NOT DESIGNATED FOR PUBLICATION
STATE OF LOUISIANA COURT OF APPEAL, THIRD CIRCUIT
11-1489
BILL BURNS MARTIN
VERSUS
D & S MARINE SERVICE, L.L.C.
**********
APPEAL FROM THE THIRTY-EIGHTH JUDICIAL DISTRICT COURT PARISH OF CAMERON, NO. 10-18356 HONORABLE PENELOPE QUINN RICHARD, DISTRICT JUDGE
ELIZABETH A. PICKETT JUDGE
Court composed of John D. Saunders, Elizabeth A. Pickett, and Billy Howard Ezell, Judges.
Saunders, J., dissents and assigns written reasons.
AFFIRMED.
John R. Pohorelsky Peter J. Pohorelsky Scofield, Gerard, Singletary, & Pohorelsky Post Office Drawer 3028 Lake Charles, Louisiana 70602 (337) 433-9436 Counsel for Plaintiff/Appellant: Bill Burns Martin Jefferson R. Tillery Jean-Paul A. Escudier Jones, Walker, Waechter, Poitevent Carrère & Denègre, L.L.P. 201 St. Charles Avenue – 48th Floor New Orleans, Louisiana 70170-5100 (504) 582-8616 Counsel for Defendant/Appellee: D&S Marine Service, L.L.C. PICKETT, Judge.
Plaintiff appeals trial court’s award for damages caused to his dock and large
steel mooring dolphin which resulted when they were struck by a tugboat and two
barges owned and/or operated by defendant. For the following reasons, we affirm.
FACTS
On February 11, 2008, the M/V ANNA MICHAEL, a push tug owned and
operated by D&S Marine Service, L.L.C. (D&S), was pushing two barges owned by
Kirby Inland Marine (Kirby), when it allided with a dock and steel mooring dolphin
situated on the Gulf Intracoastal Waterway in Grand Lake that is owned by Bill
Burns Martin. Mr. Martin sued D&S to recover the cost of repairs to his dock and
dolphin necessitated by the allision.
The morning of trial, D&S stipulated to liability, and the only issue presented
for resolution was damages. Mr. Martin testified and presented the testimony of
Captain Anthony Brown, a marine surveyor. D&S presented the deposition
testimony of marine surveyor, Harry Stark, and the live testimony of Jeffrey
Boudreaux, of B&J, Inc. (B&J), a marine construction company that submitted a bid
to repair the damaged dock and dolphin. After taking the matter under advisement,
the trial court awarded Mr. Martin $30,478.42. Mr. Martin appealed.
ASSIGNMENTS OF ERROR
Mr. Martin assigns four errors with the trial court’s judgment:
(1) The trial court erred when it relied upon two incomplete and inaccurate bids for repair in calculating damages;
(2) The trial court erred when it reduced damages by use of a linear depreciation factor;
(3) The trial court erred in not awarding damages for the cost of removing steel pilings of a mooring dolphin; and (4) The trial court erred in awarding damages in the amount of $30,478.42 when the evidence and law mandate an award in excess of $200,000.00.
DISCUSSION
Did the trial court err in including incomplete and inaccurate bids for repair in calculating damages?
Mr. Martin solicited and received three bids for repairing the dock and
dolphin. The trial court determined there were problems or issues with each of the
three bids and averaged the bids to determine the cost to repair the dock and dolphin.
The evidence established that the bid presented by B&J was incomplete and that the
bid presented by Bass Builders, L.L.C. (Bass) was also incomplete because Bass did
not have the equipment required to perform the repairs and intended to contract the
work to B&J, resulting in Bass’s bid actually being B&J’s bid with a markup.
Mr. Stark testified the third bid presented by F. Miller Construction LLC (F. Miller)
was ―too high‖ and was ―not comparable‖ to the other bids submitted. He
explained that F. Miller’s primary business was constructing and repairing large
commercial docks and opined that its bid was high because it was not interested in
performing small jobs like Mr. Martin’s. Mr. Boudreaux also opined that
F. Miller’s bid was high and that the repairs could be performed for less than the
amount quoted in its bid.
Mr. Martin argues the trial court erred in considering B&J’s and Bass’s bids
because they were incomplete and inaccurate. D&S acknowledges that
Mr. Boudreaux admitted B&J’s bid was incomplete because it did not include all the
work to be performed. It argues, however, this error did not render the bids of B&J
and Bass invalid because Mr. Boudreaux also testified that B&J would honor its bid
and perform all the required work for $61,380.00, the amount it bid, to protect its
reputation.
2 In cases such as this, maritime law, not state law, applies because the cause of
action arose under maritime law. Freeport Sulphur Co. v. S/S Hermosa, 526 F.2d
300 (5th Cir. 1976). Nevertheless, property damage principles are the same under
federal maritime law and Louisiana law: the goal is to restore the victim to the
position he was in before his property was damaged. Id.; see also Massie v.
Deloach, 04-1425 (La.App. 3 Cir. 3/2/05), 896 So.2d 1246, writ denied, 05-786 (La.
5/6/05), 901 So.2d 1107. Additionally, a defendant can only be held liable for
damages that he has been proved to have caused. Freeport, 526 F.2d 300.
Furthermore, under maritime law, a defendant cannot be held liable for repairs that
enhance or extend the useful service life of the damaged property. Id. If repairs
are not made, damages are measured by the estimated cost of repair at the time the
damage occurred. United States v. Shipowners & Merchants Tugboat Co., 103
F.Supp. 152 (N.D.Cal. 1952), aff’d, 205 F.2d 352 (9th Cir 1953), cert. denied, 346
U.S. 829, 74 S.Ct. 51 (1953); see also Kan. City S. Ry. Co. v. Barge HBC 8106, 642
F.Supp. 609 (W.D.La. 1986). Lastly, a trial court’s award of special damages is a
finding of fact that cannot be reversed unless there is no reasonable basis for the
award and it is clearly wrong. Menard v. Lafayette Ins. Co., 09-1869 (La. 3/16/10),
31 So.3d 996. Repair costs are special damages. Eddy v. Litton, 586 So.2d 670
(La.App. 2 Cir. 1991), writ denied, 590 So.2d 1203 (La.1992); see also Bernard v.
City of Lafayette, 98-1815 (La.App. 3 Cir. 5/5/99), 735 So.2d 804.
As the trier of fact, the trial court determined the credibility of the witnesses
and had the prerogative of accepting or rejecting some or all of the witnesses’
testimony; this included expert witness testimony. Ryan v. Zurich Amer. Ins. Co.,
07-2312 (La. 7/1/08), 988 So.2d 214. The trial court’s findings of fact, credibility
evaluations, and inferences of fact should not be disturbed on appeal if they are
reasonable. Sistler v. Liberty Mut. Ins. Co., 558 So.2d 1106 (La.1990).
3 Mr. Martin strongly argues that F. Miller’s bid is the only valid bid because it
includes all the repair work to be performed and Mr. Stark testified it would
construct a beautiful dock; therefore, it is the only bid the trial court should have
considered. This argument fails to acknowledge that not only did Mr. Boudreaux
testify B&J would have performed the work for the amount it originally quoted in its
bid, but Mr. Stark testified that F. Miller’s bid was high and not competitive,
explaining that F. Miller primarily performs commercial work and, more likely than
not, submitted the bid as a professional courtesy. Additionally, Mr.
Free access — add to your briefcase to read the full text and ask questions with AI
NOT DESIGNATED FOR PUBLICATION
STATE OF LOUISIANA COURT OF APPEAL, THIRD CIRCUIT
11-1489
BILL BURNS MARTIN
VERSUS
D & S MARINE SERVICE, L.L.C.
**********
APPEAL FROM THE THIRTY-EIGHTH JUDICIAL DISTRICT COURT PARISH OF CAMERON, NO. 10-18356 HONORABLE PENELOPE QUINN RICHARD, DISTRICT JUDGE
ELIZABETH A. PICKETT JUDGE
Court composed of John D. Saunders, Elizabeth A. Pickett, and Billy Howard Ezell, Judges.
Saunders, J., dissents and assigns written reasons.
AFFIRMED.
John R. Pohorelsky Peter J. Pohorelsky Scofield, Gerard, Singletary, & Pohorelsky Post Office Drawer 3028 Lake Charles, Louisiana 70602 (337) 433-9436 Counsel for Plaintiff/Appellant: Bill Burns Martin Jefferson R. Tillery Jean-Paul A. Escudier Jones, Walker, Waechter, Poitevent Carrère & Denègre, L.L.P. 201 St. Charles Avenue – 48th Floor New Orleans, Louisiana 70170-5100 (504) 582-8616 Counsel for Defendant/Appellee: D&S Marine Service, L.L.C. PICKETT, Judge.
Plaintiff appeals trial court’s award for damages caused to his dock and large
steel mooring dolphin which resulted when they were struck by a tugboat and two
barges owned and/or operated by defendant. For the following reasons, we affirm.
FACTS
On February 11, 2008, the M/V ANNA MICHAEL, a push tug owned and
operated by D&S Marine Service, L.L.C. (D&S), was pushing two barges owned by
Kirby Inland Marine (Kirby), when it allided with a dock and steel mooring dolphin
situated on the Gulf Intracoastal Waterway in Grand Lake that is owned by Bill
Burns Martin. Mr. Martin sued D&S to recover the cost of repairs to his dock and
dolphin necessitated by the allision.
The morning of trial, D&S stipulated to liability, and the only issue presented
for resolution was damages. Mr. Martin testified and presented the testimony of
Captain Anthony Brown, a marine surveyor. D&S presented the deposition
testimony of marine surveyor, Harry Stark, and the live testimony of Jeffrey
Boudreaux, of B&J, Inc. (B&J), a marine construction company that submitted a bid
to repair the damaged dock and dolphin. After taking the matter under advisement,
the trial court awarded Mr. Martin $30,478.42. Mr. Martin appealed.
ASSIGNMENTS OF ERROR
Mr. Martin assigns four errors with the trial court’s judgment:
(1) The trial court erred when it relied upon two incomplete and inaccurate bids for repair in calculating damages;
(2) The trial court erred when it reduced damages by use of a linear depreciation factor;
(3) The trial court erred in not awarding damages for the cost of removing steel pilings of a mooring dolphin; and (4) The trial court erred in awarding damages in the amount of $30,478.42 when the evidence and law mandate an award in excess of $200,000.00.
DISCUSSION
Did the trial court err in including incomplete and inaccurate bids for repair in calculating damages?
Mr. Martin solicited and received three bids for repairing the dock and
dolphin. The trial court determined there were problems or issues with each of the
three bids and averaged the bids to determine the cost to repair the dock and dolphin.
The evidence established that the bid presented by B&J was incomplete and that the
bid presented by Bass Builders, L.L.C. (Bass) was also incomplete because Bass did
not have the equipment required to perform the repairs and intended to contract the
work to B&J, resulting in Bass’s bid actually being B&J’s bid with a markup.
Mr. Stark testified the third bid presented by F. Miller Construction LLC (F. Miller)
was ―too high‖ and was ―not comparable‖ to the other bids submitted. He
explained that F. Miller’s primary business was constructing and repairing large
commercial docks and opined that its bid was high because it was not interested in
performing small jobs like Mr. Martin’s. Mr. Boudreaux also opined that
F. Miller’s bid was high and that the repairs could be performed for less than the
amount quoted in its bid.
Mr. Martin argues the trial court erred in considering B&J’s and Bass’s bids
because they were incomplete and inaccurate. D&S acknowledges that
Mr. Boudreaux admitted B&J’s bid was incomplete because it did not include all the
work to be performed. It argues, however, this error did not render the bids of B&J
and Bass invalid because Mr. Boudreaux also testified that B&J would honor its bid
and perform all the required work for $61,380.00, the amount it bid, to protect its
reputation.
2 In cases such as this, maritime law, not state law, applies because the cause of
action arose under maritime law. Freeport Sulphur Co. v. S/S Hermosa, 526 F.2d
300 (5th Cir. 1976). Nevertheless, property damage principles are the same under
federal maritime law and Louisiana law: the goal is to restore the victim to the
position he was in before his property was damaged. Id.; see also Massie v.
Deloach, 04-1425 (La.App. 3 Cir. 3/2/05), 896 So.2d 1246, writ denied, 05-786 (La.
5/6/05), 901 So.2d 1107. Additionally, a defendant can only be held liable for
damages that he has been proved to have caused. Freeport, 526 F.2d 300.
Furthermore, under maritime law, a defendant cannot be held liable for repairs that
enhance or extend the useful service life of the damaged property. Id. If repairs
are not made, damages are measured by the estimated cost of repair at the time the
damage occurred. United States v. Shipowners & Merchants Tugboat Co., 103
F.Supp. 152 (N.D.Cal. 1952), aff’d, 205 F.2d 352 (9th Cir 1953), cert. denied, 346
U.S. 829, 74 S.Ct. 51 (1953); see also Kan. City S. Ry. Co. v. Barge HBC 8106, 642
F.Supp. 609 (W.D.La. 1986). Lastly, a trial court’s award of special damages is a
finding of fact that cannot be reversed unless there is no reasonable basis for the
award and it is clearly wrong. Menard v. Lafayette Ins. Co., 09-1869 (La. 3/16/10),
31 So.3d 996. Repair costs are special damages. Eddy v. Litton, 586 So.2d 670
(La.App. 2 Cir. 1991), writ denied, 590 So.2d 1203 (La.1992); see also Bernard v.
City of Lafayette, 98-1815 (La.App. 3 Cir. 5/5/99), 735 So.2d 804.
As the trier of fact, the trial court determined the credibility of the witnesses
and had the prerogative of accepting or rejecting some or all of the witnesses’
testimony; this included expert witness testimony. Ryan v. Zurich Amer. Ins. Co.,
07-2312 (La. 7/1/08), 988 So.2d 214. The trial court’s findings of fact, credibility
evaluations, and inferences of fact should not be disturbed on appeal if they are
reasonable. Sistler v. Liberty Mut. Ins. Co., 558 So.2d 1106 (La.1990).
3 Mr. Martin strongly argues that F. Miller’s bid is the only valid bid because it
includes all the repair work to be performed and Mr. Stark testified it would
construct a beautiful dock; therefore, it is the only bid the trial court should have
considered. This argument fails to acknowledge that not only did Mr. Boudreaux
testify B&J would have performed the work for the amount it originally quoted in its
bid, but Mr. Stark testified that F. Miller’s bid was high and not competitive,
explaining that F. Miller primarily performs commercial work and, more likely than
not, submitted the bid as a professional courtesy. Additionally, Mr. Boudreaux also
opined the bid was high.
This evidence shows the trial court’s determination that there was a problem
with each bid was reasonable and that its resolution of the problem of averaging the
bids was reasonable as well. Accordingly, we cannot reverse the trial court’s
calculation of Mr. Martin’s damages.
Did the trial court err in reducing damages by use of a linear depreciation factor?
The trial court reduced its repair-cost calculation as provided in Freeport, 526
F.2d 300, which provides that if repairs enhance or extend the useful service life of
the damaged property, the damage award is reduced or depreciated to the extent that
the useful service life of the property was extended. The trial court concluded the
dock and dolphin had ten years useful service life remaining which the repairs would
extend an additional twenty-five years. As provided in Freeman, the trial court
determined a depreciation factor of 71% had to be applied to its repair-cost
calculation. Application of this factor to the repair costs of $105,098 resulted in the
trial court’s award of $30,478.42 as the cost to restore Mr. Martin’s property to its
pre-collision condition.
Mr. Martin urges the trial court erred in applying a linear depreciation factor
where the evidence shows that the property was not deteriorating at a linear rate.
He cites Pillsbury Co. v. Midland Enters., Inc., 715 F.Supp. 738 (E.D. La. 1989),
4 aff’d and remanded, 904 F.2d 317 (5th Cir. 1990), cert. denied, 498 U.S. 983, 111
S.Ct. 515 (1990), as support for this argument. Mr. Martin is correct that
straight-line depreciation is not applicable in all instances, but he has not shown it is
not applicable here.
Mr. Stark testified the dock and dolphin were at least thirty years old and had
exceeded its useful service life. As argued by Mr. Martin, Capt. Brown was of the
opinion that before the allision, the dock and dolphin had ten years useful service life
remaining, which is what the trial court found. Capt. Brown did not, however, give
an opinion as the age of the dock or dolphin. The only evidence other than
Mr. Stark’s and Capt. Brown’s opinions on this issue is more than thirty
photographs of the dock and dolphin that were introduced into evidence. The
photographs do not show that the trial court’s apparent acceptance of Mr. Stark’s
opinion over Capt. Brown’s opinion is clearly wrong. Accordingly, we cannot
disturb this conclusion.
Did the trial court err in not awarding damages for the cost of removing steel pilings of a mooring dolphin?
Mr. Martin next argues the trial court erred in not awarding damages for
removal of the dolphin pilings. He urges that Mr. Stark’s testimony was unreliable
because it showed his inspections of the dock and the dolphin were merely cursory
as compared to Capt. Brown’s inspections which were much more in depth.
Capt. Brown testified that he ―neglected‖ to include costs for removing and
replacing the dolphin pilings because he ―assumed that the dolphin had been laid
over‖ and was not broken at the mud line. Referencing Mr. Stark’s survey, counsel
for Mr. Martin asked if Mr. Stark ―suggested that perhaps the dolphin did break at
the mud line.‖ Capt. Brown agreed that it did, and counsel continued, ―If that was
true . . . what impact would that have on the cost of repairing?‖ Capt. Brown
responded, ―That would increase it significantly,‖ and explained that he performed a
5 ―tapping‖ test on the one of the piles which led him to conclude, ―there is -- it’s fair
-- reasonable to expect that -- that pipe was broken.‖ He then explained that any
piles that extended above the mud should be removed because they presented
potential liability to the plaintiff. Capt. Brown reviewed what removal of the
pilings would entail and estimated the cost would be approximately $100,000.00.
The trial court did not address Mr. Martin’s claim for the cost of removing
pilings; therefore, it is presumed the claim was denied. M.J. Farms, Ltd. v. Exxon
Mobil Corp., 07-2371 (La. 7/1/08), 998 So.2d 16. Having considered the testimony
of Mr. Stark and Capt. Brown, we find no error with the trial court’s rejection of this
claim. Although Mr. Stark’s stated in his survey ―the dolphin was apparently
broken at the mud line,‖ he and Capt. Brown both testified that without removing the
dolphin from the water they could not determine if the pilings were broken or if there
were pilings that were submerged in the mud that needed to be removed.
(Emphasis added.) Importantly, Capt. Brown testified that the tapping test he
performed led him to ―reasonably expect‖ the pilings were broken; however, he did
not call for removal and replacement of the pilings in his survey. Moreover,
Capt. Brown acknowledged that in cases such as this, it is customary for
landowner’s to pay for the removal or excavation of damaged structures to
determine the extent of damage, if any, caused by the allision. For these reasons,
the trial court could have reasonably concluded that Mr. Martin did not prove the
pilings of the dolphin were broken and needed to be replaced, and its conclusion is
not manifestly erroneous.
Did the trial court err in awarding damages in the amount of $30,478.42 when the evidence and law mandate an award in excess of $200,000.00?
Resolution of the prior assignments of error pretermits the need to address
this assignment of error.
6 DISPOSITION
The judgment of the trial court is affirmed. All costs of this appeal are
assessed to Bill Burns Martin.
This opinion is NOT DESIGNATED FOR PUBLICATION. Uniform Rules—Courts of Appeal, Rule 2–16.3.
7 STATE OF LOUISIANA
COURT OF APPEAL, THIRD CIRCUIT
BILLS BURNS MARTIN
SAUNDERS, Judge, dissents and assigns written reasons.
I disagree with the majority that the trial court did not err in reducing
damages by use of a linear depreciation factor. In Pillsbury Co. v. Midland
Enters., Inc., 715 F.Supp. 738, 765, cited by the majority, the United States District
Court for the Eastern District of Louisiana, after an extensive review of accounting
principles, concluded:
While a linear, or straight line, depreciation method is most commonly used for property with a fixed life span, this method is not to be applied where evidence establishes that the original property had been deteriorating at a nonlinear rate. Similarly, if there is no evidence of any deterioration prior to the casualty, then no deduction is made for depreciation.
After a review of the evidence submitted, in my view Mr. Martin established
that his property had not been deteriorating at a nonlinear rate. Thus, I feel that the
trial court was erroneous in reducing his recovery for the damage done to his dock
and dolphin, and I disagree with the majority that Mr. Martin did not show that
such straight line depreciation is not applicable. The result reached by both the trial
court and majority fails to fully indemnify Mr. Martin for the damage done to his
property. Thus, I respectfully dissent.