Katz v. Judice

252 So. 2d 532, 1971 La. App. LEXIS 5563
CourtLouisiana Court of Appeal
DecidedJuly 15, 1971
DocketNo. 4366
StatusPublished
Cited by5 cases

This text of 252 So. 2d 532 (Katz v. Judice) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Katz v. Judice, 252 So. 2d 532, 1971 La. App. LEXIS 5563 (La. Ct. App. 1971).

Opinion

BOUTALL, Judge.

This is a suit by plaintiff, Jerry Katz, d/b/a Jerry’s Construction Company, owner of and general contractor for a proposed apartment building, against subcontractor Joseph Judice, Jr., d/b/a Air Tex Engineering Company, and his assignee under the subcontract, Lennox Industries, Inc. The petition recites that the defendant Judice was to install certain heating and air-conditioning equipment in the apartment building under construction in accordance with a written contract for the contract price of $4,870.00. The petition alleges that the defendants have failed to perform in accordance with the contract and as a result another contractor was called in to complete the contract, causing a loss of $2,403.10, in additional charges. Plaintiff sues for this sum plus an additional $10,200.00 in lost rentals due to delay in completion. The trial court rendered a judgment in favor of the defendants and dismissed plaintiff’s suit at his costs. From this judgment he takes the present appeal.

The basic defense of the defendants is that the contract consisted of two parts, first, a “rough-in” procedure, which, when completed, called for payment of 50% of the contract price, and then the finishing procedure, after which the balance of the price was to be paid. The defendants insist that they proceeded to do the work as called for in the contract and had completed the rough-in at which time it was discovered that there was no building permit for the plans and specifications as provided for in the written contract between plaintiff and defendants, but instead approval had been obtained from the City of New Orleans, Division of Regulatory Inspection, for the installation of a different type system. Because of this, work was stopped on the job and the defendants were prevented from completing the contract. When these difficulties with the regulatory agency were settled, plaintiff had hired a third party contractor to finish the job, although defendants stood ready, willing, and able to do so.

The trial judge, in his Reasons for Judgment, found that the defendants were indeed prevented from completing the job, and rendered judgment in their favor. He found that the work that had been done already by the defendants was proper, but that the trouble started when the city inspectors found that the original plan which has been approved called for an entirely different system of heating. The situation then was such that either the plans had to be changed to the actual installation to meet city approval, or the entire work had to be taken out and started [534]*534all over in order to put in the electrical heating system called for in the original plans. The trial judge concluded that there was no showing by the plaintiff that the defendants were at fault for the difference in plans, and, in fact, it appeared to the trial judge that the plaintiff had much, if not most, of the fault in the misunderstanding that resulted in his financial loss.

An examination of the record reveals that under the written contract between the parties, the defendants were to furnish and install an electrical air-conditioning system and a gas heating system at the premise in question. However, the original plans prepared by the architect and submitted to the City of New Orleans, Division of Regulatory Inspection, for approval called for all-electric air-conditioning and heating systems. All of the testimony is to the effect that the defendants were not furnished with the original plans, and had no way of knowing that there was this difference in the heating system. The defendants began work in accordance with the specifications in their contract, and had completed their obligation to rough-in the two systems, and in accordance with their contract requested payment of half of the contract price, which was promptly paid. The equipment necessary to complete the job was ordered from the defendant Len-nox at that time, and was delivered to the job site to await completion of the contract. At this time, or shortly thereafter, the defendants were notified that there was something wrong with the installation and that it did not meet with the approval of the city inspectors. The installation job was then stopped by the Division of Regulatory Inspection. It is at this point that much of the conflict in the testimony begins.

The plaintiff, Mr. Katz, testified that he had attempted to contact the defendants on numerous occasions in an attempt to induce Justice and his workmen to return and complete the job, and, on at least one occasion, even told Judice that the job had now been reopened by the City, although it was later determined by the defendants that the job still had not been reopened. The testimony of the plaintiff is to the effect that much of the work that had been done by the defendants was improper and that was the reason for the difficulty on the job. However, this contention is not borne out by the testimony of the other witnesses. In fact, the testimony of the inspectors for the City of New Orleans shows that the contrary is true. A consideration of all of the testimony involved leads the court to the inescapable conclusion that the job was stopped by the city inspectors because it was not being done in accordance with the plans that had been submitted along with the initial application for a building permit.

Mr. Judice, in his testimony, insisted that the work was being done properly under the contract, and that there were arguments over certain errors in the plumbing, which was not his responsibility, but that of another subcontractor. The evidence presented bears out this contention. The city inspectors testified that basically there was nothing wrong with the installation as it was, except that it did not comply with the approved plans. There were violations of the building code in connection with the installation of gas lines, but this was the plumber’s responsibility and not the responsibility of the air-conditioning and heating contractor.

Mr. Lopez, who handled the completion of the job for Bann-Schumert, testified that there was nothing wrong with the installation as it existed at the time that they began to work on it, but rather that other things had to be done to bring the job to the condition which he considered to be the completion of the rough-in. An examination of his testimony reveals that the only problem which appeared to have arisen because of faulty work by the defendants was a gap above the air-conditioning coils where the equipment attaches to the duct work, and that it was necessary to fill in this space, a distance of approximately four (4) inches on each machine. How[535]*535ever, he could not testify that this space was left as a result of improper work by defendants and admitted that it could very well have happened as a result of other work done by other subcontractors on the job. He testified that the expenses of additional work to be done to justify the rough-in consisted of connecting this duct work, relocating some gas piping, running some copper tubing and drain lines, installing vents and several other minor items. However, he further testified that a number of these items were work which should properly have been done by the plumber and not by the installer of the air-conditioning and heating equipment, and, further, that others of these items are generally done by the contractor as he proceeds along to completion of the job.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Warwick v. Matheney
603 So. 2d 330 (Mississippi Supreme Court, 1992)
Chrysler Credit Corp. v. Brown
452 So. 2d 810 (Louisiana Court of Appeal, 1984)
Vitenas v. Centanni
381 So. 2d 531 (Louisiana Court of Appeal, 1980)
Lebreton v. Brown
260 So. 2d 767 (Louisiana Court of Appeal, 1972)
Katz v. Judice
254 So. 2d 461 (Supreme Court of Louisiana, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
252 So. 2d 532, 1971 La. App. LEXIS 5563, Counsel Stack Legal Research, https://law.counselstack.com/opinion/katz-v-judice-lactapp-1971.