Kansas City Southern Railway Co. v. Barge HBC 8106

642 F. Supp. 609, 1986 U.S. Dist. LEXIS 22262
CourtDistrict Court, W.D. Louisiana
DecidedJuly 25, 1986
DocketCiv. A. 83-0026
StatusPublished
Cited by3 cases

This text of 642 F. Supp. 609 (Kansas City Southern Railway Co. v. Barge HBC 8106) is published on Counsel Stack Legal Research, covering District Court, W.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kansas City Southern Railway Co. v. Barge HBC 8106, 642 F. Supp. 609, 1986 U.S. Dist. LEXIS 22262 (W.D. La. 1986).

Opinion

OPINION

VERON, District Judge.

This matter was heard by the Court without a jury on April 29, 1986. The Court having heard the evidence, examined the exhibits, pleadings, stipulations, and post-trial memoranda submitted by the parties, now makes the following Findings of Fact and Conclusions of Law as to the damages sustained by plaintiff as a result of the allision of the four defendant barges with the Kansas City Southern Railway’s Calcasieu River Bridge on December 29, 1982.

I. FINDINGS OF FACT

1. The Court expressly adopts and incorporates by reference those Stipulations of Fact entered into by the parties and filed with the Court on April 28, 1986. See Appendix.

2. Following the visit of Louisiana Limestone Aggregate’s personnel to the Westlake facility late in the evening of December 26, 1982, no agent nor employee of any of the defendants did anything to *611 monitor the weather for changing forecasts, to monitor or check the moorings of the four barges, or to move the barges to a safer mooring location.

3. Other mooring locations were available and the M/V TRIPLE R was capable of moving the barges to safer moorings.

4. Despite the weather and flood forecasts, defendants chose to leave their barges secured by moorings which were adequate for only normal conditions.

5. As a result of the flooding waters and inadequate moorings, the four defendant barges broke from the three steel cables which had kept them moored to a willow tree, a cypress stump, and a hardwood tree on the East side of the Calcasieu River across from the Louisiana Limestone Aggregate facility. See Appendix, ¶¶ 11-12.

6. Drifting downriver, the four barges came to strike the KCS Bridge, destroying and/or damaging its 225 foot swing span, its 175 foot East truss span and its supporting piers, and nine 14 foot timber trestle spans. See Appendix, 1110.

7. The Court finds that the fair and reasonable current-day reconstruction costs for the damaged portions of the bridge, according to the 1890’s bridge design, is in the amount of $2,397,155.00.

8. While the Court is aware that certain contingencies must be allowed for the unexpected in any large project, such as that which would be involved in reconstructing the damaged KCS bridge, plaintiff offered no evidence whatsoever to support its claim for “contingencies” in an amount equal to ten percent (10%) of the estimated cost of bridge reconstruction. Absent any such evidence, the Court finds five percent (5%) of the current-day reconstruction cost to be a more reasonable amount and further finds that the fair and reasonable amount for contingencies is $119,858.00.

9. The condition of the Kansas City Southern Railway bridge prior to the allision with the four barges was such that various portions of it were severely deteriorated. These deteriorated portions included the diaphragms between the caissons (see Defendants’ Exhibit No. 3), portions of the pier work, and the drive machinery. The Kansas City Southern Railway Bridge was an old structure which had minimum upkeep and maintenance performed upon it and which was, at the time of the allision, being used primarily as a switching track. See Appendix, 1124.

10. In accordance with the condition of the bridge on December 29, 1982, as appears from the numerous photographic exhibits received in evidence and the testimony of expert witnesses on behalf of both plaintiff and defendants, the Sverdrup & Parcels current-day estimate of reconstruction costs should be depreciated to reflect the pre-allision value of those portions of the bridge damaged and/or destroyed in the allision, which the Court finds to be $1,610,888.00.

11. The evidence offered by the plaintiff is entirely insufficient for the Court to make any determination as to the present-day value of those bridge portions which remained intact and undamaged after the allision. The Sverdrup & Parcels Engineering Cost Estimate set forth only reconstruction costs “for replacement of the damaged portion of the structure.”

12. Moreover, plaintiff claims that it is owed the cost of engineering and construction management in an amount equal to twelve percent (12%) of the estimated cost of bridge reconstruction. The SverdrupParcels Engineering Cost Estimate, however, included no such amount, and the evidence is utterly insufficient to support such an award. The Court finds that any award for purported costs of engineering and management of construction would result in double recovery of damages by plaintiff, and thus rejects this claim.

13. Within one month of the allision, the Kansas City Southern Railway Company made the decision to not repair nor reconstruct any part of the bridge and instead chose to remove the entirety of the remaining bridge structure down to the present mud line. See Plaintiff’s Exhibit No. 3. This decision was apparently supported by the minimal use being made of the bridge by Kansas City Southern Railway Company. See Appendix, 111124-26. Nevertheless, the damage itself rendered the bridge *612 “incapable of repair within the bounds of good business judgment.” Appendix, ¶ 18.

14. Because the U.S. Coast Guard required the damaged bridge to be removed, Appendix, II19, removal costs were necessarily incurred. The Court finds that $607,136.00 in costs was reasonably incurred by plaintiff in having the damaged bridge removed. Appendix, 1120.

II. CONCLUSIONS OF LAW

1. Jurisdiction is vested in this Court pursuant to 28 U.S.C. § 1333 as the complaint states an admiralty and maritime claim within the meaning of Rule 9(h) of the Federal Rules of Civil Procedure.

2. Insofar as the Findings of Fact determined by the Court also constitute legal conclusions, they are incorporated herein.

3. The law is well-established that when a drifting vessel causes damage, an inference arises as a matter of law that the vessel was adrift through negligence. This presumption of negligence is based upon the logical deduction that a vessel found floating loose was improperly moored. James v. River Parishes Co., Inc., 686 F.2d 1129, 1132-33 (5th Cir.1982). The defendants in the case at bar therefore bore the burden of disproving fault by a preponderance of the evidence, and they failed to carry this burden.

4. Nevertheless, the defendants have offered the defense that the allision was an unavoidable accident, or vis major, which human skill and precaution could not have prevented. Defendants have failed to carry their heavy burden of persuasion in establishing this defense, however, because they utterly failed to show that the accident in no way resulted from their own lack of due care. See Petition of M/V ELAINE JONES, 480 F.2d 11, 18 (5th Cir.1973).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bill Burns Martin v. D & S Marine Service, LLC
Louisiana Court of Appeal, 2012
Yarmouth Sea Products Ltd. v. Scully
131 F.3d 389 (Fourth Circuit, 1997)
Yarmouth Sea Products Limited v. David Scully
131 F.3d 389 (Fourth Circuit, 1997)
Tug "Sea Hawk" v. Sococo, Ltd.
707 F. Supp. 1306 (S.D. Florida, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
642 F. Supp. 609, 1986 U.S. Dist. LEXIS 22262, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kansas-city-southern-railway-co-v-barge-hbc-8106-lawd-1986.