Farnsworth v. Sewerage Water Board of New Orleans

139 So. 638, 173 La. 1105, 1932 La. LEXIS 1603
CourtSupreme Court of Louisiana
DecidedJanuary 4, 1932
DocketNo. 31390.
StatusPublished
Cited by7 cases

This text of 139 So. 638 (Farnsworth v. Sewerage Water Board of New Orleans) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Farnsworth v. Sewerage Water Board of New Orleans, 139 So. 638, 173 La. 1105, 1932 La. LEXIS 1603 (La. 1932).

Opinion

ODOM, J.

Under contract entered into by these parties, plaintiff obligated himself to build for defendant an extension of drainage, pumping station No. 6. Admittedly plaintiff did all the work he was obligated to do under the contract and specifications. But he claims that defendant is yet due him $8,723.84 for items enumerated in his petition, all of which are denied by defendant.

The present suit is for that amount. There was judgment for plaintiff as prayed for, and defendant appealed.

The first item is for removing and hauling 373 cubic yards of earth to build a levee, for which plaintiff claims he should be paid $1.18 per yard, or $440.14.

Section 28 of the specifications provides that the engineer shall determine the amount of excavated material to be removed from the station site as spoil, and section 29 that all excavation ordered removed shall be paid for at the unit price bid for removing excavated material under item No. 6. Section 1 of the specifications contains this, among other provisions: “This work is divided into (6) six items, upon which bids shall be submitted.” Then follow the six items, No. 6 being “excavated material removed from site of station.”

In plaintiff’s proposal attached to the contract and accepted by defendant we find the following:

“Item 6. For excavated material removed from the site of station, assumed • quantity 22,000 cubic yards, the sum of one dollar and eighteen cents ($1.18) per cubic yard.”

It is admitted that plaintiff was not paid for removing the 373 yards of excavated material used to build the levee, but defendant contends that it owes him nothing for this item because article 30 of the specifications provides that the contractor shall make all excavations required, and that the surplus material shall be deposited to build a leveé as shown, or at some point within a radius of 500 feet from the point where excavated.

It is contended by counsel for defendant, and we think correctly so, that under the contract plaintiff was not to be paid extra for the material excavated and deposited on the '“site of the station,” because that was cov *1109 erecl under another item of the bid. He was to be paid $1.18 per yard for “excavated material removed from the site of the station.”

Whether this material was removed “from the site of the station” is a question of fact. We think it was removed from'the “site of the station.”

Mr. Richard Kohnke, who was an employee of defendant, and who supervised the work done by plaintiff, was asked, “Now wasn’t that levee built with earth hauled from the site of the contract?” and he answered, “Yes,” and further said that it was done in accordance with his instructions. Mr. Farnsworth also stated that the dirt was hauled off the site. Mr. Wood, the engineer, denies this. He said also that plaintiff was not paid for grading this levee, yet in defendant’s answer it is stated, paragraph 4, “Defendant admits paying petitioner for grading the levee.” Mr. Wood either lacked information or his memory was at fault.

Plaintiff should be paid for this work.

Item No. 2 is for extra work done on a levee for which he claims $2,942.69.

After the contract was let, the specifications were revised, and plaintiff was ordered to build the levee higher and to change the slope, which made it more expensive to build.

It is not denied that plaintiff is entitled to some additional remuneration for building this levee, but it is claimed that he did not establish with sufficient certainty the extra amount due. The trial judge thought he did, and we think so too.

Item No. 3 is for the rebuilding of a cofferdam which washed away during the construction of the work, for which plaintiff claims $276.78. This item was allowed by the judge, but we think it should have been rejected. During the construction of the work, plaintiff built a cofferdam in front of the retaining wall of the discharge tube to hold the water out while the retaining wall was being connected with the end of the tube. This cofferdam was in front of a tube which discharged the water pumped by engine No. 4. During the night of March 21, 1930, there was an excessive rainfall, and, in order to dispose of the accumulated water, the engineers in charge of the plant set all the engines, including No. 4 to work, and as a result the cofferdam was washed away.

The complaint which plaintiff makes is that it was not necessary to operate engine No. 4. The engineers thought it was. One of them stated that an emergency existed which made it necessary to operate all the pumps, and that under the circumstances they would have, operated them at any cost.

Section 40 of the specifications provides that “during the progress , of the work the Sewerage and Water Board must operate the pumps in the station with a view of affecting the best possible conditions of general city drainage and this duty is paramount. * * * The Board obligates itself in no respect to maintain any particular status as to drainage conditions at or near the pumping station during the time that this contract is in process of execution.”

Plaintiff, under this provision, assumed the risk of having his works destroyed in case of an emergency. The board is not liable for this item.

Item No. 4 is for extra work done in building a switch track from the Southern Railways tracks to the station. For this plaintiff claims $3,639.'23.

The contract called for the building of a switch track “as shown on the plans,” and plaintiff made his bid accordingly. Later on, engineers for the railroad inspected the plans, and refused to permit the track to .be built *1111 according to the board’s specifications, but required that it be built according to specifications drawn by its own engineers, which were drawn and submitted to plaintiff, who promptly notified Mr. Wood, engineer for defendant. Mr. Wood ordered plaintiff to build the switch according to the railroad’s specifications. The changing of the specifications made the building of the track more expensive.

Mr. Wood says he approved the new specifications, but did not agree for the board to pay the additional expense.

The switch track was necessary, and plaintiff was obligated to build it, but could not build it according to the plans furnished by defendant. The change was agreed to by defendant’s engineer, who knew all the circumstances. The change necessitated extra work, which under section 195 of the specifications and article 2764 of the Civil Code must be paid for by defendant. See White v. City of New Orleans, 15 La. Ann. 667.

The contract provides that the work should be completed by a certain date, and that in case of delay in the completion of it within the time specified “the contractor agrees to pay as liquidated damages the sum of twenty five dollars ($25.00) per day for each' day of such delay, which liquidated damages shall become due by the mere elapsing .of the delay without the necessity of putting the contractor in default.” Section 189, specifications.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McElroy v. Dynasty Transp. Inc.
907 So. 2d 69 (Louisiana Court of Appeal, 2005)
Davis v. Tillman
370 So. 2d 1323 (Louisiana Court of Appeal, 1979)
Admiral Paint Company v. Goltzman
254 So. 2d 104 (Louisiana Court of Appeal, 1972)
Katz v. Judice
252 So. 2d 532 (Louisiana Court of Appeal, 1971)
Popich v. Fidelity & Deposit Co. of Maryland
231 So. 2d 604 (Louisiana Court of Appeal, 1970)
Harper v. Home Indemnity Company
140 So. 2d 653 (Louisiana Court of Appeal, 1962)
Hughes v. Breazeale
121 So. 2d 510 (Supreme Court of Louisiana, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
139 So. 638, 173 La. 1105, 1932 La. LEXIS 1603, Counsel Stack Legal Research, https://law.counselstack.com/opinion/farnsworth-v-sewerage-water-board-of-new-orleans-la-1932.