Kansas City Structural Steel Co. v. L. G. Barcus & Sons, Inc.

535 P.2d 419, 217 Kan. 88, 16 U.C.C. Rep. Serv. (West) 1280, 1975 Kan. LEXIS 408
CourtSupreme Court of Kansas
DecidedMay 10, 1975
Docket47,609
StatusPublished
Cited by35 cases

This text of 535 P.2d 419 (Kansas City Structural Steel Co. v. L. G. Barcus & Sons, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kansas City Structural Steel Co. v. L. G. Barcus & Sons, Inc., 535 P.2d 419, 217 Kan. 88, 16 U.C.C. Rep. Serv. (West) 1280, 1975 Kan. LEXIS 408 (kan 1975).

Opinion

The opinion of the court was delivered by

Fontron, J.:

This lawsuit started out as an action by the plaintiff, Kansas City Structural Steel Company, to collect the balance due on account from the defendant, L. G. Barcus & Sons, Inc. It *89 ended up being tried on a counterclaim filed by defendant against the steel company for breach of contract. The trial court entered judgment against the steel company on the Barcus counterclaim in the amount of $173,285. The steel company has appealed from that judgment.

Kansas City Structural Steel Company is a corporation engaged in manufacturing, supplying and erecting heavy structural steel. L. G. Barcus & Sons, Inc. is a general contractor engaged in the design and construction of roads, bridges and appurtenances thereto. The home offices of both companies are located in Kansas City, Kansas. For convenience the companies will hereafter be referred to as K. C. Steel, steel company, or plaintiff on the one hand, and Barcus or defendant on the other. The defendant, Travelers Indemnity Company, which is not involved in this appeal, was the bonding company for Barcus.

In September, 1968, the State of Kansas awarded Barcus a contract to widen the existing bridge on Seventh Street in Kansas City, Kansas, and to build two new ramps at the southern end of the bridge. This was known locally as the 7th Street project. The contract called for completion of the job within 250 working days and provided for payment of $280 per day liquidated damages in the event the project was not completed within that time.

Prior to being awarded the contract, Barcus had discussed structural steel prices with the plaintiff and had received verbal quotations. On September 24, 1968, K. C. Steel submitted a written proposal to Barcus confirming the prices orally quoted. A purchase order for structural steel was executed by Barcus and submitted to the steel company November 5, 1968. The order is shown to have been accepted by K. C. Steel through the signature of Robert H. Dill, its vice-president of sales.

At the commencement of the trial the court, on stipulation of counsel for both parties, entered judgment in favor of plaintiff on its account against defendant in the amount of $144,781.35, and the case proceeded to trial by the court on defendant’s counterclaim. We are advised that the plaintiff’s judgment against the defendant has since been paid. Hence, Travelers Indemnity Company has made no appearance in this court.

Defendant’s counterclaim is predicated on the plaintiff’s alleged failure to deliver structural steel according to the shipping schedule included in the purchase order. That portion of the purchase order reads:

*90 “In that time is of the essence in the prosecution of this contract, it is agreed that the shipping schedule will be as follows:
“Starting approximately June 15, 1969 with completion approximately August 15, 1969.”

According to the record, the project was substantially completed, so far as carrying traffic was concerned, in December 1970, although some handrailings appear to have been installed sometime the following April. It is not open to question that there was some delay in delivery, and the record reflects a good deal of argument pro and con as to what caused the delay and K. C. Steel’s responsibility therefor. No one disputes that a strike of ironworkers occurred in the Kansas City area about April 1, 1969, and lasted until the middle part of July; that it closed down the unionized ready-mix concrete plants in the area, including the plant from which Barcus obtained its concrete to build the piers and abutments; that Barcus ceased pouring concrete shortly after April 1, and the steel company, when its president became aware of the stoppage, cut back its production of structural steel for the 7th Street job. There was crimination and recrimination between the steel company and Barcus as to why Barcus stopped pouring the piers; why the cutback was ordered; why Barcus was not notified of the cutback until early May and what effect it had on the progress of the work. All in all it would appear there was at least some lack of communication between the two companies. Be that as it may, delivery of structural steel was begun not later than early September, 1969, K. C. Steel having been told in the meantime that delivery would be wanted six weeks after the strike ended. Deliveries appear to have continued regularly during the remainder of the work. The record reflects there were other causes contributing to work delays, including changes made by the state in the plans and specifications for the project. Disputes also arose between the contracting parties at the trial as to whether the defendant was ready to take the steel when it was available for delivery.

We believe it would prove fruitless, however, to dwell further on the numerous points of conflict existing between the parties during this litigation. The work was finally finished in 232 working days as computed by the state — this being well within the time allotted for completion. As a consequence, the state assessed no penalties against Barcus.

During the latter part of 1970 the defendant got behind in pay- *91 merits due plaintiff, despite numerous attempts on plaintiff’s part to effect collection. Eventually, on May 6, 1971, the steel company billed Barcus for the entire balance due in the amount of $132,489.65 (later established by stipulation as $144,781.35). Ten days later, and for the first time Barcus had mentioned the subject, K. C. Steel was billed for $173,285 in damages claimed to be due for added expense incurred by Barcus caused, so it was said, by plaintiff’s delay in delivering structural steel.

The plaintiff has asserted a number of defenses in opposition to defendant’s counterclaim and has raised several points on appeal. However, throughout the entire course of litigation, the steel company’s primary reliance appears to be placed on the exculpatory clause contained in the Barcus purchase order. It reads as follows:

“All of the terms and conditions of the plans and specifications and contract documents between the Owner and the Purchaser which are applicable to the materials to be furnished under this Purchase Order shall become a part of this purchase, as if written herein; provided, however, Kansas City Structural Steel Company shall not be responsible for any damages for any delay in its performance unless such delay is not excusable thereunder or is not of the type for which an extension of time may be granted thereunder and unless such delay is the sole cause of delay to the Purchaser for which the Purchaser is assessed and pays damages thereunder.”

K. C. Steel’s argument amounts to this: Inasmuch as the project was completed within the number of working days contemplated by the state as set out in the prime contract, and since the state has assessed no damages against Barcus for any delays, the proviso in the foregoing clause precludes Barcus from claiming damages from K. C. Steel. The validity of this contention depends on the proper construction of the exculpatory clause.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

M.F. v. ADT, Inc.
357 F. Supp. 3d 1116 (D. Kansas, 2018)
Utley v. Mill Man Steel, Inc.
2015 UT 75 (Utah Supreme Court, 2015)
Daggett v. Board of Public Utilities
263 P.3d 847 (Court of Appeals of Kansas, 2011)
Law Co., Inc. v. Mohawk Const. & Supply Co.
702 F. Supp. 2d 1304 (D. Kansas, 2010)
Law Co. v. Mohawk Construction & Supply Co.
523 F. Supp. 2d 1276 (D. Kansas, 2007)
Neustrom v. Union Pacific
Tenth Circuit, 1998
Champlain Enterprises, Inc. v. United States
957 F. Supp. 26 (N.D. New York, 1997)
Dixon v. Certainteed Corp.
944 F. Supp. 1501 (D. Kansas, 1996)
Beeson v. Erickson
917 P.2d 901 (Court of Appeals of Kansas, 1996)
Estate of Bryant Ex Rel. Bryant v. All Temperature Insulation, Inc.
916 P.2d 1294 (Court of Appeals of Kansas, 1996)
Olathe Manufacturing, Inc. v. Browning Manufacturing
915 P.2d 86 (Supreme Court of Kansas, 1996)
Butler Manufacturing Co. v. Americold Corp.
841 F. Supp. 1107 (D. Kansas, 1993)
Myrtle Beach Pipeline Corp. v. Emerson Electric Co.
843 F. Supp. 1027 (D. South Carolina, 1993)
Simpson v. Dixon
1993 OK 71 (Supreme Court of Oklahoma, 1993)
Elite Professionals, Inc. v. Carrier Corp.
827 P.2d 1195 (Court of Appeals of Kansas, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
535 P.2d 419, 217 Kan. 88, 16 U.C.C. Rep. Serv. (West) 1280, 1975 Kan. LEXIS 408, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kansas-city-structural-steel-co-v-l-g-barcus-sons-inc-kan-1975.