Keating v. Federal Energy Regulatory Commission

569 F.3d 427, 386 U.S. App. D.C. 270, 2009 U.S. App. LEXIS 13264, 2009 WL 1709215
CourtCourt of Appeals for the D.C. Circuit
DecidedJune 19, 2009
Docket08-1005
StatusPublished
Cited by39 cases

This text of 569 F.3d 427 (Keating v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Keating v. Federal Energy Regulatory Commission, 569 F.3d 427, 386 U.S. App. D.C. 270, 2009 U.S. App. LEXIS 13264, 2009 WL 1709215 (D.C. Cir. 2009).

Opinion

Opinion for the Court filed by Chief Judge SENTELLE.

SENTELLE, Chief Judge:

The Federal Energy Regulatory Commission granted Joseph Keating a license to build a hydroelectric power plant in 1992. At Keating’s request, the Commission stayed the four-year statutory deadline for commencing construction on the project to allow Keating to obtain the necessary water rights. Over fifteen years after the license issued, the Commission lifted the stay and Keating’s license expired. Keating now petitions for review of the Commission’s decision to lift the stay, arguing that the record does not support *429 the decision and that his reliance on the stay should estop the Commission from lifting it. We deny the petition because Keating was not entitled to an indefinite extension of the stay and the Commission’s findings concerning the remaining hurdles to commencing construction were sufficient to support the denial of a further stay.

I

In July 1992, the Commission issued Keating a license to develop his proposed “Tungstar Project,” a hydroelectric power plant in the Inyo National Forest in California. Joseph M. Keating, Order Issuing License, 60 F.E.R.C. ¶ 61,016 (July 2, 1992). Under the proposed project, a dam would divert water flowing from Morgan Creek and a nearby tungsten mine’s water treatment facility through a 3,500-fooW long penstock to one 990 kilowatt turbine generator. Id. at 61,061. After exiting the powerhouse tailrace, the water would “enter a 4,000-foot-long, man-made, meandering channel where suspended mine water floeculants w[ould] settle out” before the water would enter Pine Creek below its confluence with Morgan Creek. Id.

Under Section 4(e) of the Federal Power Act (FPA), 16 U.S.C. § 797(e), the United States Forest Service may impose conditions on the grant of a license on land within its jurisdiction. The Forest Service required Keating to obtain a special use permit from the Service before starting construction, which he did in November 1995. That permit in turn required Keating to obtain the necessary water rights before beginning construction.

Section 13 of the FPA, 16 U.S.C. § 806, requires a licensee to commence construction of a newly licensed hydroelectric facility within two years of license issuance but allows the Commission to extend the deadline once for a maximum of two additional years. If the licensee does not commence construction within the statutory time frame, then “the license shall ... be terminated” by the Commission after notice to the licensee. Id.; see 18 C.F.R. § 6.3 (requiring 90 days’ notice to the licensee before termination). Nevertheless, the Commission has stayed the commencement-of-construction deadline beyond the statutory four-year period when a licensee was required to await “necessary actions of other federal or state agencies,” such as approval of plans, before commencing construction. Boise-Kuna Irrigation Dist., 111 F.E.R.C. ¶ 61,271, 62,216 (2005); see, e.g., R.L. Garry Corp., 51 F.E.R.C. ¶ 61,-115, 61,310 (1990); cf. Kings River Conservation Dist., 30 F.E.R.C. ¶ 61,151, 61,320 (1985) (describing the Commission’s authority to issue stays as deriving from Section 309 of the FPA, 16 U.S.C. § 825h, and Section 705 of the Administrative Procedure Act, 5 U.S.C. § 705). The Commission stays the deadline only in these and similar “narrowly circumscribed circumstances”; it will not grant a stay “merely to relieve the licensee from the statutorily prescribed commencement of construction deadline.” Ronald E. Rulofson, 62 F.E.R.C. ¶ 61,268, 62,780 (1993); accord Elec. Plant Bd. of the City of Augusta, Ky., 112 F.E.R.C. ¶ 61,342, 62,504 (2005).

Keating requested, and the Commission granted, an extension of the commencement-of-construction deadline for two additional years as permitted under Section 13. See Joseph M. Keating, Order Granting Stay Request in Part and Setting Deadline for Required Filings, 77 F.E.R.C. ¶ 61,060, 61,224 n. 4 (Oct. 21, 1996) (noting that the Commission granted the extension in an unreported order issued April 12, 1994). On his last day to commence construction under the four-year deadline, Keating asked the Commission to stay the deadline while he sought the necessary water rights. The Commission granted a stay of *430 the commencement-of-construction deadline and ordered Keating to file annual reports on the status of his efforts to obtain water rights and satisfy the requirements of his Forest Service permit. Id. at 61,225-26. The Commission did not, however, stay the other requirements of Keating’s license and advised Keating that within six months of the stay order he must file a license amendment application (necessitated by his proposed project redesigns) and eleven outstanding pre-construction plans, addressing topics such as erosion control and wildlife mitigation, some of which needed Forest Service approval in addition to Commission approval. Id.

Seeking the water rights necessary to develop his project and satisfy his Forest Service permit, Keating first argued to the Forest Service that he already had riparian rights to use the water. The Forest Service disagreed and directed Keating to pursue appropriative water rights from the state or a special use permit for use of federal riparian rights. Id. at 61,224 n. 5. Keating instead litigated against the Forest Service from 1997 through 1999 in an attempt to confirm the adequacy of his riparian rights. Ultimately, the district court dismissed his suit, holding the Forest Service entitled to sovereign immunity, and the Ninth Circuit affirmed. See Keating v. U.S. Dep’t of Agric., 178 F.3d 1300, 1999 WL 311353 (9th Cir.1999) (unpub.).

In 2001, Keating began seeking appropriative water rights by filing an application with the California State Water Resources Control Board (Water Board). His application elicited protests from twelve entities; all but one — Pine Creek Mine — were eventually dismissed. Pine Creek Mine owned the mine that discharged some of the water Keating’s Tungstar Project proposed to use and also held its own FERC permit for a proposed hydroelectric project. Of concern to the Water Board was the fact that Pine Creek Mine owned the property encompassing the proposed diversion point for Keating’s project. In accordance with state regulations, the Water Board required Keating to demonstrate his ability to secure the necessary right of access over the land before it would approve his application. See Cal. Admin. Code tit. 23, § 775 (“When the owner will not consent, the board may require satisfactory evidence of the applicant’s ability through condemnation proceedings or otherwise to secure the necessary right of access before the application will be approved.”).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lebidine v. Del Toro
District of Columbia, 2025
WA Alliance of Tech. Workers v. DHS
50 F.4th 164 (D.C. Circuit, 2022)
Center for Biological Diversity v. Ashe
District of Columbia, 2020
Sprint Corp. v. Dep't of the Interior
356 F. Supp. 3d 12 (D.C. Circuit, 2018)
Pierce v. Securities & Exchange Commission
786 F.3d 1027 (D.C. Circuit, 2015)
Emanuel Medical Center, Turlock, California v. Sebelius
37 F. Supp. 3d 348 (District of Columbia, 2014)
['ASSOCIATED BUILDERS AND CONTRACTORS, INC. v. SHIU']
30 F. Supp. 3d 25 (District of Columbia, 2014)
Hildreth v. Obama
950 F. Supp. 2d 63 (District of Columbia, 2013)
Adirondack Medical Center v. Sebelius
935 F. Supp. 2d 121 (District of Columbia, 2013)
District Hospital Partners, L.P. v. Sebelius
932 F. Supp. 2d 194 (District of Columbia, 2013)
Safari Club International v. Salazar
709 F.3d 1 (D.C. Circuit, 2013)
Ferguson v. Long
885 F. Supp. 2d 294 (District of Columbia, 2012)
In Re Polar Bear Endangered Species Act Listing
818 F. Supp. 2d 240 (District of Columbia, 2011)
Ctr. for Biological Diversity v. Salazar
818 F. Supp. 2d 214 (District of Columbia, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
569 F.3d 427, 386 U.S. App. D.C. 270, 2009 U.S. App. LEXIS 13264, 2009 WL 1709215, Counsel Stack Legal Research, https://law.counselstack.com/opinion/keating-v-federal-energy-regulatory-commission-cadc-2009.