upon the hereinafter mentioned hearing, its purpose was to secure a debt of the petitioner-assignor to the bank in the sum of some $1900. On May 3rd, 1951, the bond for release of the lien was filed, and notice thereof given the petitioner-plaintiff on the following June 12th, all pursuant to Art. 5472c, supra.

Of the latter statute, the portion bearing most importantly on the case reads:

“Sec. 4. No action shall be brought or maintained in any court to establish, enforce or foreclose any lien or claim of lien referred to in such bond unless same shall be brought within thirty days after the service of notice thereof as herein provided. After such 30 days and at any time within one year from the date of such service, the party making or holding such claim of lien may sue upon such bond but no action shall be brought upon such bond after the expiration of such period. * * *”

Kelley has never brought any action concerning his claim except the present suit which he filed on April 24th, 1952 (about ten months after being served with notice of the bond) seeking judgment for the amount of his claim primarily upon the bond and alternatively, and apart from the bond and the lien, a simple money judgment against Bluff Creek alone for the amount of his claim. The mentioned date of suit was, of course, within the one-year limitation period for action on the bond, but some nine months after expiration of the thirty-day period for suits “to establish, enforce or foreclose any lien * * * .” At the time Kelley filed suit, moreover, and until long after passage of the [183]*183remaining two months of the statutory one-year period, his assignment to the bank remained in effect; nor did his original petition, nor other pleading filed by him refer to the assignment ; nor was the bank ever made a party to the suit.

On May 20th, 1952, the respondent-defendant surety filed an “answer,” alleging, so far as presently relevant, that the suit as against it “should be abated and not further considered because,” the claimed lien was invalid under the lien statutes and was not owned by the petitioner “at this time” (by reason of the petitioner having assigned it) and because no foreclosure suit had been commenced within the statutory thirty-day period provided therefor.

On July 15th, 1953, prior to any hearing upon the pleas in the case, the bank reassigned to the petitioner-plaintiff his alleged claim and lien by instrument acknowledging the collateral character of the original assignment and full payment of the debt secured.

On May 11th, 1954, the respondent-defendant, Bluff Creek, filed two pleas, the presently relevant grounds of which were substantially the same as the above-mentioned earlier pleas of the respondent-defendant surety.

In March, 1956, the trial court heard the above-described pleas, with evidence thereon, and dismissed the entire suit, including the alternative count against Bluff Creek alone and apart from the bond and lien. The dismissal was expressly and exclusively based on the alleged failure of the petitioner-plaintiff (a) to begin a suit “to establish, enforce or foreclose” his lien within the thirty-day period and (b) to sue, as and while owner of the claim, within the one-year period. The Court of Civil Appeals affirmed as to the primary count (on the bond) sustaining ground (b) of the trial court in this behalf, but reversed and ordered a trial on the merits as to the alternative count against Bluff Creek alone. 298 S.W. 2d 263. We granted writ of error, on application of the petitioner-plaintiff, Kelley, to review the affirmance and, because of this action, granted also the application of Bluff Creek questioning the reversal.

Our earlier statement, that the above holding (b) presents the principal question in the case, means that holding (a) of the trial court appears to us rather clearly without merit, as, indeed, it evidently did also to the Court of Civil Appeals. Art. 5472c was enacted in 1929 (Chap. 211, 41st Leg., Reg. Sess.). [184]*184Its provisions plainly reflect, without benefit of the emergency clause, and even more plainly with it, that its object is to free land from liens by substitution of a surety on an indemnity bond for the security otherwise afforded the unpaid mechanic, contractor or materialman by his lien claimed under Chap. 2 of Title 90, R. S. 1925. Its declared motives include that of enabling landowners, in need of loans upon their lands, to avoid delays from prior claims of liens, as well as that of easing the pressure of foreclosure threats of lien claimants. The statute deals altogether with liens and in nowise purports to affect claims asserted otherwise than as liens.

While we later refer further to the alternative count of the petitioner for a mere money judgment against the respondent, Bluff Crek, alone and apart from the bond or claimed lien, it should doubtless be noted now that this count cannot conceivably be affected by the thirty-day limitation period (or, for that matter, the one-year period) of the statute.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Armando Velardez v. Carlos E. Parra Jr.
Court of Appeals of Texas, 2022
In Re Fh Partners, L.L.C.
335 S.W.3d 752 (Court of Appeals of Texas, 2011)
Robert D. Shipley v. Unifund CCR Partners
Court of Appeals of Texas, 2010
City of New Braunfels v. Allen
132 S.W.3d 157 (Court of Appeals of Texas, 2004)
Danny Joubert v. State
Court of Appeals of Texas, 2004
In Re Canales
113 S.W.3d 56 (Texas Supreme Court, 2003)
ADKINS SERVICES INC. v. Tisdale Co., Inc.
56 S.W.3d 842 (Court of Appeals of Texas, 2001)
Stolz v. Honeycutt
42 S.W.3d 305 (Court of Appeals of Texas, 2001)
Howell v. Texas Department of Criminal Justice
28 S.W.3d 125 (Court of Appeals of Texas, 2000)
Mestiza v. De Leon
8 S.W.3d 770 (Court of Appeals of Texas, 1999)
University of Houston v. Elthon
9 S.W.3d 351 (Court of Appeals of Texas, 1999)
Martin v. DOSHOS I, LTD., INC.
2 S.W.3d 350 (Court of Appeals of Texas, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
309 S.W.2d 208, 158 Tex. 180, 1 Tex. Sup. Ct. J. 136, 1958 Tex. LEXIS 528, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kelley-v-bluff-creek-oil-company-tex-1958.