Kansas Gas and Electric Co. v. State Corporation Commission

794 P.2d 1165, 14 Kan. App. 2d 527, 1990 Kan. App. LEXIS 458
CourtCourt of Appeals of Kansas
DecidedJune 29, 1990
Docket64,975, 65,042
StatusPublished
Cited by11 cases

This text of 794 P.2d 1165 (Kansas Gas and Electric Co. v. State Corporation Commission) is published on Counsel Stack Legal Research, covering Court of Appeals of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kansas Gas and Electric Co. v. State Corporation Commission, 794 P.2d 1165, 14 Kan. App. 2d 527, 1990 Kan. App. LEXIS 458 (kanctapp 1990).

Opinion

Brazil, J.:

Kansas Gas and Electric Company (KG&E) and Beech Aircraft Corporation, The Coleman Company, Total Petroleum, Inc., LaFarge Corporation, and Texaco, Inc., (the industrial intervenors) appeal the Kansas Corporation Commission’s (KCC) decision finding fuel costs were imprudently incurred during outages at the Wolf Creek Generating Station (Wolf Creek) and ordering a $6.9 million refund with interest to KG&E’s customers. We affirm in part, reverse in part, and remand.

In September 1987, Wolf Creek embarked on a refueling outage scheduled to last 49 days. The refueling outage actually lasted 101 days and a subsequent, unscheduled outage on January 21, 1988, lasted another 26 days. As part of a general investigation into excess energy costs incurred during the 1987-88 extended outages at Wolf Creek, the KCC, on its own motion, ordered KG&E to show cause by an order dated December 30, 1988, why KG&E should be allowed to retain $6,415,582 of excess costs charged to Kansas ratepayers during the unscheduled outage periods. The industrial customers subject to KG&E’s Retail Energy Cost Adjustment Clause intervened in the action. The Citizens’ Utility Ratepayers Board (CURB), representing residential and small commercial customers, also intervened.

After a hearing, the KCC issued an order finding imprudence and mismanagement during the 1987-88 outages in question. The KCC further adopted the KCC staff s calculation of refund rather than relying on KG&E’s Retail Energy Cost Adjustment Clause (ECA clause) to determine the refund. In so doing, the KCC found a 49-day outage schedule to have been prudent and the balance of the outage to have been avoidable, and ordered KG&E to refund $6,923,457 in three equal lump sums, payable annually. (The $6,415,582 refund proposed in the show cause order as *529 sumed a 56-day outage schedule.) The refund included 9.8836 percent interest from the time the overcharges were incurred until the time each refund is made. Chairman Henley dissented from the decision.

Both KG&E and the industrial intervenors timely applied for judicial review, and those applications were consolidated for argument and decision by this court.

We are first confronted with the question of this court’s jurisdiction to hear the appeal. K.S.A. 1989 Supp. 66-118a(b) provides in relevant part: “The court of appeals shall have exclusive jurisdiction to review any agency action of the state corporation commission arising from a rate hearing requested by a public utility or requested by the state corporation commission when a public utility is a necessary party.” KG&E is clearly a public utility as defined in K.S.A. 66-104; i.e., it is a company “for the production, transmission, delivery or furnishing of heat, light, water or power. ” The jurisdictional question here is whether the agency action arises from a rate hearing.

KG&E’s position is that the ECA clause is a rate because it involves the pricing of a product to customers. In re Application of Southwestern Bell Tel. Co., 9 Kan. App. 2d 525, 685 P.2d 304, rev. denied 236 Kan. 875 (1984). The KCC’s position, as announced in its order, is that the ECA clause is a tariff and not a rate and that the hearing appealed from was not a rate hearing.

Two recent Court of Appeals decisions have addressed this jurisdictional issue. In re Application of Southwestern Bell Tel. Co., 9 Kan. App. 2d 525, involved approval of tariffs which had been severed from the underlying rate case because of the need to expedite the rate case. Jurisdiction was found to lie with the Court of Appeals based on two factors: “(1) the close relationship between this case and the prior rate case; and (2) the similarity of the involved tariff to a rate schedule.” 9 Kan. App. 2d at 529.

The court added a cautionary note, however:

“The conclusion that this court has jurisdiction in this case does not mean that all cases involving tariffs are directly appealable to this court under K.S.A. 66-118a. For example, questions of tariff interpretation should be appealed to the district court. Southwestern Bell Tel. Co. v. Kansas Corporation Commission, 233 Kan. 375 [, 664 P.2d 798 (1983)]. If the tariff is closely related to a prior rate case or if it is similar to a rate schedule, *530 jurisdiction will more likely be with this court than with the district court.” 9 Kan. App. 2d at 531.

MAPCO Intrastate Pipeline Co. v. Kansas Corporation Comm'n, 10 Kan. App. 2d 527, 704 P.2d 989 (1985), turned on application of the second Southwestern Bell factor. 10 Kan. App. 2d at 530-31. The court found the amended tariff which was the subject of appeal “dealt only with new rates” and “[t]he Commission s hearing on the tariff likewise dealt only with rates and revenues.” 10 Kan. App. 2d at 531. The court concluded this was a rate hearing, and the resulting order was one “ ‘arising from a rate hearing.’ ” 10 Kan. App. 2d at 531.

In this case the KCC issued an order to KG&E to show cause why it should be allowed to retain in excess of six million dollars of excess costs charged to Kansas ratepayers during unscheduled outage periods associated with the second refueling of the Wolf Creek Generating Station. As part of the original Wolf Creek rate hearings, the KCC approved an ECA clause as part of KG&E’s tariffs. The clause, as explained by KG&E’s Supervisor of Regulatory Accounting, is a “rate setting mechanism whereby customers are charged, as a separate component on their bills, for the estimated costs of fuel and purchased power required to meet anticipated energy consumption on KG&E’s system during each calendar month.” In calculating the proposed refund for purposes of the show cause order, the KCC staff employed an alternative fuel mix ratio, a decision challenged by KG&E, which contended before the KCC and now on appeal that a refund, if ordered, should be calculated under the ECA clause approved as part of the Wolf Creek rate hearings. KG&E argues the rejection of the ECA clause and the application of a different cost adjustment formula resulted in retroactive ratemaking in the instant case.

We find that, based on either Southwestern Bell factor, the close relationship between this case and the prior rate case, or the similarity of the involved tariff to a rate schedule, jurisdiction properly lies with this court because the show cause order in this case is inextricably bound to the tariffs established in the prior rate case and the issues involved are not simply ones of tariff interpretation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bluestem Telephone Co. v. Kansas Corp. Commission
316 P.3d 162 (Court of Appeals of Kansas, 2013)
Kansas Industrial Consumers Group, Inc. v. State Corp. Commission
138 P.3d 338 (Court of Appeals of Kansas, 2006)
Columbus Telephone Co. v. Kansas Corporation Comm'n
75 P.3d 257 (Court of Appeals of Kansas, 2003)
Matanuska Electric Ass'n v. Chugach Electric Ass'n
53 P.3d 578 (Alaska Supreme Court, 2002)
Western Resources, Inc. v. Kansas Corporation Comm'n
42 P.3d 162 (Court of Appeals of Kansas, 2002)
Farmland Industries, Inc. v. Kansas Corporation Comm'n
37 P.3d 640 (Court of Appeals of Kansas, 2001)
United Cities Gas Co. v. Brock Exploration Co.
995 F. Supp. 1284 (D. Kansas, 1998)
Citizens' Utility Ratepayer Board v. State Corp. Commission
941 P.2d 424 (Court of Appeals of Kansas, 1997)
CITIZENS'UTILITY RATEPAYER BD. v. Kansas Corporation Comm'n
941 P.2d 424 (Court of Appeals of Kansas, 1997)
Kansas Pipeline Partnership v. Kansas Corporation Comm'n
941 P.2d 390 (Court of Appeals of Kansas, 1997)
Grindsted Products, Inc. v. Kansas City Power & Light Co.
901 P.2d 20 (Court of Appeals of Kansas, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
794 P.2d 1165, 14 Kan. App. 2d 527, 1990 Kan. App. LEXIS 458, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kansas-gas-and-electric-co-v-state-corporation-commission-kanctapp-1990.