Kansas City Power & Light Co. v. United States

Procedural entryThis page is a short order in Kansas City Power & Light Co. v. United States. Read the opinion of the Court — 131 Fed. Cl. 161
United States Court of Federal Claims·Decided December 13, 2018·No. 15-348·Published

Opinion

In the United States Court of Federal Claims No. 15-348C (Filed: December 13, 2018)

************************************* KANSAS CITY POWER & LIGHT CO., * * Plaintiff, * * Motion for Judgment on the Pleadings; v. * RCFC 12(c); RCFC 12(b)(6); * Indemnification; Duty to Defend THE UNITED STATES, * * Defendant. * *************************************

William L. Yocum, Kansas City, MO, and Roy Bash, Denver, CO, for plaintiff.

Amanda L. Tantum, United States Department of Justice, Washington, DC, for defendant.

OPINION AND ORDER

SWEENEY, Chief Judge

Plaintiff Kansas City Power & Light Co. (“KCP&L”) seeks reimbursement of its expenses associated with settling a wrongful death lawsuit. KCP&L alleges that it is entitled to recoup those costs from defendant because the United States General Services Administration (“GSA”) breached its contractual obligation to defend and indemnify KCP&L with respect to the settled claims. Currently before the court is defendant’s motion for judgment on the pleadings pursuant to Rule 12(c) of Rules of the United States Court of Federal Claims (“RCFC”).1 For the reasons discussed below, the court denies defendant’s motion.

1 In addition to seeking dismissal under RCFC 12(c), defendant nominally moves for partial summary judgment on KCP&L’s request for payment of its defense costs in the wrongful death lawsuit. Defendant, however, presents no argument premised on the summary judgment standard; instead, defendant frames its analysis under the RCFC 12(c) standard. The court, therefore, construes the “motion for partial summary judgment” as a request for dismissal under RCFC 12(c) and analyzes the issues accordingly. I. BACKGROUND

A. Contracted Services

On August 19, 2005, the GSA entered into a contract with KCP&L for the latter to deliver electric utility service to the Hardesty Federal Complex in Kansas City, Missouri.2 Pursuant to that agreement, KCP&L would supply electrical service to the GSA at the point of delivery from September 15, 2004, to September 14, 2009.3 In addition, the GSA agreed to indemnify KCP&L for activities related to its work supplying electrical service. Specifically, the GSA was obligated to

indemnify, save harmless and defend [KCP&L] against all claims, demands, cost or expense, for loss, damage or injury to persons or property, in any manner directly or indirectly connected with, or growing out of the distribution or use of the electric service by the [GSA] at or on the [GSA]’s side of the point of delivery.

Compl. Ex. 6 at 21. KCP&L alleges that, pursuant to this contract, it provided the GSA with electrical service to, among other places, Building 13—an electrical vault in the Hardesty Federal Complex.

B. Underlying Litigation

While KCP&L was providing electrical service to the Hardesty Federal Complex, David Eubank—a GSA employee—sustained fatal injuries in Building 13. He suffered those injuries as he was, allegedly, working with equipment related to electrical service on the GSA’s side of the point of delivery. Following Mr. Eubank’s death, his widow (the “Eubank claimant”) filed a

2 The facts in Part I are derived from the (1) complaint and its exhibits in this case; (2) complaint in the underlying wrongful death case, Eubank v. Kansas City Power & Light Co., No. 0716-CV07429 (Mo. Cir. Ct.); and (3) orders in the state and federal iterations of the Eubank case, id.; Eubank v. Kansas City Power & Light Co., No. 07-0861-CV-W-GAF (W.D. Mo.). See Rocky Mountain Helium, LLC v. United States, 841 F.3d 1320, 1325-26 (Fed. Cir. 2016) (explaining what records can be considered when evaluating a motion to dismiss); Pucciariello v. United States, 116 Fed. Cl. 390, 401 (2014) (noting that the contents of a complaint in another case can be reviewed without converting a motion to dismiss into a motion for summary judgment); see also A & D Auto Sales, Inc. v. United States, 748 F.3d 1142, 1147 (Fed. Cir. 2014) (reviewing the denial of a dismissal under RCFC 12(b)(6) and noting that the court may review of “matters incorporated by reference or integral to the claim, items subject to judicial notice, [and] matters of public record” (quoting 5C Charles Alan Wright & Arthur R. Miller, Federal Practice & Procedure § 1357 (3d ed. 2004))). 3 The “point of delivery” was defined as “[t]he point at which [KCP&L’s] conductors and/or equipment (other than [KCP&L’s] meter installation) make electrical connection with the [GSA’s] installation . . . .” Compl. Ex. 6 at 8.

-2- lawsuit in state court (the “Eubank action”) against KCP&L in which she pleaded negligence and loss-of-consortium claims stemming from the incident in Building 13.

After being served with the complaint, KCP&L brought two GSA employees into the proceeding as third-party defendants. The United States substituted itself for the GSA employees, and removed the case to federal court. Shortly thereafter, the United States was dismissed from the case. Subsequently, KCP&L alleges that it reached a settlement with the Eubank claimant after the GSA refused to defend KCP&L in the underlying proceeding. KCP&L alleges that it paid (1) $2,250,000.00 to the Eubank claimant as part of the settlement and (2) $1,756,138.14 in legal fees, court costs, and expenses (collectively, “litigation expenses”) to defend itself in the Eubank action.

C. Procedural History

On April 6, 2015, KCP&L filed its complaint in the instant case, seeking to recover what it paid in connection with the Eubank action.4 KCP&L pleads two claims: Count I - contractual indemnity and Count II - breach of contract. With regard to the contractual indemnity claim, KCP&L alleges that the GSA was obligated to indemnify KCP&L for its expenses in the Eubank action because the claims in that case were connected to the distribution of electrical service on the GSA’s side of the point of delivery. As for the breach-of-contract claim, KCP&L pleads that the GSA failed to comply with its contractual obligation to defend and indemnify KCP&L in the Eubank action. For each claim, KCP&L avers that it is entitled to recover the litigation expenses and settlement costs it incurred in resolving the Eubank claimant’s claims.

After KCP&L filed its complaint and the parties completed some discovery, defendant filed the instant motion for judgment on the pleadings. The motion is now fully briefed. The parties did not request oral argument, and the court deems oral argument unnecessary. Thus, defendant’s motion is now ripe for adjudication.

II. STANDARD

A motion for judgment on the pleadings “is designed to provide a means of disposing of cases when the material facts are not in dispute between the parties and a judgment on the merits can be achieved by focusing on the content of the competing pleadings . . . .” 5C Wright & Miller, supra, § 1367 (footnote omitted) (discussing Federal Rule of Civil Procedure 12(c)). The “legal standard applied to evaluate a motion for judgment on the pleadings is the same as that for a motion to dismiss.” Peterson v. United States, 68 Fed. Cl. 773, 776 (2005); see id. (noting that courts “have routinely construed a motion to dismiss for failure to state a claim filed after the answer as a motion for judgment on the pleadings”). Thus, judgment on the pleadings “is

4 KCP&L previously sued the United States in this court for claims arising from the Eubank action. The United States moved to dismiss that complaint, and the parties subsequently filed a joint stipulation of dismissal without prejudice because KCP&L had failed to exhaust its administrative remedies.

Free access — add to your briefcase to read the full text and ask questions with AI

Kansas City Power & Light Co. v. United States, (uscfc 2018).

Kansas City Power & Light Co. v. United States (Kansas City Power & Light Co. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Natco Ltd. Partnership v. Moran Towing of Florida, Inc.
267 F.3d 1190 (Eleventh Circuit, 2001)
United States v. Seckinger
397 U.S. 203 (Supreme Court, 1970)
Jenkins v. Fitzgerald Marine & Repair, Inc.
619 F.3d 851 (Eighth Circuit, 2010)
New Zealand Lamb Company, Inc. v. United States
40 F.3d 377 (Federal Circuit, 1994)
Nvt Technologies, Inc. v. United States
370 F.3d 1153 (Federal Circuit, 2004)
Rhoades v. United States
986 F. Supp. 859 (D. Delaware, 1997)
Metlife Capital Corp. v. Water Quality Insurance Syndicate
100 F. Supp. 2d 90 (D. Puerto Rico, 2000)
Pucciariello v. United States
116 Fed. Cl. 390 (Federal Claims, 2014)
Warren Drilling Co., Inc. v. Ace American Ins. Co.
621 F. App'x 800 (Sixth Circuit, 2015)
County of Obion v. Edwards
19 S.W.2d 236 (Tennessee Supreme Court, 1929)
Rocky Mountain Helium, LLC v. United States
841 F.3d 1320 (Federal Circuit, 2016)
J.M. Huber Corp. v. United States
27 Fed. Cl. 659 (Federal Claims, 1993)
Sweet v. United States
63 Fed. Cl. 591 (Federal Claims, 2005)
Peterson v. United States
68 Fed. Cl. 773 (Federal Claims, 2005)