Kansas Milling Co. v. Edwards

197 P. 1113, 108 Kan. 616, 1921 Kan. LEXIS 236
CourtSupreme Court of Kansas
DecidedMarch 12, 1921
DocketNo. 22,849
StatusPublished
Cited by7 cases

This text of 197 P. 1113 (Kansas Milling Co. v. Edwards) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kansas Milling Co. v. Edwards, 197 P. 1113, 108 Kan. 616, 1921 Kan. LEXIS 236 (kan 1921).

Opinion

The opinion of the.court was delivered by

Mason, J.:

The Kansas Milling Company sued John A. Edwards for his failure to carry out a contract of July 15, 1914, for the delivery to it in that month of 5,000 bushels of wheat at 64 cents. Judgment was rendered for the plaintiff and the defendant appeals.

[617]*6171. The entering into the contract and the nondelivery of the wheat were admitted. The defendant denied liability on the ground that in the latter part of the month named it was agreed between the parties that the order should be filled from wheat then in the stack, grown upon certain land owned by him; that the contract thereby became one for the sale of that particular wheat, and that through no fault of his this wheat was destroyed by fire before the time for delivery arrived. The court gave no instructions regarding the legal effect upon the rights of the parties where the performance of a contract becomes impossible, and submitted no question to the jury in that connection. Its failure to do so is the principal basis of the defendant’s appeal. On this subject the defendant introduced evidence tending to prove these facts:

On July 23,, 1914, he wrote the plaintiff that he would be •unable to fill the order from the source he had intended, and five days later he asked an extension' through August and over September. The plaintiff replied that it was compelled to ask delivery by August 10. On August 5, 6 or 7 he talked with the agent of the company and told him he could fill the contract. The agent said not to ship the wheat; that the company could not .take it; that there was an embargo on, war was about to break out, there was financial havoc in Wichita, wheat had dropped and there was no market for it, and the plaintiff was now willing to extend the contract through August or even sixty days. The defendant then said that he had 5,000 bushels ready for delivery and could not hold it as he had no granary and would have to deliver it or dispose of it; that he had some unthreshed wheat on his Snake Creek ranch which he could deliver when it was threshed. The agent said the company would take 5,000 bushels of that wheat — to let it stay in the stack— that it could not take it then, and that the wheat market was way down and payment of wheat drafts was being refused. The defendant agreed to keep 5,000 bushels of the Snake Creek ranch wheat in stack for the plaintiff — keep it and .thresh it when it was wanted, provided it would not cost him anything to do it — provided the plaintiff would take care of it and look after him. The agent agreed to this proposal, saying that the company would make good whatever extra expense or trouble to the defendant was thereby occasioned. It was by reason of [618]*618this arrangement that the defendant did not make delivery before August 10 of the 5,000 bushels contracted for. The fire referred to took place in late August or early September, some 14.000 or 15,000 bushels being destroyed.

It is a familiar rule that performance of a contract for the sale of a particular article — as for instance the crop from a specified tract — is excused by the accidental destruction thereof. (35 Cyc. 246; 6 R. C. L. 1005; 23 R. C. L. 1431; Note, L. R. A. 1916F 10, 20.) The contract here sued upon was not of that character at its inception, nor is it clear that it became such by subsequent agreement of the parties, assuming that the defendant’s version of the later negotiations is correct. Upon that assumption the plaintiff was not seeking to buy 5.000 bushels of the wheat from the Snake Creek ranch; the defendant might have filled the order with any wheat he was able to procure. The arrangement was entered into to meet the practical difficulties of the situation. The defendant was ready to make immediate delivery of other wheat, but the plaintiff was not able then to receive it. The defendant could not store or otherwise hold the wheat he was then ready to deliver', but could hold the wheat he had in stack and fill the order from this after it was threshed. So for the accommodation of the plaintiff it was agreed that there should be a delay in the shipment, and as this could only be accomplished by the use of the unthreshed wheat, that should be held for the purpose, the plaintiff indemnifying the defendant against any resulting expense or trouble. Whether or not these circumstances would bring the case within the rule relating to contracts for the sale of specific articles, there is room for a plausible contention that the defendant ought not to be held liable for the nondelivery of this wheat as the result of an accidental fire, because delivery would have been made from other wheat if the plaintiff had been ready to accept it.

The necessity of determining the_ rights of the parties under these conditions is in our judgment dispensed with by the action of the jury. The whole defense is based upon the theory of a delay in delivery having been arranged for the benefit of the plaintiff. At the request of the defendant this question among others was submitted to the jury, a negative answer being returned: “Did plaintiff at any time advise defendant to [619]*619hold back and not make shipment of any of the wheat under the 5,000-bushel contract of July 15, 1914?” The answer to this explicit question could not have been affected by the omission of the court to give an instruction relating to the effect of the fire, and it necessarily negatives the claim of the defendant, by deciding that no delay in shipment was made for the accommodation of the plaintiff. The defense rests directly upon the theory that the defendant was ready and willing to deliver and because of the inability of the plaintiff to accept delivery a delay was arranged for its accommodation by the agreement to fill the order from the unthreshed wheat. Only on the hypothesis of the plaintiff having requested a delay could it be reasonably contended .that the contract became one for the sale of a specific article — wheat from a particular tract. The finding of the jury was therefore fatal to the establishment of the defense relied upon.

The jury were instructed that the plaintiff could not recover if it had released the defendant from furnishing the wheat at any time when the defendant was ready, willing and able to comply with the terms of the contract. The evidence in behalf of the defendant was that early in August he had notified the plaintiff that he was ready to fill the contract — to ship the wheat — and had been told not to do so because the plaintiff could not take it. Such a transaction would have amounted for the time being to a release of the defendant from his obligation and the general verdict necessarily implied a finding that it had not taken place.

2. The judgment was based upon the market price of wheat on October 1, 1914. The defendant complains of this on the ground that at later dates the plaintiff wrote him letters asking a settlement, which used language indicating an assumption of the deal still being open; that a finding of the plaintiff’s having bought in the wheat on that day was’ not warranted ; and that the evidence of the market price of wheat on October 1 did not apply specifically to the place of shipment— Englewood. There was evidence in substance that on October 1 the plaintiff bought 5,000 more bushels of wheat than it would otherwise have done because of the nonreceipt of that amount on this contract; that some time after that the defendant asked that the market price on that day, which was [620]*62092.3, be used in settling this deal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Clark v. Wallace County Cooperative Equity Exchange
986 P.2d 391 (Court of Appeals of Kansas, 1999)
City of Ottawa v. Heathman
690 P.2d 1375 (Supreme Court of Kansas, 1984)
Gannaway v. Missouri-Kansas-Texas Rld. Co.
575 P.2d 566 (Court of Appeals of Kansas, 1978)
Smith v. Union Pacific Railroad Co.
519 P.2d 1101 (Supreme Court of Kansas, 1974)
Wheeler v. Barr
4 P.2d 441 (Supreme Court of Kansas, 1931)
Ewing v. Union Pacific Railroad
231 P. 334 (Supreme Court of Kansas, 1924)
Kansas Milling Co. v. Edwards
197 P. 1115 (Supreme Court of Kansas, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
197 P. 1113, 108 Kan. 616, 1921 Kan. LEXIS 236, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kansas-milling-co-v-edwards-kan-1921.